That the revised West Suffolk Statement of Licensing Policy 2022 to 2027, as contained in Appendix B to Report number: CAB/WS/22/060, be adopted. C. Referrals from Cabinet: 6 December 2022 Following the publication of the agenda and papers for this meeting, which took place before the Cabinet meeting was held on 6 December 2022, the Chair confirmed that no changes had been made to the recommendations contained in the referral report. 1. Delivering a Sustainable Medium Term Budget Approval was sought for proposals for inclusion in the medium-term financial plans. On 17 November 2022, the Performance and Audit Scrutiny Committee (PASC) considered proposals for delivering a sustainable balanced budget for 2023 to 2024 and for developing the medium-term plans. This included a number of key budget assumptions proposed and the rationale behind those assumptions, as set out in section 2 and Table 1 of Report number: PAS/WS/22/021. The recommendations, which had been endorsed by Cabinet on 6 December 2022, were now presented for approval by Council. These, together with any further recommendations emanating from PASC and Cabinet in the coming weeks, would be incorporated into the budget setting process, the composite report for which would ... view the full minutes text for item 258.
Word for word from the decision West Suffolk published for this meeting.Source: democracy.westsuffolk.gov.uk
Western Way Project Review - December 2022 Report number: CAB/WS/22/068 Report to and Cabinet 6 December 2022 date(s): Council 13 December 2022
Cabinet member: Councillor Joanna Rayner Portfolio Holder for Leisure, Culture and Community Hubs Tel: [phone removed] Email: [email protected]
Lead officer: Alex Wilson Strategic Director Tel: 01284 757695 Email: [email protected]
Decisions Plan: The decision made as a result of this report will usually be published within 48 hours. This item will be referred to Council for a final decision and is, therefore, not subject to call-in. This item is included on the Decisions Plan.
Wards impacted: All Wards
Recommendation: Subject to approval by Council, it is recommended that:
1. This review and update of the business case for the Western Way (WW) project, Bury St Edmunds and, as part of that wider scheme, the replacement of the Bury St Edmunds Leisure Centre, be approved so that Cabinet and officers Cabinet – 6 December 2022 – CAB/WS/22/068
can continue to deliver phase 1 of the project and any interim works to the rest of the site on the revised basis set out in this review and in accordance with the Council’s Constitution;
2. The existing authorities, financial provisions, safeguards and financial tests for delivery of the project be updated as follows:
(a) the remainder of the due diligence for the second stage of tendering be carried out in accordance with the two new gateways defined in Section E of this review;
(b) for either facility to be included in the phase 1 construction contract, Suffolk County Council must have entered into a formal pre- let agreement for an archive facility and/or pre-school which meets the One Public Estate principles of full cost recovery;
(c) the previous spending caps and financial tests for the hub and leisure centre be replaced by a new combined and reduced net capital expenditure limit of £65 million for the total phase 1 scheme defined in this report i.e. project costs, market analysis, enabling works, construction of the initial community hub, installation of renewables;
(d) in addition to this cap on expenditure, at the time the main construction contract is signed, the phase 1 scheme must not increase the Council’s existing MTFS provision of £724,000 for Bury St Edmunds Leisure Centre and, in relation to other ancillary elements of the new hub, be capable of achieving at least a break-even position over the whole life of the borrowing;
(e) in addition to the phase 1 scheme defined in the review, a further capital allocation of up to £10 million be made in the Council’s capital programme for interim works to the remainder of the Western Way site as defined in Appendix 3 of this report and also on the basis of at least a break-even income position over the life of the borrowing; Cabinet – 6 December 2022 – CAB/WS/22/068
(f) subject to consultation with the relevant portfolio holders, approval be given for interim or enabling works ahead of the main contract for phase 1, to be financed from within the new combined WW capital budget of £75m. But only where these works will increase the commercial value of the site irrespective of whether the WW project proceeds or not;
(g) the cash flow risk being managed;
(h) the most beneficial and economic funding method for the project is identified, including entering into agreements with third-party investors if required; and
(i) any phase 2 scheme for a permanent use of the remainder of the WW site be subject to a new and separate business case to councillors before the conclusion of the phase 1 construction programme. Cabinet – 6 December 2022 – CAB/WS/22/068
1. Context to this report 1.1 Please see attached review document and appendices.
2. Proposals within this report 2.1 Please see recommendations and attached review document and appendices.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Pay Policy Statement 2026 to 2027That the Pay Policy Statement for 2026 to 2027, as contained in Appendix A to Report number COU/WS/26/010, be approved.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.