Investment Priority 3: Creating Great Places and Accelerated Infrastructure

Approved Committee 3 papers

West Yorkshire Combined Authority approved this item on Thursday 2 February 2023. Below is the council's own wording, with the papers it was decided on.

Item11c

Resolved

With respect to the Capital Flood Risk Management Programme the Combined Authority approved that: (i) The Capital Flood Risk Management Programme proceeds through decision point 1 (strategic assessment) and work commences on the development of individual business cases. (ii) Development costs of £113,735 be approved taking the total scheme approval to £113,735. (iii) The principal that £10,000,000 of Combined Authority funding is utilised in order to engage and leverage funding from other funding sources and that work commences on the development of individual business cases, which will seek approval through the Assurance Framework. (iv) Approval of individual business cases through the Assurance Framework be delegated to the Place, Regeneration Housing Committee. (v) Future approvals are made in accordance with the assurance pathway and approval route outlined in this report and where required, any change requests for the Capital Flood Risk Management Programme are delegated to the Place, Regeneration and Housing Committee. This will be subject to the scheme remaining within the tolerances outlined in this report. With respect to the Leeds Flood Alleviation Scheme 2, the Combined Authority approved that: (i) The Leeds Flood Alleviation Scheme (Step 2) scheme proceeds through Decision Point 1 to 4 (business justification) and work continues on activity 5 (delivery), subject to assurances on a two outstanding questions from Government’s Department for Business, Energy, and Industrial Strategy (BEIS). (ii) The Combined Authority’s contribution of £12,565,000 be given. The total scheme cost is £125,826,000. (iii) The Combined Authority enters into a funding agreement with Leeds City Council for expenditure of up to £12,565,000. 246 (iv) Future approvals are made in accordance with the assurance pathway and approval route outlined in this report. This will be subject to the scheme remaining within tolerances outlined in this report. With respect to the Brownfield Housing Programme delegation for pipeline of schemes, the Combined Authority approved that: (i) The existing delegation, as approved by the Combined Authority in July 2021, to the then Director of Delivery to make changes to the pipeline of schemes in the Brownfield Housing Programme, be transferred to the Director of Policing, Environment and Place. With respect to BHF Armley Tower Works the Combined Authority approved that, subject to the conditions set by the Programme Appraisal Team: (i) The BHF Armley Tower Works scheme proceeds through decision point 2-4 (business justification) and work commences on activity 5 (delivery). (ii) The Combined Authority’s contribution of £932,775 be given. The estimated total scheme cost is £9,909,032. (iii) The Combined Authority enters into a funding agreement with Yorkshire Housing Ltd for expenditure of up to £932,775. (iv) Future approvals are made in accordance with the assurance pathway and approval route outlined in the original report. This will be subject to the scheme remaining within the tolerances outlined in the original report. With respect to BHF Galem House the Combined Authority approved that, subject to the conditions set by the Programme Appraisal Team: (i) The BHF Galem House scheme proceeds through decision point 4 (full business case) and work ...
Word for word from the decision West Yorkshire Combined Authority published for this meeting. Source: westyorkshire.moderngov.co.uk

Follow this further

Built from West Yorkshire Combined Authority's papers

What the report saysPro

Report to West Yorkshire Combined Authority
This report is being read into text

Papers are read newest first, so recent reports come through within hours. Until then, open it at source.

Open the PDF

Papers for this item

Kept in our archive, download once signed in
PDF
Investment Priority 3: Creating Great Places and Accelerated InfrastructureReport 266 KB Copy on its way
PDF
Item 11b_ Appendix 1_ Assurance FrameworkAppendix 221 KB Copy on its way
PDF
Item 11b_Appendix 2_Leeds FAS2 Business Case SummaryAppendix 2 MB Copy on its way

At this meeting

Whole meeting

On this subject at West Yorkshire Combined Authority

Search all
  1. Investment Priority 3: Creating Great Places and Accelerated InfrastructureThis decision
  2. Project Approvals - Investment Priority 1 (IP1) - Good Jobs and Resilient Businesses (Including Entrepreneurialism)Approved
  3. Project Approvals - Investment Priority 6 (IP6) - Creative Industries, Culture, Heritage and SportApproved
  4. 13b Local Nature Recovery Strategy Project Approvals - Investment Priority 3 - Creating Great Places and AcceleratedApproved
  5. Investment Priority 3: Creating Great Places and Accelerated InfrastructureApproved
  6. Investment Priority 5: Future TransportApproved

More from West Yorkshire Combined Authority West Yorkshire Combined Authority

All decisions
MeetingDecisionOutcome
18 Sep 2025 Bus Franchising Update– That the Combined Authority: 1. Noted and endorsed the strategic approach to developing network service specificati... Noted Open
18 Sep 2025 Mass Transit Programme– That the Combined Authority: 1. Noted progress and the current position of the West Yorkshire Mass Transit programm... Noted Open
18 Sep 2025 West Yorkshire Local Nature Recovery Strategy– That the Combined Authority: 1. Noted the engagement and strategy development work undertaken in collaboration with... Noted Open
18 Sep 2025 West Yorkshire Local Remediation Acceleration Plan– That the Combined Authority: 1. Adopted the West Yorkshire Local Remediation Acceleration Plan as set out in Append... Approved Open
18 Sep 2025 Cluster Action Plans– That the Combined Authority: 1. Approved the six Cluster Action Plans developed to accelerate growth across West Yo... Approved Open