RECOMMENDED TO COUNCIL: That: (1) 11.38 acres of land be transferred to Suffolk County Council for the construction of a new upper school at Moreton Hall, Bury St Edmunds, as detailed in Section 1 of Report No: CAB/SE/15/022, for the sum of £193,460 subject to a 125 year lease back of the land forming part of the shared community sports provision and an accompanying dual use agreement, whilst ensuring the commercial advantage of the Council’s ransom strip is maintained; (2) a capital contribution of £1,366,460 be made to Suffolk County Council towards a shared community sports provision within the site made up of the balance of: (a) £813,000 capital allocation for Bury Town FC relocation; (b) £360,000 anticipated future s106 contributions for sporting facilities at Moreton Hall; (b) the capital receipt of £193,460 detailed in (1) above; and (3) delegated authority be given to the Head of Operations, in consultation with the Portfolio Holders for Waste and Property, and Leisure, Culture and Heritage, Chief Executive, s151 Officer and Monitoring Officer, to agree the terms of all legal agreements necessary to give effect to the above.
Word for word from the decision West Suffolk published for this meeting.Source: democracy.westsuffolk.gov.uk
Cabinet Title of Report: Transfer of Land to Suffolk County Council for New School at Moreton Hall, Bury St Edmunds Report No: CAB/SE/15/022 Report to and dates: Cabinet 24 March 2015 Special Council 25 March 2015 Portfolio holder: Peter Stevens Portfolio Holder for Waste and Property Tel: 01787 280284 Email: [email protected]; Portfolio holder: Sarah Stamp Portfolio Holder for Leisure, Culture and Heritage Tel: 01284 769360 Email: [email protected] Lead officer: Richard Combes Valuation and Estates Manager Tel: 01284 757361 Email: [email protected] Purpose of report: (1) To seek Cabinet and Council approval to transfer 11.38 acres of land to Suffolk County Council for the construction of a new upper school at Moreton Hall, which will serve all of Bury St Edmunds, for the sum of £193,460.
(2) To seek Cabinet and Council approval to make a capital contribution of £1,366,460 towards shared sports facilities within the site to be leased back to the Council and operated by Abbeycroft Leisure under a sub-lease with an operator’s agreement. Recommendations: It is RECOMMENDED that, subject to the approval of full Council:
(1) 11.38 acres of land be transferred to Suffolk County Council for the construction of a new upper school at Moreton Hall, Bury St Edmunds, as detailed in Section 1 of Report No: CAB/SE/15/022, for the sum of £193,460 subject to a 125 year lease back of the land
CAB/SE/15/022 forming part of the shared community sports provision and an accompanying dual use agreement, whilst ensuring the commercial advantage of the Council’s ransom strip is maintained;
(2) a capital contribution of £1,366,460 be made to Suffolk County Council towards a shared community sports provision within the site made up of the balance of:
(a) £813,000 capital allocation for Bury Town FC relocation;
(b) £360,000 anticipated future s106 contributions for sporting facilities at Moreton Hall;
(b) the capital receipt of £193,460 detailed in (1) above; and
(3) delegated authority be given to the Head of Operations, in consultation with the Portfolio Holders for Waste and Property, and Leisure, Culture and Heritage, Chief Executive, s151 Officer and Monitoring Officer, to agree the terms of all legal agreements necessary to give effect to the above.
Key Decision: Is this a Key Decision and, if so, under which definition? Yes, it is a Key Decision - ☐ (Check the appropriate box No, it is not a Key Decision - ☒ and delete all those that do not apply.) (as it is a decision of full Council) Consultation: Extensive discussions have taken place with Suffolk County Council (SCC) and the School Organisation Review (SOR) team within Children and Young People’s Services for the previous 18 months involving a shared site in this location at Moreton Hall. These discussions were initially with Community and FA Football provision and now with community leisure use. SCC has consulted the public on these proposals and will submit a planning application on 16 March 2015. Alternative option(s): To deliver the school within a constrained site further north, the terms for which could not originally be agreed with developers; or risk not delivering the new school in time for September 2016 and instead rely upon renovating an existing school site in the town centre. Implications:
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.