Transport Committee, Friday 1 July 2022

Capital Spending and Project Approvals

Approved Committee 6 papers

Transport Committee approved this item on Friday 1 July 2022. Below is the council's own wording, with the papers it was decided on.

Item13

Resolved

With respect to the Corridor Improvement Programme – Wakefield A638 Doncaster Road, the Transport Committee approved that: ( i ) The A638 Doncaster Road Wakefield scheme proceeds through decision point 3 (outline business case) and work commences on activity 4 (full business case) (ii) An indicative approval to the Combined Authority’s contribution of £6,300,000. The total scheme value is £6,794,000. (iii) Development costs of £1,090,000 are approved in order to progress the scheme to decision point 4 (full business case), taking the total scheme approval to £1,650,000. (iv) The Combined Authority enters into an addendum to the existing funding agreement with Wakefield Council for expenditure of up to £1,650,000. (v) Future approvals are made in accordance with the assurance pathway and approval route outlined in this report. This will be subject to the scheme remaining within the tolerances outlined in this report. With respect to the Leeds City Centre Cycle Connectivity, the Transport Committee approved that: ( i ) The Leeds City Centre Cycle Connectivity Scheme (phase one) progresses through decision point 5 (full business case) and work commences on activity 5 (delivery) (ii) An indicative approval to the Combined Authority’s contribution of £7,262,173. The total scheme value (Phase 1 and 2) is £7,262,173. (iii) Approval to the Combined Authority’s contribution of £3,769,199 is given, taking the total scheme approval to £5,004,199. (iv) The Combined Authority enters a variation to the existing funding agreement with Leeds City Council for expenditure of up to £4,862,819. (v) Future approvals are made in accordance with the assurance pathway and approval route outlined in this report. This will be subject to the scheme remaining within the tolerances outlined in this report. With respect to the TCF – Leeds Station Sustainable Travel Gateway, The Transport Committee, subject to the conditions set by the Programme Appraisal Team, approved: ( i ) The TCF Leeds Station Sustainable Travel Gateway scheme proceeds through decision point 4 (FBC) and work commences on activity 5 (Delivery). (ii) Approval to the Combined Authority contribution of £25,673,833 is given, taking the total scheme approval to £36,009,872. The total scheme value is £36,009,872. (iii) The Combined Authority enters into a variation to the existing funding agreement with Leeds City Council for expenditure of up to £36,009,872. (iv) Future approvals are made in accordance with the assurance pathway and approval route outlined in this report. This will be subject to the scheme remaining within the tolerances outlined in this report. Conditions That Leeds City Council provides an Approval to Proceed report to the Combined Authority’s Programme Appraisal Team (PAT) to include discharge of the conditions outlined in the PAT Appraisal Report. With respect to Zero Emissions Bus Regional Area (Phase 1), the Transport Committee approved that, subject to the conditions set by PAT: ( i ) The Zero Emission Bus Regional Area (Phase 1) project proceeds through decision point 4 (full business case) and work commences on Activity 5 (delivery). (ii) Approval to the Combined Authority’s contribution of £24,565,171. The total scheme value ... With respect to the Corridor Improvement Programme – Wakefield A638 Doncaster Road, the Transport Committee approved that: ( i ) The A638 Doncaster Road Wakefield scheme proceeds through decision point 3 (outline business case) and work commences on activity 4 (full business case) (ii) An indicative approval ... view the full minutes text for item 13.
Word for word from the decision West Yorkshire Combined Authority published for this meeting. Source: westyorkshire.moderngov.co.uk

Follow this further

Built from West Yorkshire Combined Authority's papers

What the report saysPro

Report to Transport Committee
This report is being read into text

Papers are read newest first, so recent reports come through within hours. Until then, open it at source.

Open the PDF

Papers for this item

Kept in our archive, download once signed in
PDF
Capital Spending and Project ApprovalsReport 768 KB Copy on its way
PDF
Item 13: Appendix 1: Assurance FrameworkAppendix 211 KB Copy on its way
PDF
Item 13: Appendix 2: Corridor Improvement Programme Wakefield A638 Doncaster Road: Business Case SummaryAppendix 296 KB Copy on its way
PDF
Item 13: Appendix 3: Leeds City Centre Cycle Connectivity: Business Case SummaryAppendix 468 KB Copy on its way
PDF
Item 13: Appendix 4: TCF Leeds Station Sustainable Travel Gateway: Business Case SummaryAppendix 293 KB Copy on its way
PDF
Item 13: Appendix 5: Zero Emissions Bus Regional Area (Phase 1): Business Case SummaryAppendix 153 KB Copy on its way

At this meeting

Whole meeting

On this subject at West Yorkshire Combined Authority

Search all
  1. Capital Spending and Project ApprovalsThis decision
  2. Capital Spending and Project ApprovalsDecided
  3. Capital Spending and Project ApprovalsApproved
  4. Capital Spending and Project ApprovalsApproved
  5. Capital Spending and Project ApprovalsApproved
  6. Capital Spending and Project ApprovalsApproved

More from West Yorkshire Combined Authority Transport Committee

All decisions
MeetingDecisionOutcome
29 Jan 2026 Apologies for AbsenceApologies for absence were received from Councillors Scott Haslam (Transport Engagement Lead – Wakefield Council), Al... Decided Open
29 Jan 2026 Declaration of Disclosable Pecuniary InterestsThere were no declarations of pecuniary interests given at the meeting. Decided Open
29 Jan 2026 Exempt Information - Possible Exclusion of the Press and PublicThere were no agenda items present on the agenda which required the exclusion of the press and public. Decided Open
29 Jan 2026 Minutes of the meeting of the Transport Committee held on 29 October 2025RESOLVED :– The Committee approved the minutes of the meeting held on 29 October 2025 as a correct record. Approved Open
29 Jan 2026 Transport Operations - BusRESOLVED :– That the Committee: 1. Noted the contents of the submitted report. 2. Supported the decision to withdraw ... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies