RECOMMENDED TO COUNCIL: (20 December 2017) That :- 1. Report No: CAB/FH/17/057 and its Appendices, be noted. 2. The allocation of an additional £589,000 to the Council’s Capital Programme, funded in line with paragraphs 5.14 - 5.17 of Report No: CAB/FH/17/057, be approved. 3. Subject to receiving a planning consent:- a) the Council’s option to procure land at Hollow Road Farm be exercised; b) With Suffolk County Council and St Edmundsbury Borough Council, a contract be entered into for the construction of the at Hollow Road Farm; and 4. It be agreed for the Council’s Section 151 Officer to make the necessary changes to the Council’s 2017/18 prudential indicators as a result of recommendation 2. above.
Word for word from the decision West Suffolk published for this meeting.Source: democracy.westsuffolk.gov.uk
Cabinet Title of Report: West Suffolk Operational Hub Report No: CAB/FH/17/057 Report to and Cabinet 12 December 2017 dates: Council 20 December 2017 Portfolio holder: Councillor David Bowman Portfolio Holder for Operations Tel: [phone removed] Email: [email protected] Lead officer: Mark Walsh Assistant Director (Operations) Tel: 01284 757300 Email: [email protected] Purpose of report: To update Members on project progress, seek approval to secure additional funding, exercise the Council’s option on land at Hollow Road Farm and enter into a construction contract. Recommendation: It is RECOMMENDED that, subject to the approval of Council, the Cabinet:
1. Notes this report and its appendices;
2. Approve the allocation of an additional £589,000 to council’s Capital Programme funded in line with paragraphs 5.14 - 5.17 of Report No: CAB/FH/17/000; and
3. Subject to receiving a planning consent:- a) Exercises the Council’s option to procure land at Hollow Road Farm; b) With Suffolk County Council and St Edmundsbury Borough Council, enters into a contract for the construction of the West Suffolk Operational Hub at Hollow Road Farm; and
4. Agrees for the Council’s Section 151 Officer to make the necessary changes to the Council’s 2017/18 prudential indicators as a result of recommendation 2 above.
CAB/FH/17/057 Key Decision: Is this a Key Decision and, if so, under which definition? (Check the appropriate Yes, it is a Key Decision - ☐ box and delete all those that do not apply.) No, it is not a Key Decision - ☒ As it is a decision of Council
The decisions made as a result of this report will usually be published within 48 hours and cannot be actioned until five clear working days of the publication of the decision have elapsed. This item is included on the Decisions Plan. Consultation: Two pre-application public consultations have taken place relating to these proposals on 06MAR15 to 20APR15 and 08JAN16 to 19FEB16. A third public consultation has taken place as part of the Development Control process to determine the planning application. Alternative option(s): Detailed in previous reports Implications: Are there any financial implications? Yes ☒ No ☐ If yes, please give details See report section 6 Are there any staffing implications? Yes ☒ No ☐ If yes, please give details See report paragraph 5.13 Are there any ICT implications? If Yes ☐ No ☒ yes, please give details Are there any legal and/or policy Yes ☒ No ☐ implications? If yes, please give Legally the project must comply details with planning law and guidelines and procurement must comply with EU Procurement Directives. Are there any equality implications? Yes ☐ No ☒ If yes, please give details Risk/opportunity assessment: (potential hazards or opportunities affecting corporate, service or project objectives) Risk area Inherent level of Controls Residual risk (after risk (before controls) controls) Once planning Medium Ensure planning Medium consent is granted, process is robust objectors seek a with supporting Judicial Review evidence. Legal leading to delay and advice and external additional costs support being sought at key stages. Delay in project Medium Delays to Medium programme results in programme to date additional cost, for have impacted. example, through Continue to monitor tender inflation and throughout the longer engagement of project lifecycle project consultants. Risk that the project Medium Keep Members fully Medium does not proceed or is informed of progress abandoned at some and risks. Continue later stage resulting to manage and
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.