That subject to successful negotiations: 1. A transfer of the freehold of from Suffolk County Council to Forest Heath District Council for the nominal sum of £1, be approved; 2. Forest Heath District Council operates Brandon Country Park consistent with the management of other parks in West Suffolk; 3. The estimated 2018/19 revenue budget position for the park outlined in paragraph 3.4 and Appendix 2 of Report No: CAB/FH/18/012 and the potential costs thereafter, be noted. That subject to successful negotiations: 1. A transfer of the freehold of from Suffolk County Council to Forest Heath District Council for the nominal sum of £1, be approved. 2. Forest Heath District Council operates Brandon Country Park consistent with the management of other parks in West Suffolk. 3. The estimated 2018/19 revenue budget position for the park outlined in paragraph 3.4 and Appendix 2 of Report No: CAB/FH/18/012 and the potential costs thereafter, be noted.
Word for word from the decision West Suffolk published for this meeting.Source: democracy.westsuffolk.gov.uk
Report No: CAB/FH/18/012 Report to and date: Cabinet 13 February 2018 Portfolio holders: Councillor Andy Drummond Portfolio Holder for Leisure & Culture Tel: 01638 751411 Email: [email protected]
Councillor David Bowman Portfolio Holder for Operations Tel: [phone removed] Email: [email protected] Lead officers: Mark Walsh Assistant Director (Operations) Tel: 01284 757300 Email: [email protected]
Damien Parker Service Manager (Operations) Tel: 01284 757090 Email: [email protected] Purpose of report: The purpose of this report is twofold:
(1) To consider a proposal from Suffolk County Council for Forest Heath District Council to acquire the freehold of Brandon Country Park.
(2) To obtain Member approval to proceed with the transfer based on the position negotiated with Suffolk County Council.
Recommendation: It is RECOMMENDED that, subject to successful negotiations:
(1) Members approve a transfer of the freehold of Brandon Country Park from Suffolk County Council to Forest Heath District Council for the nominal sum of £1;
CAB/FH/18/012 (2) Forest Heath District Council operates Brandon Country Park consistent with the management of other parks in West Suffolk;
(3) Members note the estimated 2018/19 revenue budget position for the park outlined in paragraph 3.4 and Appendix 2 of Report No: Cab/FH/18/012 and the potential costs thereafter; and
Key Decision: Is this a Key Decision and, if so, under which definition? (Check the appropriate Yes, it is a Key Decision - ☒ box and delete all those that do not apply.) No, it is not a Key Decision - ☐
(a) A key decision means an executive decision which, pending any further guidance from the Secretary of State, is likely to:
(ii) result in any new expenditure, income or savings of more than £50,000 in relation to the Council’s revenue budget or capital programme;
The decisions made as a result of this report will usually be published within 48 hours and cannot be actioned until five clear working days of the publication of the decision have elapsed. This item is included on the Decisions Plan. Consultation: Not at this stage Alternative option(s): Do nothing and let SCC try and find an alternative operator or close the facility. Implications: Are there any financial implications? Yes ☒ No ☐ If yes, please give details The council will need to review the revenue implications of running the facility beyond financial year 2018-19.
Are there any staffing implications? Yes ☒ No ☐ If yes, please give details Staff will TUPE to the council as outlined in the body of the report. Are there any ICT implications? If Yes ☒ No ☐ yes, please give details We will install ICT facilities in the engine/pump house to serve our staff working there. Are there any legal and/or policy Yes ☒ No ☐ implications? If yes, please give A legal transfer of asset is proposed details from SCC to FHDC. Are there any equality implications? Yes ☐ No ☒ If yes, please give details
CAB/FH/18/012 Risk/opportunity assessment: (potential hazards or opportunities affecting corporate, service or project objectives) Risk area Inherent level of Controls Residual risk (after risk (before controls) controls) Costs of running the Medium Financial modelling Low site exceed has been undertaken expectations based on actual cost data received from the current owners SCC Revenue generated at Medium Estimated revenue Low the site fails to meet based upon current amounts assumed actuals and potential and budgeted identified by our partners Verse and the car parks team Ward(s) affected: All Wards (but located in Brandon West) Background papers: N/A (all background papers are to be published on the website and a link included) Documents attached: (Please list any appendices.) Appendix 1 – Map of the park Appendix 2 – Draft budget for managing the site in 2018-19
CAB/FH/18/012 1. Background
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.