That:- 1. The content of Report No CAB/FH/16/023 and its appendices be noted; 2. The progression of a project to deliver a West Suffolk Operational Hub (Option 4) be approved; 3. The preparation and submission of a detailed planning application for a West Suffolk Operational Hub on land at Hollow Road Farm, be approved; 4. Approval be given for a gross capital budget of £3.5m (after the St Edmundsbury Borough Council contribution) to the Council’s Capital Programme for 2016/2017, funded in line with Paragraphs 6.10 to 6.21 of Report No CAB/FH/16/023; and 5. The Council’s Section 151 Officer to make the necessary changes to the Council’s 2015/2016 prudential indicators as a result of Recommendation 4, above.
Word for word from the decision West Suffolk published for this meeting.Source: democracy.westsuffolk.gov.uk
Council Title of Report: Referral of Recommendations from Cabinet: 14 June 2016 – West Suffolk Operational Hub Report No: COU/FH/16/011 Report to and date: Council 29 June 2016 Documents attached: Appendix 1: Cabinet Report No: CAB/FH/16/023 – 14 June 2016
(A) Referral from Cabinet: 14 June 2016
1. West Suffolk Operational Hub
Portfolio Holder: Cllr Stephen Edwards Report No: CAB/FH/16/023
RECOMMENDED: That:- (1) the content of Report No: CAB/FH/16/023 and its Appendices be noted; (2) the progression of a project to deliver a West Suffolk Operational Hub (Option 4), be approved; (3) the preparation and submission of a detailed planning application for a West Suffolk Operational Hub on land at Hollow Road Farm, be approved; (4) approval be given for a gross capital budget of £12.7m (after the St Edmundsbury Borough Council contribution) to the Council’s Capital Programme for 2016/17, funded in line with paragraphs 6.10 to 6.21 of Report No: CAB/FH/16/023; and (5) the Council’s Section 151 Officer to make the necessary changes to the Council’s 2015/16 prudential indicators as a result of recommendation (4) above.
1.1On 14 June 2016, the Cabinet considered Report No: CAB/FH/16/023 during joint informal discussions with St Edmundsbury Borough Council’s Cabinet. For ease of reference, this report is attached as Appendix 1 to this report; however due to the number of pages contained in Appendices A, B and C to that report, these are not attached and are available to view online at the following links:
Appendix A: Consultation Report
Appendix B: (due to the size of Appendix B – this document has been split into three parts) Potential Options and Sites: Report and Appendices A, B and C only
Potential Options and Sites: Appendices D and E only
Potential Options and Sites: Appendices F, G, H and I only
Appendix C: Sustainability Assessment
Hard copies of these Appendices are available upon request.
1.2Upon consideration of the report and its recommendations, and given the significance and public interest in the item, the Cabinets agreed to waive their executive decision making powers and made all five recommendations contained in the report subject to full Council approval. This was formally resolved during each Cabinet’s separate formal meetings which were convened immediately following the joint informal discussions.
1.3Both St Edmundsbury Borough and Forest Heath District Councils’ Cabinets unanimously agreed to support the recommendations contained in Cabinet Report No: CAB/FH/16/023 (and for reference purposes those in St Edmundsbury Cabinet Report No: CAB/SE/16/024), and these are now recommended to both Councils for approval.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.