Mildenhall Hub - Business Case for Investing in Renewable Energy Technologies (Report No: COU/FH/17/021)

Approved Committee 5 papers

Forest Heath Council approved this item on Wednesday 26 July 2017. Below is the council's own wording, with the papers it was decided on.

Item252

Resolved

That:- 1. The business case for an investment of up to £2m in renewable energy provision in the Mildenhall Hub, be approved; 2. The funding model, with estimated project budget and cash flow as set out in Report No COU/FH/17/021 and its Appendix 3, be agreed; 3. Further detailed assessment and procurement of the renewable energy provision on the basis of this report, be approved; and 4. The Council’s S151 Officer make the necessary changes to the Council’s prudential indicators as a result of Recommendation 1. above.
Word for word from the decision West Suffolk published for this meeting. Source: democracy.westsuffolk.gov.uk

Follow this further

Built from West Suffolk's papers

What the report saysPro

Report to Forest Heath Council

Council Title of Report: Mildenhall Hub – Business Case for Investing in Renewable Energy Technologies Report No: COU/FH/17/021 Council 26 July 2017 Portfolio holder: Councillor James Waters Leader Tel: [phone removed] Email: [email protected]

Lead officer: Peter Gudde Service Manager – Environmental Health Tel: 01284 757042 Email: [email protected]

Purpose of report: To finalise the business case for the Mildenhall Hub in relation to investing in renewable energy technologies should planning consent be granted, following earlier consideration of the principles by Overview & Scrutiny Committee and Cabinet in June 2017

Recommendation: It is recommended that:

1) The business case for an investment of up to £2m in renewable energy provision in the Mildenhall Hub be approved; 2) The funding model, with estimated project budget and cash flow, set out in this report and its Appendix 3, be agreed; 3) Further detailed assessment and procurement of the renewable energy provision on the basis of this report; and 4) The Council’s Section 151 Officer make the necessary changes to the Council’s prudential indicators as a result of Recommendation 1.

1 Consultation: The development of the Hub project has been based on public, partner and stakeholder consultation. The scheme is currently the subject of public consultation in respect of its planning application.

Councillors have been extensively involved in the decision-making process for the Hub (see background papers below). The Overview and Scrutiny Committee received updates on the main business case in February 2017 and on the business case for renewable energy in June 2017.

Cabinet approved the outline business case for renewable energy investment in June 2017.

Alternative option(s): (Subject to the Hub proceeding) to install conventional mechanical and engineering solutions to heat and power the new building. The business case will offer this option as the ‘base case’.

An enhancement to the option may allow heat to be exported to the existing Mildenhall College Academy Sixth Form Building. This will be subject to a separate report.

Implications of this report: Are there any financial implications? If Yes ☒ No ☐ yes, please give details Financial implications of investing in renewable energy for the hub project are outlined in report. Are there any staffing implications? If Yes ☐ No ☒ yes, please give details Covered in wider project planning. Are there any ICT implications? If yes, Yes ☐ No ☒ please give details Covered in wider project planning. Are there any legal and/or policy Yes ☒ No ☐ implications? If yes, please give details As outlined in report. Are there any equality implications? If Yes ☐ No ☒ yes, please give details Covered in wider project planning. Risk/opportunity assessment: Specific project risks which have been identified at this stage are set Please note: this is not a risk out in Appendix 1. These will be assessment for the Hub project as a fully assessed as part of the next whole, but for the subject matter of phase of the Royal Institute of this report only i.e. funding of British Architects (RIBA) Stage 4 renewable technologies. design.

Ward(s) affected: All Wards

2 Background papers:  Council Report February 2017 - (all background papers are to be Mildenhall Hub – Funding published on the website and a link  Overview & Scrutiny Report included) January 2017 - Mildenhall Hub – Funding  Mildenhall Hub – Investing in renewable energy technologies

Documents attached: Appendices: Appendix 1 – Risk Assessment summary Appendix 2: An explanation of the proposed heating and power technologies Appendix 3: Case studies Appendix 4: Indicative Cash Flow Projection Summary

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
COU.FH.17.021 Business Case Mildenhall Hub Heat and Power: Appendix 1Appendix 92 KB Download
PDF
COU.FH.17.021 Business Case Mildenhall Hub Heat and Power: Appendix 2Appendix 89 KB Download
PDF
COU.FH.17.021 Business Case Mildenhall Hub Heat and Power: Appendix 3Appendix 127 KB Download
PDF
COU.FH.17.021 Business Case Mildenhall Hub Heat and Power: Appendix 4Appendix 137 KB Download
PDF
Mildenhall Hub: Business Case for Investing in Renewable Energy Technologies (Report No: COU/FH/17/021)Report 380 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

17 of 26 attended
RA
Councillor Ruth AllenCommittee Member, apologies
MA
Councillor Michael AndersonCommittee Member, present
AA
Councillor Andrew ApplebyCommittee Member, absent
CB
Councillor Chris BarkerCommittee Member, present
JB
Councillor John BloodworthCommittee Member, present
DB
Councillor David BowmanCommittee Member, present
RB
Councillor Ruth Bowman J.P.Cabinet Member, present
RB
Councillor Rona BurtCommittee Member, present
LB
Councillor Louis BusuttilCommittee Member, present
SC
Councillor Simon ColeCommittee Member, present
RD
Councillor Roger DickerCommittee Member, present
AD
Councillor Andy DrummondCommittee Member, apologies

All 26 on the meeting page

On this subject at West Suffolk

Search all
  1. Mildenhall Hub - Business Case for Investing in Renewable Energy Technologies (Report No: COU/FH/17/021)This decision
  2. Planning Application DC/25/1798/FUL - Mildenhall Hub, Sheldrick Way, Mildenhall (Report No DEV/WS/26/009)Approved
  3. Recommendations of the Overview and Scrutiny Committee: 9 March 2023 - Mildenhall Hub post implementation reviewDecided
  4. Application DC/21/0537/P14JPA - Mildenhall Hub, Sheldrick Way, Mildenhall (Report No: DEV/WS/21/019)Approved
  5. Planning Application DC/19/0386/VAR - Mildenhall Hub, Sheldrick Way, Mildenhall (Report No: DEV/WS/19/031)Decided
  6. Planning Application DC/18/1489/VAR - Mildenhall Hub, Sheldrick Way, Mildenhall (Report No: DEV/FH/18/016)Agreed

More from West Suffolk Forest Heath Council

All decisions
MeetingDecisionOutcome
20 Mar 2019 Conferment of Honorary Freedom of the District: Nigel Antony RomanThat this Council, in recognition of the eminent services rendered by NIGEL ANTONY ROMAN for 40 years outstanding ser... Decided Open
20 Mar 2019 Referrals Report of Recommendations from Joint Executive (Cabinet) Committee (Report No: COU/FH/19/003)That the Treasury Management Report for 2018-2019 for the period 1 April to 31 December 2018, as detailed in Report N... Approved Open
20 Mar 2019 Recognising the History of Forest Heath District Council and Long Service Awards (Report No: COU/FH/19/004)That:- 1. Thanks be given to all who had contributed to the achievements of Forest Heath District Council since its f... Decided Open
20 Mar 2019 Vote of Thanks to the Retiring Chairman and Vice-ChairmanThat the Council, in recognising the most able and diligent manner in which the retiring Chairman, Councillor Brian H... Decided Open
19 Dec 2018 Referrals Report of Recommendations from Joint Executive (Cabinet) Committee (Report No: COU/FH/18/022)That the revised West Suffolk Gambling Act 2005: Statement of Policy for the period 2019 to 2022, as contained in App... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies