Agreed Executive 1 paper

St Edmundsbury Cabinet agreed this item on Tuesday 14 November 2017. Below is the council's own wording, with the papers it was decided on.

Item397

Resolved

That: (1) subject to the support of the Guildhall Feoffment Trust, and to fulfil the objectives of the 2013 Memorandum of Understanding (as reviewed in 2016), it be agreed that the Council applies to the Charity Commission seeking an amendment to Clause 4 of the scheme of 1894 in respect of the managing trustee role for the Guildhall and 79 Whiting Street, Bury St Edmunds. The said amendment if granted would allow, after the Guildhall reopens as an exhibition and heritage centre in 2018, a complete transfer of management responsibility for the two buildings and associated land to the Bury St Edmunds Heritage Trust Limited which has consented to and supports the application; and (2) a separate partnership agreement be prepared and signed with the Bury St Edmunds Heritage Trust, and any other applicable partners, in relation to the future management of the paintings in the Guildhall, Bury St Edmunds after the new exhibition and heritage centre opens. That: (1) subject to the support of the Guildhall Feoffment Trust, and to fulfil the objectives of the 2013 Memorandum of Understanding (as reviewed in 2016), it be agreed that the Council applies to the Charity Commission seeking an amendment to Clause 4 of the scheme of 1894 in respect of the managing trustee role for the Guildhall and 79 Whiting Street, Bury St Edmunds. The said amendment if granted would allow, after the Guildhall reopens as an exhibition and heritage centre in 2018, a complete transfer of management responsibility for the two buildings and associated land to the Bury St Edmunds Heritage Trust Limited which has consented to and supports the application; and (2) a separate partnership agreement be ... view the full minutes text for item 397.
Word for word from the decision West Suffolk published for this meeting. Source: democracy.westsuffolk.gov.uk

Follow this further

Built from West Suffolk's papers

What the report saysPro

Report to St Edmundsbury Cabinet

Cabinet Title of Report: Guildhall and 79 Whiting Street, Bury St Edmunds Report No: CAB/SE/17/060 Report to and date: Cabinet 14 November 2017 Portfolio holder: Cllr Joanna Rayner Portfolio Holder for Leisure and Culture Tel: [phone removed] Email: [email protected] Lead officer: Alex Wilson Director Tel: 01284 757695 Email: [email protected] Purpose of report: To update Cabinet on the project and agree actions to conclude the objectives of the original Memorandum of Understanding. Recommendation: It is RECOMMENDED that:

(1) subject to the support of the Guildhall Feoffment Trust, and to fulfil the objectives of the 2013 Memorandum of Understanding (as reviewed in 2016), the Council applies to the Charity Commission seeking an amendment to Clause 4 of the scheme of 1894 in respect of the managing trustee role for the Guildhall and 79 Whiting Street, Bury St Edmunds. The said amendment if granted would allow, after the Guildhall reopens as an exhibition and heritage centre in 2018, a complete transfer of management responsibility for the two buildings and associated land to the Bury St Edmunds Heritage Trust Limited which has consented to and supports the application; and

Continued over….

CAB/SE/17/060 (2) a separate partnership agreement be prepared and signed with the Bury St Edmunds Heritage Trust, and any other applicable partners, in relation to the future management of the paintings in the Guildhall, Bury St Edmunds after the new exhibition and heritage centre opens.

Key Decision: Is this a Key Decision and, if so, under which definition? (Check the appropriate Yes, it is a Key Decision - ☐ box and delete all those that do not apply.) No, it is not a Key Decision - ☒

The decisions made as a result of this report will usually be published within 48 hours and cannot be actioned until five clear working days of the publication of the decision have elapsed. This item is included on the Decisions Plan. Consultation:  Bury St Edmunds Heritage Trust, Guildhall Feoffment, Portfolio Holder.

Alternative option(s):  It has already been agreed to transfer the management of the properties to a third party as part of the project, and the options for doing that have been assessed by the Heritage Trust in consultation with its funders and partners, including the Council and Guildhall Feoffment. Consultation on the project itself is managed by the Trust.

Implications: Are there any financial implications? Yes ☒ No ☐ If yes, please give details  See paragraph 1.7 Are there any staffing implications? Yes ☐ No ☒ If yes, please give details Are there any ICT implications? If Yes ☐ No ☒ yes, please give details Are there any legal and/or policy Yes ☒ No ☐ implications? If yes, please give  Transfer of current role in details accordance with Charity Law Are there any equality implications? Yes ☐ No ☒ If yes, please give details Risk/opportunity assessment: (potential hazards or opportunities affecting corporate, service or project objectives) Risk area Inherent Controls Residual level of risk risk (after (before controls) controls) Community management Low Seek Cabinet approval to apply Low transfer not achieved as to the Commission for a transfer agreed at outset of project in good time.

CAB/SE/17/060 Role is transferred to an Low Project partners assess options Low inappropriate third party and seek advice, and ensure necessary governance is in place in receiving body. Charity Commission do not Low Seek legal advice and work in Low agree to transfer conjunction with partners to make a compliant application. Ward(s) affected: Principally Abbeygate (but indirectly all wards) Background papers: Cabinet reports: (all background papers are to be  D333 – 27 March 2013 published on the website and a link  CAB/SE/16/028 -14 June 2016 included) Documents attached: None

CAB/SE/17/060 1. Key issues and reasons for recommendations

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Guildhall and 79 Whiting Street, Bury St EdmundsReport 232 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

6 of 9 attended
JG
Councillor John Griffiths MBELeader, present
SM
Councillor Sara Mildmay-White HousingDeputy Leader, present
RE
Councillor Robert Everitt Families and CommunitiesCommittee Member, present
IH
Councillor Ian Houlder Resources and PerformanceCommittee Member, present
AP
Councillor Alaric Pugh Planning and GrowthCommittee Member, present
JR
Councillor Joanna Rayner Leisure and CultureCommittee Member, apologies
PS
Councillor Peter Stevens OperationsCommittee Member, present
MC
Councillor Mike ChesterGuest, in attendance
DH
Councillor Diane HindGuest, in attendance

On this subject at West Suffolk

Search all
  1. Guildhall and 79 Whiting Street, Bury St EdmundsThis decision
  2. Guildhall and 79 Whiting Street, Bury St Edmunds (Report No: CAB/JT/18/010)Decided

More from West Suffolk St Edmundsbury Cabinet

All decisions
MeetingDecisionOutcome
22 May 2018 Building Control ResourcingThat: (1) approval be given to increase the permanent establishment of the Building Control Service by one Full-Time ... Approved Open
22 May 2018 Annual Review and Appointment of Cabinet's Working Party, Joint Committees/Panels and Other GroupsThat: (1 ) the Grant Working Party continues to operate in accordance with its current Terms of Reference, as detaile... Noted Open
17 Apr 2018 Investing in the Regeneration of Bury St Edmunds Town Centre: 17-18 CornhillRECOMMENDED TO COUNCIL (24 April 2018): That: (1) the project objectives set out at paragraph 1.3.1 of Report No: CAB... Approved Open
27 Mar 2018 Recommendations of the Overview and Scrutiny Committee: 7 March 2018: West Suffolk Information FrameworkThat the West Suffolk Information Framework, attached as Appendix A to Report No: OAS/SE/18/008, be approved. That th... Approved Open
27 Mar 2018 Recommendations of the Overview and Scrutiny Committee: 7 March 2018: Lettings PolicyThat the revised Lettings Policy, attached at Appendix 1 to Report No: OAS/SE/18/005, be approved. That the revised L... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies