Newmarket Cinema and Restaurant Development: Outline Business Case (Report No: CAB/JT/19/018)
ApprovedExecutive1 paper
Joint Executive (Cabinet) Committee approved this item on Tuesday 12 March 2019. Below is the council's own wording, with the papers it was decided on.
RECOMMENDED TO FHDC COUNCIL: (20 March 2019) That: (1) the project objectives to continue to work towards bringing a cinema and restaurant development to the heart of Newmarket, be endorsed; (2) the Outline Business Case for the development of a 3 or 4 screen cinema, as contained in Exempt Appendix A to Report No: CAB/JT/19/018, be approved; (3) a budget of up to £190,000 be approved, funded by Strategic Priorities and MTFS reserve, to deliver the further design and study work as set out in paragraph 6.1 and Table 11 of the Outline Business Case; and (4) an additional £20,000 be approved, funded by Strategic Priorities and MTFS reserve, to undertake a condition and options review of the Guineas multi-storey car park.
Word for word from the decision West Suffolk published for this meeting.Source: democracy.westsuffolk.gov.uk
Joint Executive (Cabinet) Committee Title of Report: Newmarket Cinema and Restaurant Development: Outline Business Case Report No: CAB/JT/19/018 Report to and Joint Executive 12 March 2019 date/s: (Cabinet) Committee FHDC Council 20 March 2019 Portfolio holder: Councillor Lance Stanbury FHDC Portfolio Holder for Planning and Growth Tel: [phone removed] Email: [email protected] Lead officer: Jill Korwin Director Tel: 0128 757252 Email: [email protected] Purpose of report: To seek adoption of the Outline Business Case and a budget for the next stage of the project to enable detailed plans to be developed for a cinema development in Newmarket. Recommendation: It is RECOMMENDED that:
(1) Members endorse the project objectives to continue to work towards bringing a cinema and restaurant development to the heart of Newmarket;
(2) the Outline Business Case for the development of a 3 or 4 screen cinema, as contained in Exempt Appendix A to Report No: CAB/JT/19/018, be approved;
(3) a budget of up to £190,000 be approved, funded by Strategic Priorities and MTFS reserve, to deliver the further design and
CAB/JT/19/018 study work as set out in paragraph 6.1 and Table 11 of the Outline Business Case; and
(4) an additional £20,000 is approved, funded by Strategic Priorities and MTFS reserve, to undertake a condition and options review of the Guineas multi-storey car park.
Key Decision: Is this a Key Decision and, if so, under which definition? Yes, it is a Key Decision - ☐ (Check the appropriate box and delete all those No, it is not a Key Decision - ☒ that do not apply.) As it is a decision of full Council. The decisions made as a result of this report will usually be published within 48 hours and cannot be actioned until five clear working days of the publication of the decision have elapsed. This item is included on the Decisions Plan. Consultation: Initial consultation has been undertaken with Suffolk County Council Highways Department. Any planning application will be subject to a public consultation. Alternative option(s): Not to adopt the Outline Business Case and not progress any further work on the development of a cinema for Newmarket. Implications: Are there any financial implications? Yes ☒ No ☐ If yes, please give details As set out in the Outline Business Case and recommendations. At this stage the decision is to approve the budget for further plans and associated studies, not the final development Are there any staffing implications? Yes ☐ No ☒ If yes, please give details Are there any ICT implications? If Yes ☐ No ☒ yes, please give details Are there any legal and/or policy Yes ☒ No ☐ implications? If yes, please give As explained in the Outline Business details Case Are there any equality implications? Yes ☐ No ☒ If yes, please give details Risk/opportunity assessment: See section B of the Outline Business case Risk area Inherent level Controls Residual risk of risk (before (after controls) controls) 1. Decline in success of High Development of a Medium existing Newmarket cinema and restaurant town centre offer to increase footfall businesses and loss into the town centre to of income to Council protect its future from existing investments
CAB/JT/19/018 2. Financial case does High Explore value Medium improve as full engineering business case is opportunities/design developed refinement. Review car parking solutions. Review alternative funding options and delivery methods including seeking external funding.
3. Cost overrun at the High Agree a fixed price Low design stage contract with professional design teams/contractors. Produce realistic estimates from the outset that regularly monitored against the design.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Joint Executive (Cabinet) Committee at West Suffolk and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.