The Forum (1) notes the stage 2 lottery application bid by Oaklands and Meadows Residents Association for the replacement of worn out equipment and upgrade to the tots park at Oaklands Road Play Park; (2) confirming that this supports the Play Strategy that the Forum has developed in partnership with Wigan Leisure & Culture Trust, writes a letter of support for the bid and (3) notes that Councillors J N Grundy and J Cowley will contribute an additional £800 from their Brighter Borough Fund to the cost of the installation of the living Christmas tree in Lowton .
Word for word from the decision Wigan published for this meeting.Source: democracy.wigan.gov.uk
Report to Golborne and Lowton Township Forum (expired)
Oaklands & Meadows 1st October 2010
THE OAKLANDS AND MEADOWS RESIDENTS ASSOCIATION
Oaklands Play park Stage 2 Lottery Bid Overview
The Oaklands Road Play Park has recently had new equipment installed as part of a Pathfinder play project; this was funded from Play England and was supplied through Wigan and Leisure Culture Trust. The Pathfinder play funding was specifically for 8-14 year old play, and the tots park (swings and slides) was left untouched by the renovations.
OMRA has been seeking for 18 months for a play facility for all ages and has recently applied for Lottery Grant Funding for the replacement of worn out equipment and upgrade to the tot’s park. We have recently been advised that we have successfully passed the stage 1 application process , and now much work is to be done to deliver a stage 2 bid in order to realise this fantastic opportunity. There are many stakeholders involved in a project such as this and all of these need to be consulted. The most important being the Parents ,Grand parents, and carers of under 8’s who are going to use the park facility, others being the Housing authority ( as landowner) WLCT (as maintainer and operator) The insurance requirements , RoSPA , Planning interfaces and Suppliers. There will also be an Authority who are overseeing the lottery bid and will be checking that we have complied with all the requirements and conditions. As this process is quite complicated, OMRA have broken the project down into five separate Phases (see sheet).
Each phase has a detailed programme so that OMRA can track and maintain its progress. There are deadlines for submissions of major documents and this has required OMRA to set its own deadlines; also if it is to be successful in this application. The success of this project depends on the determination of the OMRA volunteers, the support from the local authority departments many of whom have to provide letters or documents, and the involvement and engagement of the local residents in the planning of their own facility.
If you would like to get involved in some way, either as a committee member or to share your opinions in the consultations, we would like to hear from you. If you are reading this and know somebody with young children in the area please pass this on, the success of the new facility depends on people saying what they want to see and how they want it to be used.
If you would like to be kept up to date with the process as it progresses, please email us below.
For Further Information Call 0773 459 1187 Or Email [email removed] Oaklands & Meadows 1st October 2010
Phases of project and General Timescales. Phase A Checking we have permissions from all mandatory stakeholders Permissions Planning letters , Parks department letter of authority Landowners letters of authority , Insurance requirements, maintenance underwritten , support from local counsellors etc. It is also important that we have a completed list of all the stakeholders so that we may involve them in the consultation process at the correct time and in the correct capacity. We hope this will be complete by end of October. Contact us now if you want to be involved.
Phase B We will receive some assistance from the Lottery commission to Consultations develop consultations; We wish to involve the local people in as many ways as possible. Our initial intention is to send surveys out to local nurseries and schools up to Year 3 collect the data and respond to it with opportunities to develop it further later in the the year , WE hope to start this important stage of the process In October and complete this by Mid December.
Phase C OMRA will need time to prepare and write the bid document Bid Submission responding to all 109 points of order required by the Grant authority. We expect that we will need the involvement of some council departments during this period. Allowing our volunteers a short Christmas break, we expect to be able submit the Bid document for assessment at the end of January.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Golborne and Lowton Township Forum (expired) at Wigan and we tell you when its next papers are published, before the meeting rather than after it.
Exclusion of the Press and PublicThe public is excluded from the meeting when the Committee discusses the following item for the reasons set out below...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.