Resolved
The Cabinet notes the contents of the report for monitoring purposes and the impact on balances.
Cabinet decided this item on Thursday 24 November 2011. Below is the council's own wording, with the papers it was decided on.
Resolved
The Cabinet notes the contents of the report for monitoring purposes and the impact on balances.
This is an open report
Report to: Cabinet
Date: 24 November 2011
Subject: Financial Monitoring Quarter 2
Report of: Director of Corporate Service - Resources
Contact officer: P McKevitt Ext 2235
Cabinet Portfolio Holder: G M Bretherton (Efficiency)
Purpose / summary: To report progress on budgets against spending to the end of September 2011.
Alternative options considered No alternatives to reporting. This is essential and reason for selecting the one best practice financial management recommended:
Recommendation / decision: To note the report and impact upon balances
Key Decision: This report does not involve a key decision. The decision made as a result of this report will be published within 48 hours and cannot be actioned until seven working days have elapsed, i.e. before 6 December 2011
Risks / Implications:
Financial: This report shows that at quarter 2 it is predicted that an underspend of £1.990m will occur by the end of the financial year when compared to the original budget. This will provide the necessary support to the Council’s balances.
The capital programme is forecasted to have a deficit of £1m to be met by re-programming expenditure to balance the programme. Further measures may be required to ensure the deficit is contained.
Staffing: None identified within the report Policy: Budget Framework Equal Opportunities - Has a A diversity impact assessment is not Diversity Impact Assessment necessary at this stage, however, equality and been conducted? diversity implications have been considered when producing this report. Wards affected: All
Summary of reasons for report being closed in the public interest:
Property Implications – Does the proposal involve a reduction, addition or change to the Council’s asset base or its occupation? No If yes, have the property implications been agreed with the Property Division?
Has the Head of Service, Legal and Risk (Monitoring Officer) (John Yes / Mitchell) confirmed that the recommendations within this report are lawful and comply with the Council’s Constitution? Has the Director Corporate Services (Paul McKevitt) confirmed that Yes / * any expenditure referred to within this report is consistent with the Council’s budget? Are any of the recommendations within this report contrary to the No * Policy Framework of the Council? * delete which applicable
For Cabinet reports only :
Categorisation of the report: x x
Key Decision Corporate Issues
Non-key Decision x Performance Monitoring x
Tracking/Process:
Consultation Ward Members Partners SMT 15 November Committee Overview & Scrutiny Cabinet Council 24 November
There are no Background Papers to this Report within the meaning of Section 100D of the Local Government Act 1972.
Proper Officer Paul McKevitt Date 3rd November 2011 1. Introduction
The report shows the summary position for both capital and revenue expenditure for the second quarter of 2011/12. It is more important than ever to ensure that close monitoring of these budgets is undertaken and scrutinised to identify at the earliest possible time any potential impact upon balances and deviation from the current year’s budget. The report shows the summary position to highlight to Members any major variances and to provide explanations for those variations.
2. Revenue Budget Position
The overall predicted position for the financial year 2011/12 is an underspend of £1.990m which is shown below (further details are provided in Appendix A) :
Variation compared to Original Estimate £m
People -0.093 Places 0.758 Resources -3.300 DSOs’ 0.230 Transfers to restructuring reserve 0.415 Total predicted Position (impact on balances) -1.990 NB: the underspend on resources includes £1m unbudgeted airport dividend and potential auto carry forward of Brighter Budget Initiative and the IT Investment account underspends of £1m.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Financial Monitoring Quarter 2 report:Report | 265 KB | DownloadRead as text |
Follow Cabinet at Wigan and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 24 Sep 2026 | Exclusion of the PublicThat the public is excluded from the meeting when the Cabinet discusses the following item for the reason set out bel... | Decided | Open |
| 24 Sep 2026 | Medium Term Financial Plan 2027/28 - 2029/30The Cabinet:- (1) notes the updated Medium-Term Financial Plan forecast; (2) notes the forecast budget gap for 2027/2... | Approved | Open |
| 24 Sep 2026 | Annual Standards Report 2025/26The Cabinet approves the . | Approved | Open |
| 24 Sep 2026 | Task and Finish (Cabinet Response) - CLA and PCLA Support in SchoolsThe Cabinet:- (1) notes the Director – Children and Family Services’ response to the Task and Finish Outcome Report; ... | Approved | Open |
| 27 Aug 2026 | Exclusion of the PublicThat the public is excluded from the meeting when the Cabinet discusses the following item for the reason set out bel... | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.