13d. (3) Bus Highway Hotspot Improvements Programme (BSHHIP)

Approved Committee

West Yorkshire Combined Authority approved this item on Thursday 14 March 2024. Below is the council's own wording, with the papers it was decided on.

Item25

Resolved

That, subject to the conditions set by the Portfolio Investment Panel, the Combined Authority approved: i. Development costs of £252,000 were approved in order to progress the schemes to approval to proceed, the total scheme approvals being £592,000. The £252,000 was comprised of £232,000 from the City of Bradford Metropolitan District Council and £20,000 from Wakefield Council. ii. The Combined Authority enter into an addendum to the existing funding agreements for expenditure as listed above. iii. The Bus Highway Hotspot Improvement Programme proceed through decision point 2 (strategic outline case) and work commences on decision point 5 (delivery) of individual schemes. iv. Approval of £1,743,359, taking the total Combined Authority approval to £2,083,359 with indicative allocations for each scheme as below. The total scheme value is £2,083,359. Expenditure up to the following was authorised; £1,287,004 from the City of Bradford Metropolitan District Council, £350,899 from Leeds City Council and £357,357 from Wakefield Metropolitan District Council. v. The Combined Authority enter into addendums to the existing funding agreements for expenditure as listed above. vi. That a Delegation to the Executive Director for Transport be approved to allow allocated funding amounts released as part of this decision to be amended as required and for grant funding agreements or addendums to grant funding agreements to be amended accordingly. vii. That future approvals would be made in accordance with the assurance pathway and approval route and tolerances outlined in the report. Where required, any future committee level approvals were delegated to the Transport Committee. That, subject to the conditions set by the Portfolio Investment Panel, the Combined Authority approved: (i) Development costs of £252,000 were approved in order to progress the schemes to approval to proceed, the total scheme approvals being £592,000. The £252,000 was comprised of £232,000 from the City of Bradford Metropolitan District Council and £20,000 from Wakefield Council. (ii) The Combined Authority enter into an addendum to the existing funding agreements for expenditure as listed above. (iii) The Bus Highway Hotspot Improvement Programme proceed through decision point 2 (strategic outline case) and work commences on decision point 5 (delivery) of individual schemes. (iv) Approval of £1,743,359, taking the total Combined Authority approval to £2,083,359 with indicative allocations for each scheme as below. The total scheme value is £2,083,359. Expenditure up to the following was authorised; £1,287,004 from the City of Bradford Metropolitan District Council, £350,899 from Leeds City Council and £357,357 from Wakefield Metropolitan District Council. (v) The Combined Authority enter into addendums to the existing funding agreements for expenditure as listed above. (vi) That a Delegation to the Executive Director for Transport be approved to allow allocated funding amounts released as part of this decision to be amended as required and for grant funding agreements or addendums to grant funding agreements to be amended accordingly. (vii) That future approvals would be made in accordance with the assurance pathway and approval route and tolerances outlined in the report. Where required, any future committee level approvals were delegated to the Transport Committee.
Word for word from the decision West Yorkshire Combined Authority published for this meeting. Source: westyorkshire.moderngov.co.uk

Follow this further

Built from West Yorkshire Combined Authority's papers

Papers for this item

Kept in our archive, download once signed in

No papers were published with this item. The decision above is the council's full record of it.

At this meeting

Whole meeting
4Exempt Information - Possible Exclusion of the Press and PublicDecided 5Minutes of the Meeting of the Combined Authority held on 1 February 2024Approved 6Bus ReformNoted 7West Yorkshire Mass Transit: Outcomes from the first Strategic Outline Case in advance of submission to the DfT and subsequent consultation and engagement activitiesNoted 8Better Homes HubNoted 9West Yorkshire Housing Strategy 2040Decided 10Rail StrategyNoted 11Local Transport PlanApproved 12Economic StrategyNoted 13Working towards a Child First Approach in the Combined AuthorityDecided 14Project Approvals - 13a, 13b, 13c, 13d, 13eOn the agenda 1513a Investment Zone Programme Approvals - Investment Priority 3 - Creating Great Places and Accelerated InfrastructureOn the agenda 1613a (1) Enterprise West YorkshireApproved 1713a (2). West Yorkshire HealthTech and Digital Tech Investment Zone programmeApproved 1813b Local Nature Recovery Strategy Project Approvals - Investment Priority 3 - Creating Great Places and AcceleratedApproved 1913c Better Homes Hub Project Approvals - Investment Priority 4 - Tackling the Climate Emergency and EnvironmentalOn the agenda 2013c (1) Better Homes Hub (BHH) Area-Based Scheme (Leeds - Part 1)Approved 2113c (2) Better Homes HubApproved 2213d Project Approvals - Investment Priority 5 - Delivering Sustainable, Integrated, Inclusive and Affordable TransportOn the agenda 2313d. (1) Transport Committee DelegationApproved 2413d. (2) BCPC Kings Road Sustainable Transport CorridorApproved
2513d. (3) Bus Highway Hotspot Improvements Programme (BSHHIP)This decision
2613d. (4) Huddersfield Rail Station ConnectionsApproved 2713d. (5) TCF Dewsbury - Batley - Chidswell Sustainable Travel CorridorApproved 2813d (6). Harrogate Railway Station Gateway - Active Travel Improvement SchemeApproved 2913d (7). TCF: Skipton Railway Station Gateway - Active Travel Improvement SchemeApproved 3013d (8). TCF Selby Station GatewayApproved 3113d (9). Kirklees Speed Limit ReviewApproved 3213d (10). A58/A672 Corridor Improvement SchemeApproved 3313d (11). Zero Emission Bus Regional Area (ZEBRA)Approved 3413d (12). Active Travel Fund and Capability Fund Programme - Active Travel Fund 4 Extension and Capability Fund ExtensionApproved 3513e Project Approvals - Investment Priority 6 - Creative Industries, Culture, Heritage and SportOn the agenda 3613e (1). West Yorkshire Tourism - Local Visitor Economy Partnership (LVEP)Approved 3713e (2). Bradford 2025 UK City of CultureApproved 3813e (3). British Library NorthApproved 39Scrutiny Protocol ReviewAgreed 40Corporate Plan 2024-25Decided 41Corporate DelegationsDecided 42Minutes for InformationOn the agenda

More from West Yorkshire Combined Authority West Yorkshire Combined Authority

All decisions
MeetingDecisionOutcome
18 Sep 2025 Bus Franchising Update– That the Combined Authority: 1. Noted and endorsed the strategic approach to developing network service specificati... Noted Open
18 Sep 2025 Mass Transit Programme– That the Combined Authority: 1. Noted progress and the current position of the West Yorkshire Mass Transit programm... Noted Open
18 Sep 2025 West Yorkshire Local Nature Recovery Strategy– That the Combined Authority: 1. Noted the engagement and strategy development work undertaken in collaboration with... Noted Open
18 Sep 2025 West Yorkshire Local Remediation Acceleration Plan– That the Combined Authority: 1. Adopted the West Yorkshire Local Remediation Acceleration Plan as set out in Append... Approved Open
18 Sep 2025 Cluster Action Plans– That the Combined Authority: 1. Approved the six Cluster Action Plans developed to accelerate growth across West Yo... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies