The Cabinet:- (1) approve the entering into a contractual relationship with the Heritage Lottery Fund and in doing so accepts the grant award offer of £1,972,000, the Wigan Leisure and Culture Trust / Council contribution of £634,000 and the risks associated with this project as presented in the summary risk register; (2) approves the inclusion of the project within the Capital Programme in line with the attached CPR1 and grant budget release; and (3) supports the proposal that any funding shortfall arising through Phases One and Two are met by ring fencing all or part of the proceeds from the sale or lease of property in the Council’s Leisure portfolio.
Word for word from the decision Wigan published for this meeting.Source: democracy.wigan.gov.uk
Element Risk Category Risk Description Risk Probability Risk Impact Mitigation actions
Cost engineering exercise underway to identify Unable to obtain a tender sum below the target tender omissions/specification changes to achieve the Conservation Package One Financial price Low High necessary savings prior to contract award
Contract contingency of £99,000 included in the contract equating to 6.8% of the contract value. At the first sign of incurring additional expense a cost engineering exercise will be undertaken to keep the Conservation Package One Financial Overspend during the contract period Low High contract within the contract sum.
Funding Group established to identify additional external funding towards the Training Centre. Review of WLCT sites proposed to identify sites for possible sale or long lease and the ring fencing of capital Phase One Cost and Funding Plan Financial Shortfall in match funding Medium High receipts to address any shortfall
The Training Centre, the only element of the Phase One project currently unfunded by way of match funding is to be delivered alongside the Lodge Restoration. The Project team have eleven months to identify the match funding shortfall of £150,000 through additional funding or the release of WLCT Inability to deliver all elements of the Phase One sites for long lease or sale and the ring fencing of Phase One HLF contract Reputation and Financial Project Medium High capital receipts.
Funding Group established to target additional external funding for elements within the Phase Two Project alongside a review of WLCT sites to identify possible sites for sale and the subsequent ring fencing of Phase Two Cost and Funding Plan Financial Unsecured Council match funding of £300,000 Medium High capital receipts towards the Council match funding
Launch and promotional plan developed to create and maintain awareness of the Sponsorship opportunities within a local and regional corporate network alongside Phase Two Cost and Funding Plan Financial Unsecured Sponsorship match funding of £100,000 Medium High a general public appeal.
Phase Two Cost and Funding Plan Financial Withdrawal of WLCT match funding Low High WLCT funding built into medium term financial plans Cost plans developed by Quantity Surveyors based on detailed surveys, architectural , structural and M+E proposals. A Project contingency of £155,000 is included within the Phase Two cost plan to address any unforeseen during the Design ,Procurement and Construction stages in addition to a 5% contingency allowance within the cost plans for the Phase Two Phase Two Contracts Financial Contract works are underestimated Low High elements.
Planning and Listed Building Consents have been secured for all elements of Phase One and Phase Two with the exception of the Training Centre extension. Planning and Conservation Officers are actively Unable to secure Statutory consents for the Lodge engaged in the Design process alongside an intention Phase Two Statutory Consents Statutory and Training Centre Low High to carry out Stakeholder consultation in early 2011
Delays in the Phase Two programme leading to additional scaffolding hire charges and reputational Detailed programme in place to direct the Project Phase Two Programme Programme issues with Project Stakeholders and partners Medium High design, procurement and construction stages
Strategies in place to address any shortfall in match funding plus contingency allowances within the Project cost plan to address any unforeseen expenses. At the first sign of incurring additional expenses a cost Inability to deliver all elements of the Phase Two engineering exercise will be undertaken to keep the Phase Two HLF contract Reputation and Financial project Low High contract within the contract sum.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.