Joint Executive (Cabinet) Committee approved this item on Tuesday 4 September 2018. Below is the council's own wording, with the papers it was decided on.
RECOMMENDED TO FHDC COUNCIL: (26 September 2018) That:- 1. On the basis set out in the exempt Appendix to Report No: CAB/JT/18/027, the final cost plan for the Mildenhall Hub project (including renewables and health facilities) be approved, and contractor appointments be made, subject to it still achieving at least the net revenue position previously agreed in 2017; and 2. The Council’s Section 151 Officer make any necessary changes to the Council’s prudential indicators as a result of recommendation 1. above.
Word for word from the decision West Suffolk published for this meeting.Source: democracy.westsuffolk.gov.uk
Joint Executive (Cabinet) Committee Title of Report: Mildenhall Hub Report No: CAB/JT/18/027 Report to and Joint Executive 4 September 2018 dates: (Cabinet) Committee Forest Heath Council 26 September 2018 Portfolio Holder: Councillor James Waters Leader of Forest Heath District Council Tel: [phone removed] Email: [email protected]
Lead officer: Alex Wilson Director Tel: 01284 757695 Email: [email protected]
Purpose of report: To review the financial model for the Mildenhall Hub project before completion of the procurement of the main construction contract in Autumn 2018.
Recommendation: It is RECOMMENDED to Council that:
(1) On the basis set out in the exempt Appendix to Report No: CAB/JT/18/027, the final cost plan for the Mildenhall Hub project (including renewables and health facilities) be approved, and contractor appointments be made, subject to it still achieving at least the net revenue position previously agreed in 2017; and
(2) The Council’s Section 151 Officer make any necessary changes to the Council’s prudential indicators as a result of recommendation (1) above.
CAB/JT/18/027 Key Decision: Is this a Key Decision and, if so, under which definition? Yes, it is a Key Decision - ☐ No, it is not a Key Decision - ☒
Consultation: The prior development of the Hub project has been based on public, partner and stakeholder consultation. Public consultation has also taken place in early 2017 before the submission of a planning application (which will entail its own consultation). Councillors have been extensively involved in the decision-making process for the Hub (see background papers below).
Alternative The 2014 Hub business case examined over 10 option(s): different options Implications of this report: Are there any financial Yes ☒ No ☐ implications? If yes, please give As outlined in report details Are there any staffing Yes ☐ No ☒ implications? If yes, please give Covered in wider project planning. details Are there any ICT implications? If Yes ☐ No ☒ yes, please give details Covered in wider project planning. Are there any legal and/or policy Yes ☒ No ☐ implications? If yes, please give Signing of contracts with contractors. details Are there any equality Yes ☐ No ☒ implications? If yes, please give Covered in wider project planning. details Risk/opportunity assessment: (potential hazards or opportunities affecting corporate, service or project Please note: this is not a risk assessment for objectives) the Hub project as a whole, but for the subject matter of this report only Risk area Inherent Controls Residual level of risk (after risk (before controls) controls) The Hub is unaffordable to Medium Properly review and evaluate Low FHDC and its taxpayers – likely costs (including borrowing either at the outset or due costs), with contingencies, and to budget changes during sources of funding through this project delivery report prior to award of contract.
Deliver project in accordance with the Council’s project and risk management processes, and maintain strong project governance. There is not a transparent Low Develop a funding agreement Low and fair means of dividing along the principles outlined in costs for the project this report. There are not safeguards to Low Ditto Low protect the interests of FHDC and the taxpayer
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Joint Executive (Cabinet) Committee at West Suffolk and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.