Gatwick Northern Runway - Approval of consultation response (CAB09_21/22)

Approved Executive 4 papers

Cabinet approved this item on Tuesday 16 November 2021. Below is the council's own wording, with the papers it was decided on.

Item28

Resolved

Following consideration of the report, Cabinet resolved : (a) to approve the comments in paragraphs 2.36-2.98 of the report and the detailed comments on the PEIR in Appendix C of the report as the County Council’s formal response to the consultation on the Northern Runway Project; (b) to authorise the Director of Highways, Transport and Planning to respond to any further stages of pre-submission consultation and to make minor or technical changes to the pre-submission in consultation with the Cabinet Member for Environment and Climate Change – in support of the formal response approved under (a); (c) if an application for a Development Consent Order is submitted, authorises the Director of Highways, Transport, and Planning to: (i) approve the County Council’s ‘adequacy of consultation’ response; (ii) prepare and submit the County Council’s written representation and Local Impact Report, and to negotiate with the applicant on the DCO requirements, any S106 Agreement, and the preparation of a Statement of Common Ground – all in support of the formal response approved under (a); and (iii) attend the examination hearings and answer the Examining Authority’s questions in support of the County Council’s position; and (d) if a Development Consent Order is made, approves the County Council becoming a relevant authority for the discharge of requirements, provided that the Authority’s costs are met in full. The call-in deadline is 25 November 2021. UPDATE – Wednesday 17 November 2021 Following approval by Cabinet, the Director of Highways, Transport and Planning, in consultation with the Cabinet Member for Environment and Climate Change, has made some minor changes to the Northern Runway Project report and to Appendix C (detailed comments on PEIR) for the reasons set out in the Schedule of Post-Cabinet Changes.
Word for word from the decision West Sussex published for this meeting. Source: westsussex.moderngov.co.uk

Follow this further

Built from West Sussex's papers

What the report saysPro

Report to Cabinet
This report is being read into text

Papers are read newest first, so recent reports come through within hours. Until then, open it at source.

Open the PDF

Papers for this item

Kept in our archive, download once signed in
PDF
Project Site BoundaryAppendix A 676 KB Copy on its way
PDF
Key Elements of the NRPAppendix B 587 KB Copy on its way
PDF
Detailed Comments on PEIRAppendix C 317 KB Copy on its way
PDF
Gatwick Northern Runway: Approval of consultation response (CAB09_21/22)Report 289 KB Withheld: personal details

At this meeting

Whole meeting

On this subject at West Sussex

Search all
  1. Gatwick Northern Runway - Approval of consultation response (CAB09_21/22)This decision
  2. Establishment of a Gatwick Airport Northern Runway Consultation Task and Finish GroupAgreed

More from West Sussex Cabinet

All decisions
MeetingDecisionOutcome
22 Oct 2025 Approval of Order for Establishing a Strategic Authority for Sussex - CAB06 (25/26)Following consideration of the report the Cabinet resolved: (1) To approve and consent to the establishment of the Su... Approved Open
8 Jul 2025 Performance and Resources Report - Quarter 4 2024/25 - CAB02 (25/26)Following consideration of the report the Cabinet resolved: (1) To note the Q4 Performance and Resources Report in An... Noted Open
8 Jul 2025 West Sussex Fire and Rescue Service Annual Statement of Assurance 2024-2025 - CAB03 (25/26)Following consideration of the report the Cabinet approved the West Sussex Fire and Rescue Service Annual Statement o... Approved Open
11 Mar 2025 Performance and Resources Report - Quarter 3 2024/25 CAB10 (24/25)Following consideration of the report the Cabinet agreed the allocation of £2.012m from the Contingency Budget to Ser... Agreed Open
11 Mar 2025 West Sussex Economic Strategy 2025-2035 CAB11 (24/25)Following consideration of the report the Cabinet agreed to adopt the West Sussex Economic Strategy 2025-2035. The ca... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies