Audit Recommendation Follow Up

Noted Finance 1 paper

AI summaryWest Yorkshire Combined Authority's Governance & Audit Committee acknowledged outstanding audit action updates. The report highlights overdue and at risk recommendations and records no direct financial impact.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedRatings show overdue, revised, at risk and on track actions.
MoneyNot stated
What happens nextRefine follow up reportingRecommendation and risk updates need greater clarity.
Who it affectsAudit recommendation deliveryOverdue and at risk actions need effective interim management.

What was decided

The Governance & Audit Committee acknowledged updates on outstanding audit actions. Report 2.1

Why

The revised follow up process uses colour coding to show overdue recommendations, revised dates or delivery risk, and recommendations on track. Report 3.1

Management updates need to show progress clearly and address each recommendation and its risks. Report P6

The report highlights delayed delivery and whether interim action manages risk effectively. Report 4.1

What happens next

Internal Audit Team will continue implementing the revised follow up process and refine it further. Report 3.1, P6

Management should provide clearer updates on specific recommendations and delivery risks. Report P6

Actions that take longer than appropriate need effective interim risk management. Report 4.1

Options considered

  • Chosen: Note updates on outstanding audit actions Report 2.1

Implications

  • Risk: The report identifies risk where recommendations take longer to deliver than appropriate, including whether interim action manages risk effectively. Report 4.1
  • Financial: The report has no direct financial implications. Report 8.1
  • Legal: The report has no direct legal implications. Report 9.1
  • Equalities: The report has no direct equity and diversity implications. Report P13
  • Climate: The report has no direct climate emergency implications. Report P9
  • Other: The report has no direct inclusive growth implications. Report P11

Who and where

  • Management responsible for progressing actions and providing clearer updates Report 3.1, P6
  • Internal Audit Team responsible for monitoring and reporting follow up Report 3.1, P6
  • Governance & Audit Committee receiving updates and assurance on progress Report 2.1, P6

Timeline

  • 2026-01-30: The committee acknowledged updates on outstanding audit actions. Report 2.1
  • At the last Committee meeting: The need for faster responses and clearer management updates was raised. Report P6

Plain English for the jargon

  • RAB rating: Red is overdue. Amber means a revised date or delivery risk. Blue is on track.
  • Follow up process: The process for tracking audit recommendation progress, delays and delivery risk.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item7

Resolved

– That the Committee: Noted the updates on outstanding audit actions. – That the Committee: Noted the updates on outstanding audit actions.
Word for word from the decision West Yorkshire Combined Authority published for this meeting. Source: westyorkshire.moderngov.co.uk

Follow this further

Built from West Yorkshire Combined Authority's papers

What the report saysPro

Report to Governance & Audit Committee, 2 pages

Recommendations

2.1That the Committee notes the updates on outstanding audit actions.

3. Information

Process

Reporting on recommendation follow up

3.1Internal Audit Team have continued to implement the revised follow up process and as per discussion at the last Committee meeting, the report format RAB rating has been revised to show where recommendations are overdue (red), where a revised date has been agreed and/or there is a view from the auditor that there may be a risk to delivery (amber) and where actions have not yet reached the due date and management and Internal Audit agree that they are on track to meet the due date (blue).

Timeliness of follow up responses 3.2 At the last Committee meeting, the Internal Audit Team raised the issue of response times and the need for clearer updates from management to give a better indication of where progress is positive. There have been improvements to reporting, but this is still embedding and the process is still being refined to try and streamline further. It would be particularly helpful to see updates that clearly address the specific recommendation and risks to give the required level of assurance on progress.

4. Risks and Mitigations

4.1The risks arising from this report relate to those actions where recommendations are taking longer to deliver than is appropriate and whether sufficient action is being taken in the interim to manage that risk as effectively as possible.

5. Tackling the Climate Emergency Implications

5.1There are no climate emergency implications directly arising from this report.

6. Inclusive Growth Implications

6.1There are no inclusive growth implications directly arising from this report.

7. Equity and Diversity Implications

7.1There are no equity and diversity implications directly arising from this report.

Financial implications

8.1There are no financial implications directly arising from this report.

9.1There are no legal implications directly arising from this report.

10. External Consultees

10.1No external consultations have been undertaken in the preparation of this report.

11. Background Documents

11.1There are no background documents referenced in this report.

Appendices

Appendix 1 – Recommendation Follow Up Update Report

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Audit Recommendation Follow UpReport 2 pages DownloadRead as text

At this meeting

Whole meeting

More from West Yorkshire Combined Authority Governance & Audit Committee

All decisions
MeetingDecisionOutcome
30 Jan 2026 Exempt Information - Possible Exclusion of the Press and Public– That the Committee: Exclude the public from the meeting during consideration of Agenda Item 9 – Risk Management (Ap... Decided Open
30 Jan 2026 Minutes of the Meeting of the Governance and Audit Committee held on 24 October 2025– That the Committee: Agreed that the minutes of the Governance and Audit Committee meeting held on 24 October 2025 b... Agreed Open
30 Jan 2026 Internal Audit Progress Update– That the Committee: Noted the progress update contained in the submitted report. – That the Committee: Noted the pr... Noted Open
30 Jan 2026 Internal Audit Strategy and Charter– That the Committee: Approved the Internal Audit Strategy. Approved the Internal Audit Charter. – That the Committee... Approved Open
30 Jan 2026 External Audit Report– That the Committee: Noted the update from Forvis Mazars. – That the Committee: Noted the update from Forvis Mazars. Noted Open