West Yorkshire Combined Authority approved this item on Thursday 6 February 2020. Below is the council's own wording, with the papers it was decided on.

Item64b

Resolved

That following a recommendation from the Investment Committee, the Combined Authority approves: ( i ) That the Future Mobility Zone (FMZ) programme proceeds through Decision Point 2 and work commences on the development of business cases for individual packages (ii) That an indicative approval to £30.793 million, which will be funded from the Local Transport Plan (£2.75 million), the Leeds Public Transport Investment Programme (£0.763 million) and the Department for Transport FMZ fund (£27.28 million) is given with full approval to spend being granted as individual scheme or packages have progressed through the Assurance Process to Decision Point 5. The total programme cost is £32.01 million, including £1.22 million from District Partners. (iii) That an approval for development funding of £2.01 million be made to enable initial work on outline business cases for individual packages, subject to DfT funding being announced. (iv) That future programme approvals are made in accordance with the assurance pathway and approval route outlined in the submitted report including at Decision Point 6 and 7 through a delegation to the Combined Authority’s Managing Director following a recommendation by the Combined Authority’s Programme Appraisal Team. This will be subject to the scheme remaining within the tolerances outlined in the report. That following a recommendation from the Investment Committee, the Combined Authority approves: ( i ) That the Future Mobility Zone (FMZ) programme proceeds through Decision Point 2 and work commences on the development of business cases for individual packages (ii) That an indicative approval to £30.793 million, which will be funded from the Local Transport Plan (£2.75 million), the Leeds Public Transport Investment Programme (£0.763 million) and the Department for Transport FMZ fund (£27.28 million) is given with full approval to spend being granted as individual scheme or packages have progressed through the Assurance Process to Decision Point 5. The total programme cost is £32.01 million, including £1.22 million from District Partners. (iii) That an approval for development funding of £2.01 million be made to enable initial work on outline business cases for individual packages, subject to DfT funding being announced. (iv) That future programme approvals are made in accordance with the assurance pathway and approval route outlined in the submitted report including at Decision Point 6 and 7 through a delegation to the Combined Authority’s Managing Director following a recommendation by the Combined Authority’s Programme Appraisal Team. This will be subject to the scheme remaining within the tolerances outlined in the report.
Word for word from the decision West Yorkshire Combined Authority published for this meeting. Source: westyorkshire.moderngov.co.uk

Follow this further

Built from West Yorkshire Combined Authority's papers

Papers for this item

Kept in our archive, download once signed in

No papers were published with this item. The decision above is the council's full record of it.

At this meeting

Whole meeting

On this subject at West Yorkshire Combined Authority

Search all
  1. Leeds City Region Future Mobility ZoneThis decision
  2. BHF Leeds City Village Phase 1 (Leeds)Approved
  3. Leeds City Region Transport UpdateDecided
  4. Leeds City Region Transport updateDecided
  5. Getting Building Fund: Leeds City Centre 'Grey to Green'Approved
  6. Leeds City Region Employment HubApproved

More from West Yorkshire Combined Authority West Yorkshire Combined Authority

All decisions
MeetingDecisionOutcome
18 Sep 2025 Bus Franchising Update– That the Combined Authority: 1. Noted and endorsed the strategic approach to developing network service specificati... Noted Open
18 Sep 2025 Mass Transit Programme– That the Combined Authority: 1. Noted progress and the current position of the West Yorkshire Mass Transit programm... Noted Open
18 Sep 2025 West Yorkshire Local Nature Recovery Strategy– That the Combined Authority: 1. Noted the engagement and strategy development work undertaken in collaboration with... Noted Open
18 Sep 2025 West Yorkshire Local Remediation Acceleration Plan– That the Combined Authority: 1. Adopted the West Yorkshire Local Remediation Acceleration Plan as set out in Append... Approved Open
18 Sep 2025 Cluster Action Plans– That the Combined Authority: 1. Approved the six Cluster Action Plans developed to accelerate growth across West Yo... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies