That the following levels of funding be approved and included in the budget for 2015/2016, as detailed in Report No: CAB/SE/15/007: (1) Theatre Royal, Bury St Edmunds: £66,250 (a reduction of £5,000); (2) Smith’s Row Art Gallery, Bury St Edmunds: £25,000 (a reduction of £9,485); and (3) Victory Ground Sports Ground, Bury St Edmunds: £45,250 (a reduction of £2,500). That the following levels of funding be approved and included in the budget for 2015/2016, as detailed in Report No: CAB/SE/15/007: (1) Theatre Royal, Bury St Edmunds: £66,250 (a reduction of £5,000); (2) Smith’s Row Art Gallery, Bury St Edmunds: £25,000 (a reduction of £9,485); and (3) Victory Ground Sports Ground, Bury St Edmunds: £45,250 (a reduction of £2,500).
Word for word from the decision West Suffolk published for this meeting.Source: democracy.westsuffolk.gov.uk
Cabinet Title of Report: Grant Funding 2015/2016: Arts and Sports Revenue Support Grants Report No: CAB/SE/15/007 Report to and date: Cabinet 10 February 2015 Portfolio holder: Sarah Stamp Portfolio Holder for Leisure, Culture and Heritage Tel: 01284 769360 Email: [email protected] Lead officer: Liz Watts Director Tel: 01284 757252 Email: [email protected] Purpose of report: To approve the grant funding levels for key arts and sports facilities for 2015/2016. Recommendation: It is RECOMMENDED that Cabinet approves the following levels of funding to be included in the budget for 2015/2016, as detailed in Report No: CAB/SE/15/007:
(1) Theatre Royal, Bury St Edmunds: £66,250 (a reduction of £5,000);
(2) Smith’s Row Art Gallery, Bury St Edmunds: £25,000 (a reduction of £9,485); and
(3) Victory Ground Sports Ground, Bury St Edmunds: £45,250 (a reduction of £2,500). Key Decision: Is this a Key Decision and, if so, under which definition? (Check the appropriate Yes, it is a Key Decision - ☐ box and delete all those that do not apply.) No, it is not a Key Decision - ☒
Consultation: Smith’s Row Art Gallery, Theatre Royal, Victory Sports Ground, Grant Working Party Alternative option(s): Grant funding could be more or less than that set out in the recommendations.
CAB/SE/15/007 Implications: Are there any financial implications? Yes ☒ No ☐ If yes, please give details Annual savings for the council Are there any staffing implications? Yes ☐ No ☒ If yes, please give details Are there any ICT implications? If Yes ☐ No ☒ yes, please give details Are there any legal and/or policy Yes ☐ No ☒ implications? If yes, please give details Are there any equality implications? Yes ☐ No ☒ If yes, please give details Risk/opportunity assessment: (potential hazards or opportunities affecting corporate, service or project objectives) Risk area Inherent level of Controls Residual risk (after risk (before controls) controls) Reputational damage Medium Budget consultation Low to the council if the carried out in 2014 cuts are too high or confirmed the too low decisions taken are appropriate Arts/Sports Medium Discussions have Low organisations are no taken place with all longer sustainable organisations and with reduced funding none have indicated that they would no longer be sustainable. Ward(s) affected: All wards Background papers: Minute 9 of Grant Working Party meeting: 12 January 2015 Documents attached: None
CAB/SE/15/007 1. Key issues and reasons for recommendation(s)
1.1Arts Funding
1.1.1 The council has traditionally supported the art gallery (Smith’s Row) and the Theatre Royal with grant funding. They each play a different role within our community, and have varying degrees of accessibility amongst our residents. The council has suffered significant funding cuts over the last few years, and as our funding becomes tighter, the requirement to ensure we are getting value for money becomes even more of an imperative.
1.1.2 As of 1 April 2015, the Theatre Royal will no longer receive Arts Council England grant funding through its National Portfolio Organisations (NPO) funding stream. This is a significant reduction for the theatre, although they have undertaken considerable work in the last 12 months to prepare themselves for the cut. Recent discussions have taken place with the theatre to see whether there is more joint working that could be undertaken with The Apex, in order to generate further savings and/or increased income for both organisations. This work is ongoing, and in the light of the potential for closer working, it is proposed that a funding cut of £5,000 be made for 2015/2016, resulting in the grant being £66,250.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.