Planning Advice Service Review: Proposed Improvements and Associated Fees

Agreed Executive 3 papers

AI summaryWest Suffolk Cabinet has agreed a new planning advice service with updated fees, to replace the current service that has not been reviewed since 2016. The changes recategorise development types and introduce bespoke packages for major housing schemes of 50 or more dwellings, with fees based on cost recovery.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeAgreed
MoneyNot specified in report text
What happens nextAnnual review
Who it affectsNot stated

What was decided

Cabinet agreed the new planning advice service as proposed in the report Report P9

Cabinet agreed the fee schedule for the new planning advice service as set out in Appendix B Report P9

Why

The current service was established in 2016 and has not had a substantive review since that time. The existing officer time assumptions for householder development are accurate but for other categories the time and expertise needed varies by scale of development, suggesting categories are too broad Report 1.2, 2.8, 2.9, 2.10

Developers and officers agreed that for complex major applications a single meeting or written response is rarely sufficient. The best outcomes come from bespoke arrangements with a programme of meetings, which is currently missing from the service Report 2.5, 2.6, 2.11

Benchmarking indicates current fees are below comparable offers from other Suffolk authorities and the Planning Advisory Service data, meaning the council is not adequately recovering costs Report 2.12, P51

What happens next

The new service and fees will be implemented following the decision, with the first annual review to follow Report 3.9, P6

The council will continue to work with developers through the existing developer forums and consider the approach across Suffolk authorities to bring West Suffolk into greater alignment Report 4.3, 4.4

Options considered

  • Chosen: Implement the new planning advice service with updated fees now. Maximises the ability to influence and improve larger developments, ensures appropriate cost recovery, and creates greater scope for meaningful engagement on larger schemes Report 5.3
  • Rejected: Wait until the next budget setting process to introduce the revised service. This would delay cost recovery improvements and miss the opportunity to encourage larger developments to engage through bespoke advice packages Report 4.2

Implications

  • Financial: The council must recover only the cost of providing the planning advice service rather than making a profit, as required by the Local Government Act. The revised categories and bespoke approach for larger sites will provide more accurate cost recovery Report 6.2, P51
  • Legal: National Planning Policy requires local planning authorities to work positively and proactively with applicants but does not require extensive negotiations or extensions of time to deal with poor quality submissions Report 1.4
  • Equalities: There are no known adverse equalities implications. Limited changes are proposed to the householder advice service which is accessed by members of the public
  • Risk: Continuing without the proposed changes risks work being undertaken without appropriate cost recovery, and missing the opportunity to engage larger developments in a more meaningful way Report P45, P46

Who and where

  • Residents and householders seeking planning advice on small-scale proposals Report 2.2, 2.3
  • Developers and agents working on minor and major housing schemes Report P29, 3.6
  • Local businesses and community groups requiring planning advice Report 6.5

Timeline

  • 2016: Current pre-application planning advice service was established as part of the Planning Improvement Plan Report 1.2
  • 2026-09-15: Cabinet agreed the new planning advice service and fee schedule Report P3
  • Annually after implementation: The advice service and fees will be reviewed to ensure they remain fit for purpose and continue to recover costs Report 3.9

Plain English for the jargon

  • Pre-application planning advice: Guidance provided by the council to developers, agents and residents before a formal planning application is submitted, to improve the quality of submissions and efficiency of the planning process
  • Bespoke packages: Tailored arrangements for large developments with a programme of meetings rather than a single written response or meeting
  • Householder development: Smaller scale development such as extensions, alterations or outbuildings to existing residential properties
  • Minor development: Development comprising 1 to 9 dwellings
  • Major development: Development comprising 10 or more dwellings
  • Cost recovery: Charging fees that cover the cost of providing the service without making a profit
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item12

Resolved

That: 1. The new planning advice service be agreed. 2. The fee schedule for the new planning advice service, as set out in Appendix B to Report number CAB/WS/26/042, be agreed.
Word for word from the decision West Suffolk published for this meeting. Source: democracy.westsuffolk.gov.uk

Follow this further

Built from West Suffolk's papers

What the report saysPro

Report to Cabinet

Cabinet – 15 September 2026 – CAB/WS/26/042

+

Planning advice service review: Proposed improvements and associated fees Report number: CAB/WS/26/042 Report to and date: Cabinet 15 September 2026

Cabinet member: Councillor Frank Stennett Portfolio Holder for Planning Email: [email protected]

Lead officer: Penny Mills Head of Service (Planning) Telephone: 01284 757367 Email: [email protected]

Decisions Plan: The decisions made as a result of this report will usually be published within 48 hours and cannot be actioned until five clear working days of the publication of the decision have elapsed. This item is included on the Decisions Plan.

Wards impacted: All Wards – District wide service.

Recommendation: It is recommended that Cabinet:

1. Note and agree the new planning advice service. 2. Agree the fee schedule for the new planning advice service. Cabinet – 15 September 2026 – CAB/WS/26/042

1. Context for the review 1.1 Pre-application planning advice can significantly improve the efficiency and effectiveness of the planning application process, improving the quality of development.

1.2West Suffolk offers a range of pre-application planning advice options with fees based on the nature of the advice sought and the type of development being proposed. The current offer was established in 2016 as part of the Planning Improvement Plan and there has been no substantive review of the service since that time.

1.3The Planning Service has been implementing targeted interventions to reduce delays, improve application quality, and enhance service delivery. This includes a firmer approach on determining applications that are fundamentally flawed, rather than entering lengthy discussions requiring extensions of time.

1.4National Planning Policy requires Local Planning Authorities to work positively and proactively to try and approve applications wherever possible. However, Local Planning Authorities are not required to enter extensive negotiations and extensions of time to deal with poor quality submissions. Rather it encourages early engagement and the use of pre- application discussions to resolve issues before an application is submitted.

1.5It is essential that West Suffolk offer’s a good planning advice service to provide an opportunity for negotiation and discussion with applicants, agents and developers to overcome issues and improve developments. As such, officers have undertaken a review of current service.

1.6The review sought to understand the current offer, and establish what is working well and what could work better to inform any changes. Officers have also reviewed the associated fees to ensure costs are being recovered.

1.7A new, revised planning advice service is proposed following the review with associated new fees. As a number of these fees involve an increase of over 5 per cent from the previous service, in accordance with the constitution the proposal is brought to Cabinet for a final decision.

2. Reviewing the current offer 2.1 West Suffolk’s pre-application planning advice service covers a wide variety of development projects from small householder developments to large scale housing schemes (attached at Appendix A). Cabinet – 15 September 2026 – CAB/WS/26/042

2.2Currently, for householder advice or advice on advertisements, it is possible to request a 30-minute meeting with an officer or a written response. This is a popular service which allows members of the public to seek the views of the Local Planning Authority on a proposal for a modest fee.

2.3No significant changes are proposed to this part the service as it works well and plays an important role in assisting and informing the public on their planning proposals.

2.4In terms of the service offered for other development types, the views of the developer community were sought through discussions at West Suffolk developer forums.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
CAB-WS-26-042-Appendix-A-Existing-Pre-Application-Advice-OfferAppendix 732 KB Download
PDF
CAB-WS-26-042-Appendix-B-Proposed-Pre-Application-Advice-Offer-and-Proposed-FeesAppendix 83 KB Download
PDF
Planning Advice Service Review: Proposed Improvements and Associated FeesReport 85 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

8 of 14 attended
CW
Councillor Cliff WatermanLeader, present
VL
Councillor Victor LukaniukDeputy Leader, present
DH
Councillor Donna Higgins (Portfolio Holder for Families and Communities)Committee Member, apologies
DH
Councillor Diane Hind (Portfolio Holder for Resources)Committee Member, present
GK
Councillor Gerald Kelly (Portfolio Holder for Environment and Regulatory)Committee Member, present
RO
Councillor Richard O'Driscoll (Portfolio Holder for Housing)Committee Member, present
IS
Councillor Ian Shipp (Portfolio Holder for Leisure and Culture)Committee Member, present
FS
Councillor Frank Stennett (Portfolio Holder for Planning)Committee Member, present
DT
Councillor David Taylor (Portfolio Holder for Operations)Committee Member, present
IW
Councillor Indy Wijenayaka (Portfolio Holder for Growth)Committee Member, apologies
PA
Councillor Peter ArmitageGuest, in attendance
SB
Councillor Sarah BroughtonGuest, in attendance

All 14 on the meeting page

On this subject at West Suffolk

Search all
  1. Planning Advice Service Review: Proposed Improvements and Associated FeesThis decision
  2. Introduction of Charging for a Pre-Application Advice Planning ServiceApproved
  3. Introduction of Charging for a Pre-Application Advice Planning ServiceApproved

More from West Suffolk Cabinet

All decisions
MeetingDecisionOutcome
15 Sep 2026 Recommendations of the Overview and Scrutiny Committee: 16 July 2026 - Transport and Infrastructure Task and Finish Group RecommendationsThat the approach, set out in Section 2 of Report number CAB/WS/26/038, to assist infrastructure planning and deliver... Approved Open
15 Sep 2026 Recommendations of the Performance and Audit Scrutiny Committee: 23 July 2026 - Treasury Management Report - June 2026Recommended to Council: (13 October 2026) That the Treasury Management Report (June 2026), as set out in Report Numbe... Approved Open
15 Sep 2026 Recommendations of the Performance and Audit Scrutiny Committee: 23 July 2026 - Annual Treasury Management and Financial Resilience Report (2025 to 2026)Recommended to Council: (13 October 2026) That the Annual Treasury Management and Financial Resilience Report 2025 to... Approved Open
15 Sep 2026 Public Space Protection Orders (PSPO): Review of Existing OrdersThat: 1. To continue with the existing Public Space Protection Orders (PSPOs) for Newmarket, Brandon and Moreton Hall... Agreed Open
15 Sep 2026 Commercial RecyclingThat: 1. The requirement for businesses and non-domestic organisations to implement the requirements of Simpler Recyc... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies