Rail Station Legacy Projects - Final Accounts

Approved Committee 1 paper

Annual Meeting, West Yorkshire Combined Authority approved this item on Thursday 28 June 2018. Below is the council's own wording, with the papers it was decided on.

Item20

Resolved

(a) That the proposed final account and payment(s) with Network Rail for Kirkstall Forge and Apperley Bridge outlined in Appendix 2 and 3 to the submitted report be approved, subject to receipt in writing of Network Rail’s acceptance of the terms. (b) That the final account and payment(s) with Network Rail for LSSE outlined in Appendix 4 to the submitted report be approved, subject to receipt in writing of Network Rail’s acceptance of the terms. (c) That the current status of discussions with Network Rail on Low Moor and the potential budget implications be noted and that authority be delegated to the Managing Director, in conjunction with the Chair of the Combined Authority, to conclude final account discussions and make the relevant payment(s) within the funding approval detailed in Appendix 1 of the submitted report, subject to receipt in writing of Network Rail’s acceptance of the terms. (d) That the budget allocations and virements detailed in Appendix 1 of the submitted report be approved. (a) That the proposed final account and payment(s) with Network Rail for Kirkstall Forge and Apperley Bridge outlined in Appendix 2 and 3 to the submitted report be approved, subject to receipt in writing of Network Rail’s acceptance of the terms. (b) That the final account and payment(s) with Network Rail for LSSE outlined in Appendix 4 to the submitted report be approved, subject to receipt in writing of Network Rail’s acceptance of the terms. (c) That the current status of discussions with Network Rail on Low Moor and the potential budget implications be noted and that authority be delegated to the Managing Director, in conjunction with the Chair of the Combined Authority, to conclude final account discussions and make the relevant payment(s) within the funding approval detailed in Appendix 1 of the submitted report, subject to receipt in writing of Network Rail’s acceptance of the terms. (d) That the budget allocations and virements detailed in Appendix 1 of the submitted report be approved.
Word for word from the decision West Yorkshire Combined Authority published for this meeting. Source: westyorkshire.moderngov.co.uk

Follow this further

Built from West Yorkshire Combined Authority's papers

What the report saysPro

Report to Annual Meeting, West Yorkshire Combined Authority
This report is being read into text

Papers are read newest first, so recent reports come through within hours. Until then, open it at source.

Open the PDF

Papers for this item

Kept in our archive, download once signed in
PDF
Rail Station Legacy Projects: Final AccountsReport 111 KB Copy on its way

At this meeting

Whole meeting
1Membership of the West Yorkshire Combined AuthorityNoted 2Appointment of the Chair and Vice ChairDecided 5Exempt Information - Possible Exclusion of the Press and PublicDecided 6Minutes of the Meeting of the Combined Authority held on 10 May 2018Approved 8Committee Arrangements and AppointmentsNoted 9Representation on Outside BodiesDecided 10Governance ArrangementsApproved 11Corporate Governance Code and FrameworkApproved 12Members' Allowances SchemeApproved 13Officer Delegation SchemeApproved 14Calendar of Meetings 2018/19Agreed 15Capital Spending and Project ApprovalsApproved 15aLeeds integrated station masterplanApproved 15bNorthgate HouseApproved 15cReal Time Bus Information, LeedsApproved 15dUltra Low Emissions Vehicles (ULEV) taxi schemeApproved 15eHarrogate Road New Line – junction improvements on the Bradford/Leeds corridorApproved 15fA65-A658 airport link road projectApproved 16Further Capital Spend Proposals (following the 'Call for Projects')Approved 16aInstitute for High Speed RailwaysApproved 16bLeeds City Region Enterprise Zones ProgrammeApproved 16cLeeds Inland PortApproved 16dGateway to Huddersfield - Phase 1Approved 16eCityConnect Cycle City Ambition ProgrammeApproved 16fCity Centre heritage propertiesApproved 16gWakefield City Centre - South East GatewayApproved 16hRail Park & Ride Programme Phase 2Approved 16iLeeds City Centre Package (change request)Approved 17Corporate Planning and PerformanceNoted 18Corporate PrioritiesNoted 19Superfast Broadband West Yorkshire and YorkApproved
20Rail Station Legacy Projects - Final AccountsThis decision
21Draft minutes of the Green Economy Panel held on 17 April 2018Noted 22Minutes of the West Yorkshire and York Investment Committee held on 18 April 2018Noted 23Draft Minutes of the Land and Assets Panel held on 20 April 2018Noted 24Draft Minutes of the Business Innovation and Growth Panel held on 24 May 2018Noted 25Draft Minutes of the Transport Committee held on 25 May 2018Noted 26Draft Minutes of the Employment and Skills Panel held on 1 June 2018Noted 27Draft Minutes of the West Yorkshire and York Investment Committee held on 5 June 2018Noted

On this subject at West Yorkshire Combined Authority

Search all
  1. Rail Station Legacy Projects - Final AccountsThis decision
  2. White Rose Rail StationApproved
  3. 13d. (4) Huddersfield Rail Station ConnectionsApproved
  4. 13d (6). Harrogate Railway Station Gateway - Active Travel Improvement SchemeApproved
  5. 13d (7). TCF: Skipton Railway Station Gateway - Active Travel Improvement SchemeApproved
  6. Transforming Cities Fund: Harrogate Railway Station Gateway - Active Travel Improvement SchemeApproved

More from West Yorkshire Combined Authority Annual Meeting, West Yorkshire Combined Authority

All decisions
MeetingDecisionOutcome
22 Jun 2023 Membership of the West Yorkshire Combined AuthorityThat the Combined Authority noted: • the position of Mayor as Chair of the Combined Authority by virtue of that offic... Noted Open
22 Jun 2023 Minutes of the Meeting of the Combined Authority held on 25 May 2023That the minutes of the meeting of the West Yorkshire Combined Authority held on 25 May 2023 be approved and signed b... Approved Open
22 Jun 2023 Committee Arrangements and AppointmentsThat each of the following statutory committees with the terms of reference set out in the relevant appendix of the s... Noted Open
22 Jun 2023 Representation on Outside BodiesThat the appointments to the outside bodies for the municipal year 2023/24 as detailed in Appendix 1 of the submitted... Approved Open
22 Jun 2023 Officer ArrangementsThat Officer Delegation Scheme in relation to Non-Mayoral Functions attached as Appendix 1 to the submitted report be... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies