Investment Priority 5: Delivering Sustainable, Inclusive and Affordable Transport

Approved Committee 5 papers

West Yorkshire Combined Authority approved this item on Thursday 27 July 2023. Below is the council's own wording, with the papers it was decided on.

Item28b

Resolved

With respect to Local Electric Vehicle Infrastructure (LEVI) Programme the Combined Authority approved that: i. The Local Electric Vehicle Infrastructure (LEVI) Programme proceed through decision point 2 (strategic outline case) and work commence on individual project business cases as outlined in the submitted report. ii. An indicative approval to the Combined Authority’s contribution of £17,142,000. The total programme value is between £20,642,000 and £32,642,000, dependent on leveraged private sector contributions. iii. Subject to the conditions set by the Programme Appraisal Team, approval to funding of £1,316,000 to progress the Local Electric Vehicle Infrastructure (LEVI) Capability Fund scheme to Activity 5 (Delivery). The total scheme costs are £1,316,000. iv. Indicative approval to funding of £1,500,000 for the Local Electric Vehicle Infrastructure (LEVI) Phase 1 Pilot scheme be given and work commence on Activity 4 (full business case). The total scheme costs are £3,000,000. v. Indicative approval to funding of £14,326,000 for the Local Electric Vehicle Infrastructure (LEVI) Phase 2 scheme be given and work commence on Activity 3 (outline business case). The total scheme costs are £16,326,000. vi. The following development costs be approved: • £354,953 for the Combined Authority for the LEVI Capability scheme • £ 961,047 for the five West Yorkshire partner local authorities for the LEVI Capability scheme • £120,000 for the Combined Authority for the Phase 1 LEVI Pilot scheme and the Phase 2 LEVI scheme vii. The Combined Authority enter into a funding agreement for the amounts set out below with each of the five partner councils for the capability fund: • City of Bradford Metropolitan District Council for expenditure of up to £184,480. • Calderdale Council for expenditure of up to £195,000. • Kirklees Council for expenditure of up to £188,631. • Leeds City Council for expenditure of up to £197,936. • Wakefield Council for expenditure of up to £195,000. viii. Future approvals be made in accordance with the assurance pathway and approval route outlined in the submitted report and where required, any change requests be delegated to the transport committee. This will be subject to the scheme remaining within the tolerances outlined in the submitted report. With respect to CRSTS Highways Asset Management and Enhancement Programme and Off Highway Walking and Cycling Network the Combined Authority approved that: i. The CRSTS Highways Asset Management and Enhancement Programme for the 2023/24 financial year (year 2) proceed through decision point 2 to 4 (strategic outline case) and delivery continue to end of 2023/24, and work commence on the strategic outline case for future years. ii. The CRSTS Off Highway Walking and Cycling Network Programme for the 2023/24 financial year (year 2) proceed through decision point 2 to 4 (strategic outline case) and delivery continue to end of 2023/24, and work commence on the strategic outline case for future years. iii. The Department for Transport’s Pothole Fund proceed through decision point 2 to 4 (strategic outline case) and into delivery. iv. An indicative approval be given to the total £248,000,000 for CRSTS Highways Asset Management CRSTS ...
Word for word from the decision West Yorkshire Combined Authority published for this meeting. Source: westyorkshire.moderngov.co.uk

Follow this further

Built from West Yorkshire Combined Authority's papers

What the report saysPro

Report to West Yorkshire Combined Authority
This report is being read into text

Papers are read newest first, so recent reports come through within hours. Until then, open it at source.

Open the PDF

Papers for this item

Kept in our archive, download once signed in
PDF
Investment Priority 5: Delivering Sustainable, Inclusive and Affordable TransportReport 655 KB Copy on its way
PDF
Item 8b: Appendix 1: IP5 Business Case Summary: Local Electric Vehicles Infrastructure SchemeAppendix 120 KB Copy on its way
PDF
Item 8b: Appendix 2: IP5 Business Case Summary: Highway Asset ManagementAppendix 71 KB Copy on its way
PDF
Item 8b: Appendix 3: IP5 Business Case Summary: Safer RoadsAppendix 83 KB Copy on its way
PDF
Item 8b: Appendix 4: IP5 Business Case Summary: Active Travel Fund 3: A660 Otley RoadAppendix 265 KB Copy on its way

At this meeting

Whole meeting

On this subject at West Yorkshire Combined Authority

Search all
  1. Investment Priority 5: Delivering Sustainable, Inclusive and Affordable TransportThis decision
  2. Project Approvals - Investment Priority 1 (IP1) - Good Jobs and Resilient Businesses (Including Entrepreneurialism)Approved
  3. Project Approvals - Investment Priority 6 (IP6) - Creative Industries, Culture, Heritage and SportApproved
  4. 13b Local Nature Recovery Strategy Project Approvals - Investment Priority 3 - Creating Great Places and AcceleratedApproved
  5. Investment Priority 3: Creating Great Places and Accelerated InfrastructureApproved
  6. Investment Priority 5: Future TransportApproved

More from West Yorkshire Combined Authority West Yorkshire Combined Authority

All decisions
MeetingDecisionOutcome
18 Sep 2025 Bus Franchising Update– That the Combined Authority: 1. Noted and endorsed the strategic approach to developing network service specificati... Noted Open
18 Sep 2025 Mass Transit Programme– That the Combined Authority: 1. Noted progress and the current position of the West Yorkshire Mass Transit programm... Noted Open
18 Sep 2025 West Yorkshire Local Nature Recovery Strategy– That the Combined Authority: 1. Noted the engagement and strategy development work undertaken in collaboration with... Noted Open
18 Sep 2025 West Yorkshire Local Remediation Acceleration Plan– That the Combined Authority: 1. Adopted the West Yorkshire Local Remediation Acceleration Plan as set out in Append... Approved Open
18 Sep 2025 Cluster Action Plans– That the Combined Authority: 1. Approved the six Cluster Action Plans developed to accelerate growth across West Yo... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies