That:- 1. Taking into account the known risks outlined in Report No COU/FH/15/030, a capital budget of £537,500 be approved to the Council’s Capital Programme for 2015/2016 together with an additional revenue income budget of £53,750, in respect of an investment in the Council asset interest at the site at 227 London Road, Brandon; 2. Delegated Authority be given to the Council’s Head of Operations, Monitoring Officer and Section 151 Officers to finalise the necessary due diligence and lease arrangements with Omar Parks Homes Ltd as outlined in Report No COU/FH/15/030 and the Heads of Terms detailed in Paragraph 2.7; 3. The Council’s Section 151 Officer be authorised to make the necessary changes to the Council’s 2015/2016 prudential indicators as a result of Recommendation 1 (above); and 4. Taking into account the procurement process conducted by Omar Park Homes Ltd to date, as set out in the exempt Appendix A of Report No COU/FH/15/030, an exemption be approved to the Council’s Contract Procedure Rules to enable the Council to enter into a contractual relationship with the proposed contractor as named at the exempt Appendix A.
Word for word from the decision West Suffolk published for this meeting.Source: democracy.westsuffolk.gov.uk
Full Council Title of Report: Investing in our Commercial Asset Portfolio - Brandon Report No: COU/FH/15/030 Report to and Extraordinary Council 16 September 2015 date/s: Portfolio holders: Councillor James Waters Portfolio Holder for Planning and Growth Tel: [phone removed] Email: [email protected]
Councillor Stephen Edwards Portfolio Holder for Resources and Performance Tel: 01638 660518 Email: [email protected]
Lead officer: Rachael Mann Head of Resources and Performance Tel: 01638 719245 Email: [email protected]
Purpose of report: An opportunity has arisen for the Council to secure a new 15 year lease (9 year lease extension) with Omar Park Homes Ltd, for its premises at 227, London Road, Brandon. However, a significant investment is required at the Council owned site in order to secure the extended lease. This paper seeks members views on the potential for such an investment in the Councils commercial asset portfolio on the basis of an invest to earn initiative.
COU/FH/15/030 Recommendation: It is recommended that Council:
1. Taking into account the known risks outlined in the report, approve a capital budget of £537,500 to the Council’s Capital Programme for 2015/16 and an additional revenue income budget of £53,750, in respect of an investment in the Council Asset interest at the site at London Road, Brandon;
2. Delegate authority to the Council’s Head of Operations, Monitoring Officer and Section 151 Officer to finalise the necessary due diligence and lease arrangements with Omar Parks Homes Ltd as outlined in the report and the Heads of Terms detailed in Paragraph 2.7;
3. Agree for the Council’s Section 151 Officer to make the necessary changes to the Council’s 2015/16 prudential indicators as a result of recommendation (i); and
4. Taking into account the procurement process conducted by Omar Park Homes Ltd to date at Exempt Appendix A, approve an exemption to the Councils Contract Procedure Rules to enable the Council to enter into a contractual relationship with the proposed contractor named at Exempt Appendix A.
Key Decision: Is this a Key Decision and, if so, under which definition? (Check the appropriate Yes, it is a Key Decision - ☐ box and delete all those that do not apply.) No, it is not a Key Decision - ☒
The decisions made as a result of this report will usually be published within 48 hours and cannot be actioned until five clear working days of the publication of the decision have elapsed. This item is included on the Decisions Plan. Consultation: Planning
Alternative option(s): The Council could choose not to proceed with this project. However, it is likely that the Council will be missing the opportunity to enter into an extended lease to the site. Implications: Are there any financial implications? Yes ☒ No ☐ If yes, please give details As set out in the report Are there any staffing implications? Yes ☐ No ☒ If yes, please give details None
COU/FH/15/030 Are there any ICT implications? If Yes ☐ No ☒ yes, please give details None Are there any legal and/or policy Yes ☒ No ☐ implications? If yes, please give As set out in the report details Are there any equality implications? Yes ☐ No ☒ If yes, please give details None Risk/opportunity assessment: (potential hazards or opportunities affecting corporate, service or project objectives)
Risk area Inherent level of Controls Residual risk (after risk (before controls) controls) The investment in the Low The eight units are Low site is of a specialised self-contained units, nature and if Omar through individual Park Homes Ltd was shutters, away from to fail then the the main factory investment may not building. Discuss re- be realised through use with Economic re-let Development.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.