Recommendations of the Forest Heath and St Edmundsbury Performance and Audit Scrutiny Committees: 28 November 2018 - Approach to Delivering a Sustainable West Suffolk Budget 2019-2020 and Medium Term Plan (Report No: EXC/SA/19/001)
ApprovedExecutive1 paper
Shadow Executive (Cabinet) approved this item on Tuesday 8 January 2019. Below is the council's own wording, with the papers it was decided on.
RECOMMENDED TO SHADOW COUNCIL: (19 February 2019) : That, subject to the approval of Shadow Council as part of the budget setting process, the proposals detailed in Section 2 and Table 1 and Table 2 of Report Nos: PAS/SE/18/ 035 and PAS/FH/18/039, be included in securing a balanced budget for 2019/2020.
Word for word from the decision West Suffolk published for this meeting.Source: democracy.westsuffolk.gov.uk
Extraordinary Shadow Executive (Cabinet) Title of Report: Recommendations of the Forest Heath and St Edmundsbury Performance and Audit Scrutiny Committees: 28 November 2018 – Approach to Delivering a Sustainable West Suffolk Budget 2019-2020 and Medium Term Plan Report No: EXC/SA/19/001 Report to and Extraordinary dates: Shadow Executive 8 January 2019 (Cabinet) 19 February 2019 (as part of Shadow Council the budget setting process) Shadow Executive Stephen Edwards Ian Houlder Members/Portfolio FHDC Portfolio Holder SEBC Portfolio Holder for holders: for Resources and Resources and Performance Performance Tel: 01284 810074 Tel: 01799 530325 Email: Email: [email protected] Stephen.edwards@for est-heath.gov.uk Chairmen of the Louis Busuttil Sarah Broughton Committees: Chairman of FHDC Chairman of SEBC Performance and Performance and Audit Audit Scrutiny Scrutiny Committee Committee Tel: 01284 787327 Tel: 01638 810517 Email: Email: [email removed] louis.busuttil@forest- .uk heath.gov.uk
Extraordinary EXC/SA/19/001 Lead officer: Gregory Stevenson Service Manager (Finance and Performance) Tel: 01284 757264 Email: [email protected] Purpose of report: On 28 November 2018, the Performance and Audit Scrutiny Committees considered Report Nos: PAS/SE/18/035 / PAS/FH/18/039, which update members on progress made towards delivering a balanced budget for 2019/20 and sustainable budget in the medium term.
Recommendation: It is RECOMMENDED that, subject to the approval of Shadow Council as part of the budget setting process, the proposals detailed in Section 2 and Table 1 and Table 2 of Report Nos: PAS/SE/18/ 035 and PAS/FH/18/039, be included in securing a balanced budget for 2019/2020.
Key Decision: Is this a Key Decision and, if so, under which definition? (Check the appropriate Yes, it is a Key Decision - ☐ box and delete all those that do not apply.) No, it is not a Key Decision - ☒
Consultation: See Report Nos: PAS/SE/18/035 PAS/FH/18/039 Alternative option(s): • See Report Nos: : PAS/SE/18/035 PAS/FH/18/039 Implications: Are there any financial implications? Yes ☐ No ☐ If yes, please give details See Report Nos: : PAS/SE/18/035 PAS/FH/18/039 Are there any staffing implications? Yes ☐ No ☐ If yes, please give details See Report No: : PAS/SE/18/035 PAS/FH/18/039 Are there any ICT implications? If Yes ☐ No ☐ yes, please give details See Report No: : PAS/SE/18/035 PAS/FH/18/039 Are there any legal and/or policy Yes ☐ No ☐ implications? If yes, please give See Report No: : PAS/SE/18/035 details PAS/FH/18/039 Are there any equality implications? Yes ☐ No ☐ If yes, please give details See Report No: : PAS/SE/18/035 PAS/FH/18/039 Risk/opportunity assessment: (potential hazards or opportunities affecting corporate, service or project objectives) Risk area Inherent level of Controls Residual risk (after risk (before controls) controls) See Report Nos: PAS/SE/18/035 PAS/FH/18/039 Ward(s) affected: All Wards
Extraordinary EXC/SA/19/001 Background papers: Shadow Executive Agenda 17 July 2018 – Item 5: West Suffolk Council – Setting the Strategic Context for the Development of the 2019/2020 Budget and Medium Term Financial Plans
Informal Joint PASC – Approach to Delivering a Sustainable West Suffolk Budget 2019-2020 and Medium term Plan: PAS/FH/18/032 and PAS/SE/18/029
Documents attached: None
Extraordinary EXC/SA/19/001 1. Key issues and reasons for recommendation(s)
1.1It was reported at the 27 September 2018, Performance and Audit Scrutiny Committee meeting, that the budget position was a gap of £0.5m, and included the following set of adverse trends:
- The lower growth trend in car parking income as seen in 2018-2019 and anticipated to continue into 2019-2020. - The increased cost relating to recycling charge per tonne. - The estimated impact of revising the pay-line. - The new business case for Barley Homes.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Recommendations of the Forest Heath and St Edmundsbury Performance and Audit Scrutiny Committees: 28 November 2018: Approach to Delivering a Sustainable West Suffolk Budget 2019-2020 and Medium Term Plan (Report No: EXC/SA/19/001)Report
36Recommendations of the Forest Heath and St Edmundsbury Performance and Audit Scrutiny Committees: 28 November 2018 - Approach to Delivering a Sustainable West Suffolk Budget 2019-2020 and Medium Term Plan (Report No: EXC/SA/19/001)This decision
Recommendations of the Forest Heath and St Edmundsbury Performance and Audit Scrutiny Committees: 28 November 2018 - Approach to Delivering a Sustainable West Suffolk Budget 2019-2020 and Medium Term Plan (Report No: EXC/SA/19/001)This decision
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.