RECOMMENDED TO COUNCIL: (22 February 2017) That:- 1. The funding model, with estimated project budget and cash flow, as set out in Report No: CAB/FH/17/011 and its Appendix, be agreed and the Mildenhall Hub Project be approved to proceed to its planning and delivery stages. 2. A funding/partnership agreement with the project partners be prepared and signed by the Director, in consultation with the Leader and Portfolio Holder for Resources and Performance, on the basis set out in Section 6 of Appendix A to Report No: CAB/FH/17/011. 3. Cabinet be authorised to approve a separate business case for an investment of up to £4m in renewable energy provision in the Hub provided that this business case is in line with the Council’s Medium Term Financial Strategy. 4. The Council’s Section 151 Officer make the necessary changes to the Council’s prudential indicators as a result of recommendation 1. above.
Word for word from the decision West Suffolk published for this meeting.Source: democracy.westsuffolk.gov.uk
Report No: CAB/FH/17/011 Report to and Overview and 12 January 2017 dates: Scrutiny Committee Cabinet 14 February 2017 Council 22 February 2017 Portfolio holder: Councillor James Waters Leader of the Council Tel: [phone removed] Email: [email protected] Lead officer: Alex Wilson Director Tel: 01284 757695 Email: [email protected] Purpose of report: To present and update the Overview and Scrutiny Committee report of 12 January 2017 and present recommendations regarding the funding and delivery of the Mildenhall Hub Project, reflecting the outcome of the scrutiny process and further activity on the Project.
Recommendations: It is RECOMMENDED to Council that:
(1) the funding model, with estimated project budget and cash flow, set out in this report and its Appendix, be agreed and the Mildenhall Hub Project be approved to proceed to its planning and delivery stages;
(2) a funding/partnership agreement with the project partners be prepared and signed by the Director, in consultation with the Leader and Portfolio Holder for Resources and Performance, on the basis set out in Section 6 of Appendix A to this report;
CAB/FH/17/011 Recommendations (3) Cabinet be authorised to approve a (contd): separate business case for an investment of up to £4m in renewable energy provision in the Hub provided that this business case is in line with the Council’s Medium Term Financial Strategy; and
(4) The Council’s Section 151 Officer make the necessary changes to the Council’s prudential indicators as a result of recommendation (1). Consultation: The prior development of the Hub project has been based on public, partner and stakeholder consultation. Public consultation has also taken place in early 2017 before the submission of a planning application (which will entail its own consultation).
Councillors have been extensively involved in the decision-making process for the Hub (see background papers below). The Overview and Scrutiny Committee examined the project in January 2016 and January 2017 and this report reflects the outcome of the latter.
Alternative The 2014 Hub business case examined over 10 option(s): different options Implications of this report: Are there any financial Yes ☒ No ☐ implications? If yes, please give As outlined in report details Are there any staffing Yes ☐ No ☒ implications? If yes, please give Covered in wider project planning. details Are there any ICT implications? If Yes ☐ No ☒ yes, please give details Covered in wider project planning. Are there any legal and/or policy Yes ☒ No ☐ implications? If yes, please give As outlined in report details Are there any equality Yes ☐ No ☒ implications? If yes, please give Covered in wider project planning. details
CAB/FH/17/011 Risk/opportunity assessment: (potential hazards or opportunities affecting corporate, service or project Please note: this is not a risk assessment for objectives) the Hub project as a whole, but for the subject matter of this report only Risk area Inherent Controls Residual level of risk (after risk (before controls) controls) The Hub is unaffordable to Medium Properly evaluate likely costs Low FHDC and its taxpayers – (including borrowing costs), with either at the outset or due contingencies, and sources of to budget changes during funding through this report prior project delivery to adoption of a funding agreement and a final decision to proceed.
Report back to Members if initial procurement results in a cost which exceeds the agreed budget in this paper.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.