That:- 1. The assessment of a cinema and restaurant development for Newmarket, be supported, in principle. 2. A revenue budget facility of up to £50,000 be allocated and funded from the ‘Investing in our Growth Agenda’ Reserve, to enable detailed feasibility to be undertaken on preferred sites, to improve cost confidence and enable the preferred site to be identified. That:- 1. The assessment of a cinema and restaurant development for Newmarket, be supported, in principle. 2. A revenue budget facility of up to £50,000 be allocated and funded from the ‘Investing in our Growth Agenda’ Reserve, to enable detailed feasibility to be undertaken on preferred sites, to improve cost confidence and enable the preferred site to be identified.
Word for word from the decision West Suffolk published for this meeting.Source: democracy.westsuffolk.gov.uk
Cabinet Title of Report: Leisure Opportunities in Newmarket Report No: CAB/FH/17/031 Report to and date: Cabinet 20 June 2017 Portfolio holder: Councillor Lance Stanbury Portfolio Holder for Planning and Growth Tel: 01284757252 Email: [email protected] Lead officer: Jill Korwin Director Tel: 01284 757252 Email: [email protected] Purpose of report: Following on from the recommendations of the Forest Heath Retail and Leisure Study, to inform Councillors of the findings of the feasibility study undertaken into the proposed leisure opportunities in Newmarket town centre and outline feasibility undertaken at potential sites;
To request Cabinet to support the allocation of a budget facility of up to £50,000 to enable detailed feasibility to be undertaken to enable a preferred site to be selected. Recommendation: It is RECOMMENDED that:
1) Cabinet supports the assessment of a cinema and restaurant development in principle for Newmarket; and
2) Cabinet allocates a revenue budget facility of up to £50,000, funded from the ‘Investing in our growth agenda’ reserve, to enable detailed feasibility to be undertaken on preferred sites to improve cost confidence and enable the preferred site to be identified.
CAB/FH/17/031 Key Decision: Is this a Key Decision and, if so, under which definition? (Check the appropriate box and Yes, it is a Key Decision - ☐ delete all those that do not apply.) No, it is not a Key Decision - ☒
The decisions made as a result of this report will usually be published within 48 hours and cannot be actioned until five clear working days of the publication of the decision have elapsed. This item is included on the Decisions Plan. Consultation: Over a number of years there has been significant engagement with the public in regard to what they want to see in Newmarket. Retail studies commissioned by Forest Heath District Council in 2006, 2011 & 2016 have carried out household surveys and in each case the desire for a cinema has been consistent. In 2012/13 The Princes Foundation, through the Newmarket Vision, also noted the desire for and the benefits of introducing a cinema to Newmarket Town Centre (Appendix 1). Alternative option(s): Do not support progress feasibility studies leaving it to the market to bring forward a proposal; Implications: A site is developed that does offer such benefit to the Council, or is sited out of town impacting on town centre trade. Are there any financial implications? If Yes ☒ No ☐ yes, please give details Detailed within the body of this report Are there any staffing implications? If Yes ☒ No ☐ yes, please give details Detailed within the body of this report Are there any ICT implications? If yes, Yes ☐ No ☒ please give details No significant issues identified as a result of this report Are there any legal and/or policy Yes ☐ No ☒ implications? If yes, please give details Subject to site selection, existing leases may be impacted Are there any equality implications? If Yes ☐ No ☒ yes, please give details Equality Impact Assessment will be completed if the project proceeds beyond feasibility. Risk/opportunity assessment: (potential hazards or opportunities affecting corporate, service or project objectives) Risk area Inherent level of risk Controls Residual risk (after (before controls) controls) There are no current High Ensure that Medium planning submissions feasibility study is however there is a expedited to provide risk that a developer supporting evidence may propose an out towards a decision of town cinema – an on planning out of town submission
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.