Resolved
That in respect of West Yorkshire Combined Authority Head Office Accommodation Project Investment Committee approves that: (a) The West Yorkshire Combined Authority Head Office Accommodation project proceeds through decision point 4 and work commences on activity 5 (full business case with finalised costs). (b) An indicative approval to the total project cost of £6.847 million is given. This will be funded entirely by the Combined Authority (from the approved budget for Corporate Projects), with full approval to spend being granted once the scheme has progressed through the assurance process to decision point 5 (full business case with finalised costs). (c) Future approvals are made in accordance with the assurance pathway and approval route set out in the submitted report following a recommendation by the Combined Authority’s Programme Appraisal Team. This will be subject to the scheme remaining within the tolerances outlined in the report.