Resolved
The Committee:- (1) notes the revenue and capital budget monitoring position for quarter 1 and the potential impact upon the general fund balances; (2) notes the ... view the full minutes text for item 23.
Overview and Scrutiny Co-ordinating Committee (re named) decided this item on Monday 16 August 2010. Below is the council's own wording, with the papers it was decided on.
Resolved
The Committee:- (1) notes the revenue and capital budget monitoring position for quarter 1 and the potential impact upon the general fund balances; (2) notes the ... view the full minutes text for item 23.
Budget Monitoring APPENDIX 1
1. Revenue Monitoring
The following paragraphs provide more details of the position at quarter 1.
Building Stronger Communities Scrutiny Committee Significant Variations
Environmental Services Department Neighbourhoods Division
The first quarter of the year produced an underspend on the Community Risk Initiative Township allocation of £0.015m, however this does not include the underspends carried forward from previous years of £0.129m and as such a significant amount of money remains to be committed by each individual ward.
Economy, Environment, Culture & Housing Scrutiny Committee Significant Variations
Environmental Services Department Neighbourhoods Division
The final phase of the roll out of the kerbside dry recyclable collection has been completed in stages from April to June resulting in an underspend in collection costs of £0.093m. However expenditure of £0.322m has been incurred to purchase the requisite bins to complete the roll out. The Council’s medium term forecast contains a provision to purchase these bins out of balances rather than create a specific general fund budget. If formal approval is given to trial the kerbside collection of paper and cardboard via a blue bin, then it is projected that with the purchase of these receptacles the year end call on balances will be £0.500m.
This additional expenditure has been counterbalanced to some degree by the impact of the additional kerbside recycling and operational improvements at the civic amenity sites producing an underspend on the disposal of civic amenity waste of £0.138m. Historically the annual contract uplift on the waste contract is agreed in September, the budget assumes a 1% uplift and a commitment has been included in the figures to reflect this 1% increase. Given that the calculated uplift could be higher and the fact that monthly waste streams can be volatile, a year end saving of £0.100m is currently projected.
Environmental Services Department Regeneration & Protection Division
The management of vacant posts has produced savings on salary costs of £0.041m within the division, and a favourable variance of £0.175m has been projected for year end. This will need to absorb budgetary pressures elsewhere within the department. An under recovery of income on rentals and utilities has resulted in an adverse variation of £0.044m on Markets. Although measures are in place to control expenditure, given the economic climate it is projected that the year end variance will be £0.150m.
Environmental Services Development Division
The first three months of the year has seen an under recovery of planning application fees of £0.116m and building regulation fees of £0.056m due to the current economic climate. Whilst the volume of planning applications has fallen slightly the main issue is that the value of the applications is significantly lower than previous. An adverse variation of £0.450m is projected by the financial year end.
Increased expenditure on metered water, contract costs and a reduction in fine income has resulted in an adverse variation on Car Parks of £0.060m. Whilst the re-tendering of the car park contract may bring savings within the second half of the financial year this will only be factored in once realised. As such given the expenditure and income pressures a year end adverse variation of £0.150m is currently projected.
Audit, Governance & Improvement Review Committee
The significant variations to the Council’s Corporate & Democratic Services, Chief Executive’s Department and Business Support Services Department budgets after three months activity are set out below:
Chief Executive’s Department
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Financial Monitoring Qtr1 reportAppAReport | 223 KB | DownloadRead as text |
PDF |
Financial Monitoring Quarter 1 2009/10:Report | 148 KB | Download |
Follow Overview and Scrutiny Co-ordinating Committee (re named) at Wigan and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 4 Apr 2011 | Forward Plan of Key DecisionsThe Committee did not request for any of the issues listed to be future Scrutiny Committee agenda items. | Decided | Open |
| 4 Apr 2011 | Review of the Overview and Scrutiny Function and ProceduresThe Committee (1) agrees to the proposed amendments to the constitution and terms of reference of the Co-ordinating C... | Agreed | Open |
| 4 Apr 2011 | Organisational Development strategy updateThe Committee: (1) notes the progress made in implementing the strategy; (2) agrees to receive regular reports on the... | Agreed | Open |
| 4 Apr 2011 | Customer Transformation Strategy updateThe Committee:- (1) notes the progress made in implementing the strategy; (2) requests the Customer and Compliance Ma... | Decided | Open |
| 4 Apr 2011 | Corporate Performance 2010/11 - Quarter 3 update.The Committee (1) notes the report; and (2) requests that the Head of Policy and Programmes consults accordingly with... | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.