That the Masterplan for Western Way, as set out in Appendix A to Report No: SDW/SE/16/003, be adopted as non-statutory planning guidance. 2. Western Way, Bury St Edmunds Development Site, Phase II (PSVII) Approval was sought for the adoption of the revised Western Way, Bury St Edmunds Masterplan. Councillor Alaric Pugh, Portfolio Holder for Planning and Growth, drew relevant issues to the attention of Council, including that the original Public Service Village concept (now to be known as Western Way Development site) was approved and adopted by the Council in 2006. West Suffolk House was built as part of Phase 1. On 16 December 2014, Council had agreed to undertake initial work to formulate Phase II of the Public Service Village project. Funding was approved for the appointment of consultants to: (a) assist with the review of the adopted Masterplan; (b) provide project management support ; and (c) provide legal and property advice. As part of this initial stage, the commercial considerations were examined to establish whether the proposals contained in the revised masterplan for this project were financially feasible. The initial appraisal concluded that the most financially prudent option, if the ... view the full minutes text for item 142.
Word for word from the decision West Suffolk published for this meeting.Source: democracy.westsuffolk.gov.uk
Extraordinary Council Title of Report: Schedule of Referrals from Cabinet Report No: COU/SE/16/006 Report to and date: Extraordinary 19 April 2016 Council Documents attached: Exempt Appendix 1: Western Way, Bury St Edmunds Development Site, Phase II (PSV II) – commercially sensitive information
(A) Referrals from Cabinet: 29 March 2016
1. Western Way, Bury St Edmunds Masterplan (Revised)
Portfolio Holder: Cllr Alaric Pugh Report No: CAB/SE/16/016 (Sustainable Development Working Party Report No: SDW/SE/16/003) RECOMMENDED:
That the Masterplan for Western Way, as set out in Appendix A to Report No: SDW/SE/16/003, be adopted as non- statutory planning guidance.
1.1In December 2006, the Council adopted a Masterplan for phased development of land at Western Way as a Public Service Village. The first phase of that development has been completed with the construction of West Suffolk House and the car park at Olding Road. The Masterplan excluded the NHS Logistics site in Olding Road as it was in separate ownership and not available for redevelopment at that time.
1.2Recently, new owners of the NHS site expressed an interest in working with the Council and bringing forward their site for inclusion in the Masterplan. This opens up a new set of opportunities for the development of the area and has prompted a review of the adopted masterplan.
1.3A revised Masterplan has now been prepared taking full account of the opportunities offered by the inclusion of the NHS site. The opportunities
COU/SE/16/006 now available exceed what was originally required for the creation of a Public Service Village (PSV), so although the concept of a PSV remains, the Masterplan has been retitled the Western Way Masterplan (Appendix A to Report No. SDW/SE/16/003 -Appendices to the draft Western Way Masterplan document are available via the following link:http://www.westsuffolk.gov.uk/Council/Consultations/westernway.cfm).
1.4A formal consultation process was undertaken on the revised Masterplan. Details of all the replies, together with Officer comments and consequential changes to the Masterplan document were included in the Consultation Report attached as Appendix B to Report No: SDW/SE/16/003.
1.5Those responding to the Masterplan had been generally supportive of the document and its key aims. However, some important issues were raised, some of which had resulted in changes or clarification within the document. These key issues were:
Residents of Newmarket Road were concerned about the scale and impact of any multi-decked car park, particularly during the winter months when the deciduous tree belt is least effective. Concerns about traffic impact on the surrounding road network. A desire to see a common architectural design theme.
1.6The Sustainable Development Working Party and Cabinet support the content of the revised Masterplan. Particular attention has however, been drawn to the following issues, further details of which can be found in Cabinet Report No: CAB/SE/16/016:
(a) Sustainable Transport Initiatives; (b) Increased traffic generation and transport infrastructure; (c) Site Contamination; (d) Skatepark; and (e) Multi-decked car park.
1.7Subject to the approval of this revised Masterplan, the Chairman of the Sustainable Development Working Party has also requested for the Working Party to be provided with regular updates on the Delivery Plan for this project.
1.8The Cabinet and officers are satisfied that the Masterplan has been prepared in accordance with the Bury St Edmunds Vision 2031 Development Plan document and the Council’s Protocol for preparing Masterplans.
COU/SE/16/006 2. Western Way, Bury St Edmunds Development Site, Phase II (PSV II)
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.