What the committee will consider, in order, with every paper attached to its item.
In the event of a fire, please await direction from staff who will assist with the evacuation. Please do not return to the building until instructed to do so by the fire warden(s).
Members who consider that they have an interest to declare are asked to: a) State the item number in which they have an interest, b) The nature of the interest, c) Whether the interest is a disclosable pecuniary interest, non-disclosable pecuniary interest or non-pecuniary interest. Any Member who is unsure about the above should seek advice from the Monitoring Officer prior to the meeting in order to expedite...
To confirm the minutes of the meeting of the West of England Combined Authority Committee held on 18 January 2019 as a correct record.
Decision: RESOLVED : That the minutes of the meeting of the committee held on 18 January 2019 be confirmed as a correct record and signed by the Chair. Decision page
To receive any announcements from the Chair of the West of England Combined Authority Committee.
To receive any comments from the Chair of the Local Enterprise Partnership Board.
To receive any comments from the Chair of the WECA Overview and Scrutiny Committee.
If you wish to present a petition or make a statement at this meeting, you are required to submit this by 12 noon on the working day before the meeting by email to [email protected] For this meeting, this means that your petition/statement must be received in this office by 12 noon on Thursday 31 January 2019. If you wish to ask a question at the meeting, you are required to submit the...
Any member of the West of England Combined Authority may present a petition at a West of England Combined Authority Committee Meeting.
This report presents the forecast revenue and capital financial outturn budget monitoring information for WECA and the Mayoral budget for the financial year 2018/19 based on actual data for the period April – December 2018.
Decision: RESOLVED : 1. That the Mayoral Fund and WECA revenue and capital budget outturn forecasts as set out in Appendices 1, 2 and 3 be noted. 2. That a delegation be given to the WECA S151 Officer in order to make all necessary adjustments to Mayoral and WECA Budgets. Decision page
This report asks the committee to consider and approve the budget for the West of England Combined Authority Mayoral functions for 2019/20.
Decision: RESOLVED : 1. To formally note and ratify the Mayoral budget for 2019/20 together with the funding contribution from the WECA budget of £1.828m as set out in Appendix 1 – Table 1. 2. To formally note and ratify the specific Highways and Transport Capital Grant allocations totalling £17.572m to the constituent councils for 2019/20 as set out in Appendix 1 – Table 2. Decision page
This report asks the committee to consider and approve the 2019/20 Combined Authority budget.
Decision: RESOLVED to approve the following recommendations: 1. The following new drawdowns against the WECA Investment Fund: (a) £500k to develop a co-ordinated Transport Strategy and Policy resource; (b) £500k to continue to develop the Housing Infrastructure Fund bid; (c) £200k to progress mass-transit strategic development; (d) £200k to progress feasibility work for two bypass schemes ( Coalpit Heath/ Westerleigh bypass; and Frampton Cotterrell /Winterbourne bypass) (e) £300k to progress feasibility... Decision page
The report seeks approval for identified feasibility and development and delivery funding, and for change requests for schemes within the current approved programme.
Decision: RESOLVED : 1. To delegate approval of the revised West of England Assurance Framework to the WECA Chief Executive in consultation with the West of England Chief Executives . 2. To approve the scheme changes set out in Appendix 3. 3. To approve the Outline Business Case for the A4174/ Wraxall Road Roundabout Improvement and Signalisation scheme and award a further £1.488m of funding to develop a Full Business Case. 4. To approve a £100,000 increase to the current development funding award to... Decision page
This report presents the Capital Strategy for the Combined Authority including the Treasury Management and Investment Strategies.
Decision: RESOLVED : To approve: 1. The Capital Budget as shown in Appendices 1 and 2. 2. The proposed method of prioritising capital investment over the next 20 years. 3. The Treasury Management Strategy for 2019/20 detailed in Appendix 3. 4. The Investment Strategy for 2019/20 as shown in Appendix 4. Decision page
This report updates members on and seeks approval for the next steps of the Mass Transit study work and Bath transport study work.
Decision: RESOLVED : 1. To endorse the approach for the development of the Mass Transit and Bath Transport Study work. 2. To delegate the development and agreement of the Strategic Outline Business Case preparation scope to the WECA Director of Infrastructure in consultation with the relevant Directors of the constituent authorities. 3. To allocate a sum of £200k from the WECA investment fund, subject to the completion and approval of a Feasibility and Development Funding Application. Decision page
This report updates this committee on this bid and seeks additional resource to enable continued work on the schemes once the bid has been submitted to meet the delivery programme.
Decision: RESOLVED : 1. That it be acknowledged that the submission of this HIF bid will be undertaken in consultation with the Mayors/Leaders and Chief Executives of WECA, Bristol and B&NES and will be on the basis of : A bid that includes all schemes for a flagship JSP intervention from Bristol Temple Meads to Keynsham along the A4/A37 corridor. Recognising the need to show visibly recycled funding that is generated from HIF funded schemes back into the HIF programme as a mandatory requirement of the... Decision page
This report proposes a procurement strategy for the Combined Authority and sets out the case for establishing a Professional Services Framework to secure support to assist the delivery of the WECA capital investment programme.
Decision: RESOLVED : 1. That approval be given to the WECA Procurement Strategy (Appendix A). 2. That approval be given to the principle of establishing a Professional Services Framework and to delegate authority to the Director of Infrastructure to commence the Supplier Questionnaire / Supplier Selection process. The outcome of / recommendations from the tender process will be brought to the committee for approval in May 2019. Decision page
This report provides an update on progress in delivering the WECA Business Plan for 2018/19.
Decision: RESOLVED : - That the update on delivery of the 2018/19 Business Plan be noted. Decision page
This report presents the 2019/20 WECA Business Plan for approval.
Decision: RESOLVED : - That the Business Plan for 2019/20 be approved. Decision page
Details of the decisions taken at this meeting and the draft minutes of this meeting will be published on the West of England Combined Authority website as soon as possible after the meeting.
All 19 papers in one list, with the item each belongs to, its size, and our copy of it. Download any paper from our archive once signed in; read and search it here with Pro.
Every England Combined Authority Committee meeting we have read, the dates it has set for the future, and each time those dates have changed.
Choose what you want to hear about. The preview is built from this committee's real papers and changes, so you can see what would have reached you.
West of England Combined Authority, England Combined Authority Committee
One alert, sent weekly, on titles and decisions.
Unlimited alerts the same day, searching every page.
Your team, with every match pushed into your own tools.
Every council's records in your own products and research.
Papers, decisions and date changes for the England Combined Authority Committee, and every other committee you follow, the day they appear.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.