Investment Priority 5: Future Transport

Approved Committee 2 papers

West Yorkshire Combined Authority approved this item on Thursday 16 March 2023. Below is the council's own wording, with the papers it was decided on.

Item85d

Resolved

The Combined Authority approved that: Castleford Growth Corridor The change request to the Castleford Growth Corridor scheme to increase the Combined Authority contribution funding to £11,519,000 and to increase the outputs as detailed in this report be approved. The total scheme value will increase from £9,491,000 to £11,740,000. The Combined Authority enters into a variation to the existing Funding Agreement with Wakefield Council for expenditure of up to £3,497,473. Future approvals be made in accordance with the assurance pathway and approval route outlined in this report. This will be subject to the scheme remaining within the tolerances outlined in this report. CRSTS Programme The Combined Authority, approved that: The change request to the CRSTS Programme to increase the approved programme development costs by £7,000,000 to £10,000,000 be approved, and delegation to the West Yorkshire Combined Authority’s Chief Operating Officer to authorise schemes access to these development costs, in accordance with the Assurance Framework be approved. The Combined Authority be authorised to enter into funding agreements between the Combined Authority and Districts for District led schemes for business case development for CRSTS led schemes. Where scheme approval is required before 30 June 2023, the schemes outlined in paragraph 3.5 be delegated for approval to the Transport Committee, due to expediency of delivery. Where scheme approval is required before 30 June 2023, the schemes outlined in paragraph 3.6 be delegated for approval to the Chief Executive, due to expediency of delivery. The Combined Authority approved that: Castleford Growth Corridor The change request to the Castleford Growth Corridor scheme to increase the Combined Authority contribution funding to £11,519,000 and to increase the outputs as detailed in this report be approved. The total scheme value will increase from £9,491,000 to £11,740,000. The Combined Authority enters into a variation to the existing Funding Agreement with Wakefield Council for expenditure of up to £3,497,473. Future approvals be made in accordance with the assurance pathway and approval route outlined in this report. This will be subject to the scheme remaining within the tolerances outlined in this report. CRSTS Programme The Combined Authority, approved that: The change request to the CRSTS Programme to increase the approved programme development costs by £7,000,000 to £10,000,000 be approved, and delegation to the West Yorkshire Combined Authority’s Chief Operating Officer to authorise schemes access to these development costs, in accordance with the Assurance Framework be approved. The Combined Authority be authorised to enter into funding agreements between the Combined Authority and Districts for District led schemes for business case development for CRSTS led schemes. Where scheme approval is required before 30 June 2023, the schemes outlined in paragraph 3.5 be delegated for approval to the Transport Committee, due to expediency of delivery. Where scheme approval is required before 30 June 2023, the schemes outlined in paragraph 3.6 be delegated for approval to the Chief Executive, due to expediency of delivery.
Word for word from the decision West Yorkshire Combined Authority published for this meeting. Source: westyorkshire.moderngov.co.uk

Follow this further

Built from West Yorkshire Combined Authority's papers

What the report saysPro

Report to West Yorkshire Combined Authority
This report is being read into text

Papers are read newest first, so recent reports come through within hours. Until then, open it at source.

Open the PDF

Papers for this item

Kept in our archive, download once signed in
PDF
Investment Priority 5: Future TransportReport 289 KB Copy on its way
PDF
Item 9d: Appendix 1: Assurance FrameworkAppendix 221 KB Copy on its way

At this meeting

Whole meeting

On this subject at West Yorkshire Combined Authority

Search all
  1. Investment Priority 5: Future TransportThis decision
  2. Project Approvals - Investment Priority 1 (IP1) - Good Jobs and Resilient Businesses (Including Entrepreneurialism)Approved
  3. Project Approvals - Investment Priority 6 (IP6) - Creative Industries, Culture, Heritage and SportApproved
  4. 13b Local Nature Recovery Strategy Project Approvals - Investment Priority 3 - Creating Great Places and AcceleratedApproved
  5. Investment Priority 3: Creating Great Places and Accelerated InfrastructureApproved
  6. Investment Priority 5: Future TransportApproved

More from West Yorkshire Combined Authority West Yorkshire Combined Authority

All decisions
MeetingDecisionOutcome
18 Sep 2025 Bus Franchising Update– That the Combined Authority: 1. Noted and endorsed the strategic approach to developing network service specificati... Noted Open
18 Sep 2025 Mass Transit Programme– That the Combined Authority: 1. Noted progress and the current position of the West Yorkshire Mass Transit programm... Noted Open
18 Sep 2025 West Yorkshire Local Nature Recovery Strategy– That the Combined Authority: 1. Noted the engagement and strategy development work undertaken in collaboration with... Noted Open
18 Sep 2025 West Yorkshire Local Remediation Acceleration Plan– That the Combined Authority: 1. Adopted the West Yorkshire Local Remediation Acceleration Plan as set out in Append... Approved Open
18 Sep 2025 Cluster Action Plans– That the Combined Authority: 1. Approved the six Cluster Action Plans developed to accelerate growth across West Yo... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies