What the committee will consider, in order, with every paper attached to its item.
To receive declarations by Members and Officers of the existence and nature of any pecuniary interests or any other significant interest in matters on this agenda.
To approve the minutes of the meeting held on 29 February 2024. : The Chair, with the consent of the Members present, agreed that the minutes of the meeting held on 29 February 2024 were a true and accurate record of proceedings.
To approve the development of a Stage 3 (detailed) design for the Oxford Street project.
Decision: Cabinet approved the option to p roceed to Stage 3 design on the basis set out in the report in the knowledge that the remaining funding is yet to be formally confirmed. Cabinet also approved spend of £3.845m to progress the Stage 3 design. Reasons for The Stage 2 design for Oxford Street is complete and the finalisation of design is required in advance of pre-mobilisation and construction. A decision is required on how to progress the Oxford Street project. Implementation Date: 5pm 22/7/24 Decision page
To approve the next steps for the place-based North Paddington Programme, including the indicative Years 2-4 programme of works and delegated authority to the Executive Director for Regeneration, Economy and Planning to initiate and deliver projects.
Decision: Cabinet approved: Spend of the remaining North Paddington budget, subject to further feasibility and project scoping (where required), to fund the Years’ 2-4 indicative programme of works, as detailed in Appendix 1 (“Years’ 2-4 Programme of Works”). The Years’ 2-4 indicative programme of Works (Appendix 1) and notes that some of the indicative Years’ 2-4 programme of works’ projects will, enter a feasibility and pilot stage, if required, before moving to full delivery (subject to due... Decision page
To approve the implementation of a hybrid delivery model for Housing Solutions Services.
Decision: Cabinet approved: The implementation of a hybrid delivery model for Housing Solutions Services. To bring in-house Lot 1: Frontline housing advice and homelessness prevention and Lot 3: Families Pathway, Housing Assessment, Allocations and Nominations Services, to be directly delivered by the Council by April 2025. To insource back-office functions currently commissioned to support Housing Solutions including, a contact centre, complaint management, and finance functions, to sit within existing... Decision page
To approve Neighbourhood CIL funding to support the transformation of Seymour Leisure Centre; and the restoration of the Abbey Centre.
Decision: Cabinet approved: The allocation of £1 million of Neighbourhood CIL funding from the Marylebone Neighbourhood Area pot to the Council to support the transformation of Seymour Leisure Centre. The allocation of £424,435 of Neighbourhood CIL to support the restoration of the Abbey Centre. Reasons for There is a need for Neighbourhood CIL funding to supplement the project’s capital budget, driven by rising costs from build cost inflation and from changes to the project that reflect community... Decision page
To note the overall performance of the Council, and progress as at year-end (2023/24) towards the Fairer Westminster Strategy ambitions, as well as priority actions for 2024/25 set out in the recently published 2024/25 Delivery Plan.
To note the revised medium term financial planning forecast to 2027/28 and to agree the budget process approach as set out in the report.
Decision: Cabinet noted the Medium Term Financial Planning 2025/26 – 2027/28 report and approved the budget process for the year ahead. Implementation date: 15/7/2024 Decision page
To note the revenue outturn position for 2023/24, and approves the reprofiling from the 2023/24 capital programme into future years.
Decision: Cabinet noted the revenue outturn position for 2023/24 and approved the reprofiling from the 2023/24 capital programme into future years as set out in Appendix 1 (GF) and Appendix 2 (HRA). Reasons for This is an annual reporting setting out an updated position on the Council’s budget. Implementation Date: 15/7/24 Decision page
All 22 papers in one list, with the item each belongs to, its size, and our copy of it. Download any paper from our archive once signed in; read and search it here with Pro.
Every Cabinet meeting we have read, the dates it has set for the future, and each time those dates have changed.
Choose what you want to hear about. The preview is built from this committee's real papers and changes, so you can see what would have reached you.
Westminster, Cabinet
One alert, sent weekly, on titles and decisions.
Unlimited alerts the same day, searching every page.
Your team, with every match pushed into your own tools.
Every council's records in your own products and research.
Papers, decisions and date changes for the Cabinet, and every other committee you follow, the day they appear.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.