Haverhill Research Park and Suffolk Business Park Investment Fund

Agreed Executive 1 paper

Joint Executive (Cabinet) Committee agreed this item on Tuesday 26 February 2019. Below is the council's own wording, with the papers it was decided on.

Item112

Resolved

That:- 1. The business case to support a £7m loan, as set out in Report No: CAB/JT/19/007, for the development of business centres and associated works by way of loan(s) for Haverhill Research Park and Suffolk Park (Enterprise Zone) Bury St Edmunds be agreed. RECOMMENDED TO SEBC COUNCIL: (19 March 2019) That:- 2. A £7m investment facility for the development of business centres and associated works by way of loan(s) for Haverhill Research Park and Suffolk Park (Enterprise Zone) Bury St Edmunds be approved. 3. Subject to the satisfaction of the Section 151 Officer and the Monitoring Officer that appropriate security is in place to protect the Council’s investment and due diligence, highlighting no significant risks to the Council has been completed, delegated authority be given to the Chief Executive in consultation with the SEBC Portfolio Holder for Planning and Growth to enter into a loan agreement(s) with the developer. 4. The Council’s Section 151 Officer to make the necessary changes to the Council’s prudential indicators as a result of recommendation 2. above. That:- 1. The business case to support a £7m loan, as set out in Report No: CAB/JT/19/007, for the development of business centres and associated works by way of loan(s) for Haverhill Research Park and Suffolk Park (Enterprise Zone) Bury St Edmunds be agreed. and RECOMMENDED TO SEBC COUNCIL: (19 March 2019) That:- 2. A £7m investment facility for the development of business centres and associated works by way of loan(s) for Haverhill Research Park and Suffolk Park (Enterprise Zone) Bury St Edmunds be approved. 3. Subject to the satisfaction of the Section 151 Officer and the Monitoring Officer that appropriate security is in place to protect the Council’s investment and due diligence, highlighting no significant risks to the Council has been completed, delegated authority be given to the Chief Executive in consultation with the SEBC Portfolio Holder for Planning and Growth to enter into a loan agreement(s) with the developer. 4. The Council’s Section 151 Officer to make the necessary changes to the Council’s prudential indicators as a result of recommendation 2. above.
Word for word from the decision West Suffolk published for this meeting. Source: democracy.westsuffolk.gov.uk

Follow this further

Built from West Suffolk's papers

What the report saysPro

Report to Joint Executive (Cabinet) Committee

(Extraordinary) Joint Executive (Cabinet) Committee Title of Report: Haverhill Research Park and Suffolk Business Park Investment Fund Report No: CAB/JT/19/007 Report to and (Extraordinary) Joint dates: Executive (Cabinet) 26 February 2019 Committee SEBC Council 19 March 2019 Portfolio holder: SEBC Councillor Susan Glossop Portfolio Holder for Planning and Growth Tel: 01284 728377 Email: [email protected] Lead officer: Andrea Mayley Service Manager (Economic Development and Growth) Tel: 01284 757343 Email: [email protected] Purpose of report: This report seeks the Joint Executive (Cabinet) Committee’s support for a loan of up to £7m towards costs that will support growth on the Enterprise Zones at Haverhill Research Park and Suffolk Business Park, Bury St Edmunds. The benefits to the Council include creating more jobs, supporting the local economy, generating income from the commercial loan and enabling the Council to benefit from retained business rates on both sites.

As with any loan facility, there are risks to the funding body however, the Council follows a clear and robust process to mitigate these risks to ensure that the loan is protected.

Recommendations: It is RECOMMENDED that the Joint Executive (Cabinet) Committee:

(1) Agrees the business case to support a £7m loan, as set out in Report No: CAB/JT/19/007, for the development of business centres and associated works by way of loan(s) for Haverhill Research Park and Suffolk Park (Enterprise Zone) Bury St Edmunds; and

CAB/JT/19/007 RECOMMENDS to St Edmundsbury Borough Council:

(2) To approve a £7m investment facility for the development of business centres and associated works by way of loan(s) for Haverhill Research Park and Suffolk Park (Enterprise Zone) Bury St Edmunds; and

(3) Subject to the satisfaction of the Section 151 Officer and the Monitoring Officer that appropriate security is in place to protect the Council’s investment and due diligence, highlighting no significant risks to the Council has been completed, delegated authority be given to the Chief Executive in consultation with the SEBC Portfolio Holder for Planning and Growth to enter into a loan agreement(s) with the developer; and

(4) Agree for the Council’s Section 151 Officer to make the necessary changes to the Council’s prudential indicators as a result of recommendation (2) above.

Key Decision: Is this a Key Decision and, if so, under which definition? Yes, it is a Key Decision - ☐ (Check the appropriate box and delete all those No, it is not a Key Decision - ☒ that do not apply.) The decisions made as a result of this report will usually be published within 48 hours and cannot be actioned until five clear working days of the publication of the decision have elapsed. Consultation: With regard to this report and its recommendations, consultation has been undertaken with the developer/promoters, the landowners, the LEP’s, Combined Authority and advisors.

Alternative option(s): The alternative option is to not enter into a loan arrangement and require the match funding for the businesses centres to be funded privately. This option was discounted for three reasons:

 Private funding may not be forthcoming;  Private funding may take longer to secure resulting in a delay to the programme which would put the grant funding at risk; and  This option would mean that the Council would not generate income from interest payable on the loan. Implications: Are there any financial implications? Yes ☒ No ☐ If yes, please give details  As detailed in the report Are there any staffing implications? Yes ☐ No ☒ If yes, please give details

CAB/JT/19/007 Are there any ICT implications? If Yes ☐ No ☒ yes, please give details Are there any legal and/or policy Yes ☒ No ☐ implications? If yes, please give  As detailed in the report details Are there any equality implications? Yes ☐ No ☒ If yes, please give details

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Haverhill Research Park and Suffolk Business Park Investment FundReport 171 KB DownloadRead as text

At this meeting

Whole meeting
112Haverhill Research Park and Suffolk Business Park Investment FundThis decision

Who was there

13 of 15 attended
JG
Councillor John Griffiths MBECommittee Member (St Edmundsbury), apologies
JW
Councillor James WatersCommittee Member (Forest Heath), present
RM
Councillor Robin MillarCommittee Member (Forest Heath), present
DB
Councillor David BowmanCommittee Member (Forest Heath), present
RB
Councillor Ruth Bowman J.P.Committee Member (Forest Heath), present
AD
Councillor Andy DrummondCommittee Member (Forest Heath), present
SE
Councillor Stephen EdwardsCommittee Member (Forest Heath), present
LS
Councillor Lance StanburyCommittee Member (Forest Heath), present
SM
Councillor Sara Mildmay-WhiteCommittee Member (St Edmundsbury), present
CB
Councillor Carol BullCommittee Member (St Edmundsbury), present
RE
Councillor Robert EverittCommittee Member (St Edmundsbury), apologies
SG
Councillor Susan GlossopCommittee Member (St Edmundsbury), present

All 15 on the meeting page

On this subject at West Suffolk

Search all
  1. Haverhill Research Park and Suffolk Business Park Investment FundThis decision
  2. Haverhill Research ParkNoted

More from West Suffolk Joint Executive (Cabinet) Committee

All decisions
MeetingDecisionOutcome
12 Mar 2019 Report of the Forest Heath and St Edmundsbury (Informal Joint) Performance and Audit Scrutiny Committees: 31 January 2019 (Report No: CAB/JT/19/009)Decision. Councillor Sarah Broughton, Chairman of SEBC’s Performance and Audit Scrutiny Committee, drew relevant issu... Decided Open
12 Mar 2019 Recommendations of the Forest Heath Performance and Audit Scrutiny Committee: 31 January 2019 - Treasury Management Report 2018-2019 and Investment Activity (1 April - 31 December 2018) (Report No: CAB/JT/19/010)RECOMMENDED TO FHDC COUNCIL: (20 March 2019) That the Treasury Management Report for 2018-2019 for the period 1 April... Approved Open
12 Mar 2019 Recommendations of the St Edmundsbury Performance and Audit Scrutiny Committee: 31 January 2019 - Treasury Management Report 2018-2019 and Investment Activity (1 April - 31 December 2018) (Report No: CAB/JT/19/011)RECOMMENDED TO SEBC COUNCIL: (19 March 2019) That the Treasury Management Report for 2018-2019 for the period 1 April... Approved Open
12 Mar 2019 Recommendations of St Edmundsbury's Overview and Scrutiny Committee: 9 January 2019 - Public Space Protection Order, Bury St Edmunds - Addition of Condition (Report No: CAB/JT/19/012)That: (1) the addition of a new condition to the existing Public Space Protection Order (PSPO) for Bury St Edmunds to... Approved Open
12 Mar 2019 Hatchfield Farm, Newmarket: Masterplan (Report No: CAB/JT/19/013)That the masterplan for Hatchfield Farm, Newmarket, as contained in Appendix A to Report No: CAB/JT/19/013, be adopte... Approved Open