Eastern Relief Road, Bury St Edmunds: Update

Approved Executive 1 paper

St Edmundsbury Cabinet approved this item on Tuesday 24 February 2015. Below is the council's own wording, with the papers it was decided on.

Item47

Resolved

That the amendment and clarification of resolutions (1) and (2) at its meeting on 2 September 2014(minute 42 refers) in accordance with paragraphs 3.2 and 3.3 of Report No: CAB/SE/15/017, be approved. RECOMMENDED TO COUNCIL: That (1) subject to the approval of full Council and the satisfaction of the Section 151 and Monitoring Officers, a commitment be made to the full £4,528,871 million programme of works for the provision of electricity to serve Suffolk Business Park, including an immediate financial allocation of £356,186 currently due on 27 February 2015, as detailed in Section 3 of Report No: CAB/SE/15/017; (2) subject to the approval of full Council and the satisfaction of the Section 151 and Monitoring Officers, delegated authority be given to the Head of Planning and Growth in consultation with the Leader of the Council to enter into an agreement or agreements to be entered into by St Edmundsbury Borough Council (SEBC) and the developer/landowner to enable the development of Suffolk Business Park and Eastern Relief Road to enable SEBC to realise a return on its investment in line with the principles approved in the Medium Term Financial Strategy; and (3) Council be asked to approve the financial allocation of £150,000 towards the costs of specialist advice for this project from reserves.
Word for word from the decision West Suffolk published for this meeting. Source: democracy.westsuffolk.gov.uk

Follow this further

Built from West Suffolk's papers

What the report saysPro

Report to St Edmundsbury Cabinet

Cabinet Title of Report: Eastern Relief Road, Bury St Edmunds: Update Report No: CAB/SE/15/017 Report to and Cabinet (Special) 24 February 2015 date/s: Council 24 February 2015 Portfolio holder: Cllr John Griffiths Leader of the Council Tel: 01284 757001 Email: [email protected] Lead officer: Steven Wood Head of Planning and Growth Tel: 01284 757306 Email: [email protected] Purpose of report: To provide an update with regard to the Eastern Relief Road project since the last reports (Papers F97 and F120 refer) dated 2 and 23 September 2014 were presented to Cabinet and Council; to ask for authority to forward fund electricity costs up to £4.5m; to request delegated authority to enter into legal agreement(s); and to ask for authority to fund specialist advice of £150,000 in relation to the total project.

CAB.SE.15.017 Recommendations: It is RECOMMENDED that:

(1) subject to the approval of full Council and the satisfaction of the Section 151 and Monitoring Officers, a commitment be made to the full £4,528,871 million programme of works for the provision of electricity to serve Suffolk Business Park, including an immediate financial allocation of £356,186 currently due on 27 February 2015, as detailed in Section 3 of Report No: CAB/SE/15/017;

(2) Cabinet approves the amendment and clarification of resolutions (1) and (2) at its meeting on 2 September 2014(minute 42 refers) in accordance with paragraphs 3.2 and 3.3 of Report No: CAB/SE/15/017;

(3) subject to the approval of full Council and the satisfaction of the Section 151 and Monitoring Officers, delegated authority be given to the Head of Planning and Growth in consultation with the Leader of the Council to enter into an agreement or agreements to be entered into by St Edmundsbury Borough Council (SEBC) and the developer/landowner to enable the development of Suffolk Business Park and Eastern Relief Road to enable SEBC to realise a return on its investment in line with the principles approved in the Medium Term Financial Strategy; and

(4) Council be asked to approve the financial allocation of £150,000 towards the costs of specialist advice for this project from reserves.

Key Decision: Is this a Key Decision and, if so, under which definition? Yes, it is a Key Decision - ☐ (Check the appropriate No, it is not a Key Decision - ☐ box and delete all those that do not apply.) Key Decision in part, however, the majority of decisions require full Council approval.

CAB.SE.15.017 Consultation: The development of the Eastern Relief Road and Suffolk Business Park is a long established policy of SEBC. Most recently the Vision 2031 documents confirm the allocation of the residential, commercial and leisure/community uses along with the ERR and junction 45 of the A14 Trunk Road upgrade.

In June 2010 the Masterplan for the extension to Suffolk Business Park was adopted following the due consultation phase.

A series of meetings have also been held with Rougham Parish Council; Moreton Hall Residents’ Association; and local business representative organisations. Alternative option(s): Not to commission the electricity works would result in a delay to the programme such that electricity may not be available in time for the first occupiers of the school, residences or commercial land.

To delay the works would adversely affect the programme as above and may result in an increase in costs.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Eastern Relief Road, Bury St Edmunds: UpdateReport 274 KB DownloadRead as text

At this meeting

Whole meeting
46Suffolk Business Park Land AssemblyApproved
47Eastern Relief Road, Bury St Edmunds: UpdateThis decision

Who was there

6 of 8 attended
JG
Councillor John Griffiths MBELeader, present
SM
Councillor Sara Mildmay-White Health and CommunitiesDeputy Leader, present
T(
Councillor Terry (Terence) Clements Planning and RegulationCommittee Member, present
AP
Councillor Alaric Pugh Economic GrowthCommittee Member, present
S(
Councillor Sarah (Sarah-Anne) Stamp Leisure, Culture and HeritageCommittee Member, present
PS
Councillor Peter Stevens Waste and PropertyCommittee Member, present
RE
Councillor Robert EverittGuest, in attendance
DN
Councillor David NettletonGuest, in attendance

On this subject at West Suffolk

Search all
  1. Eastern Relief Road, Bury St Edmunds: UpdateThis decision
  2. Eastern Relief Road, Bury St Edmunds: UpdateAgreed

More from West Suffolk St Edmundsbury Cabinet

All decisions
MeetingDecisionOutcome
22 May 2018 Building Control ResourcingThat: (1) approval be given to increase the permanent establishment of the Building Control Service by one Full-Time ... Approved Open
22 May 2018 Annual Review and Appointment of Cabinet's Working Party, Joint Committees/Panels and Other GroupsThat: (1 ) the Grant Working Party continues to operate in accordance with its current Terms of Reference, as detaile... Noted Open
17 Apr 2018 Investing in the Regeneration of Bury St Edmunds Town Centre: 17-18 CornhillRECOMMENDED TO COUNCIL (24 April 2018): That: (1) the project objectives set out at paragraph 1.3.1 of Report No: CAB... Approved Open
27 Mar 2018 Recommendations of the Overview and Scrutiny Committee: 7 March 2018: West Suffolk Information FrameworkThat the West Suffolk Information Framework, attached as Appendix A to Report No: OAS/SE/18/008, be approved. That th... Approved Open
27 Mar 2018 Recommendations of the Overview and Scrutiny Committee: 7 March 2018: Lettings PolicyThat the revised Lettings Policy, attached at Appendix 1 to Report No: OAS/SE/18/005, be approved. That the revised L... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies