The Cabinet agrees:- (1) that the Phoenix Group submission is satisfactory and provides adequate public benefit to allow the pool to be transferred to them on 10 February 2013. (2) that the Officers of the Council and Wigan Leisure and Culture Trust (WLCT), continue to work with the Phoenix Group to ensure the criteria raised in the evaluation matrix are properly dealt with to ensure that the ... view the full minutes text for item 39.
Word for word from the decision Wigan published for this meeting.Source: democracy.wigan.gov.uk
Subject: An evaluation of the expression of interest exercise for Hindley swimming pool and to decide the future of the pool
Report of: Corporate Director (Places)
Contact officer: Penny McGinty, Head of Leisure and Culture
Cabinet Portfolio Holder: Councillor C Ready
Purpose / summary: Cabinet have been kept informed with regard to the provision of swimming pools across the Borough and the impact of local government funding pressures on this service. After carefully considering the evidence Cabinet approved to transfer Tyldesley pool to the Pelican Group from 1st April 2012 and agreed that Hindley pool can no longer be sustained beyond 30th December 2012 and its future will depend on whether a community group comes forward to take it over.
Following the Cabinet decision taken on 2nd August an advert was placed in the local newspaper inviting any groups interested in taking over Hindley pool from 1st January 2013 to submit an expression of interest by 28th September 2012.
Following the expression of interest exercise one submission was received from the Phoenix Group. This report will evaluate the expression of interest submitted by the Phoenix Group with a view to determining the future of the pool beyond 1st January 2013.
Alternative options considered Given that Cabinet recommended that this and reason for selecting the one work was undertaken and included in a future recommended: report to Cabinet the alternative option would be that this report was not produced. Without this report Cabinet will not be able to make a decision on the future of Hindley pool beyond 30th December 2012.
Recommendation / decision: The Cabinet is asked to agree:
That the Phoenix Group submission is satisfactory and provides adequate public benefit to allow the pool to be transferred to them on 10th February 2013. That Officers of the Council and WLCT continue to work with the Phoenix Group to ensure the criteria raised in the evaluation matrix are properly dealt with and ensure the hand over of the pool is as smooth as possible. That all the conditions requested by the Phoenix Group are complied with, with the exception of the one requesting for all priority repairs to be completed before hand over of the building. That the terms of The Local Government Act 1972: General Disposal Consent (England) 2003 are met and consent is given for the purposes of s.123 Local Government Act 1972, (having considered the advice set out at Appendix 6 and in particular the terms of the General Consent), to the transfer of Hindley Pool to the Phoenix Group. That authority be delegated to the Head of Assets Property and Procurement to negotiate the detailed terms of the lease of the Hindley Pool to the Phoenix Group on terms consistent with those set out in the report.
Key Decision: This report involves a key decision within ground(s) 2.
The decision made as a result of this report will be published within 48 hours and cannot be actioned until seven working days have elapsed, i.e. before 6 November 2012
In accordance with the General Exception rules - Regulation 10 of the – General Exception Local Authorities (Executive Arrangements) (Meetings and Access to Information) (England) Regulations 2012, the Chairman of the Corporate Places Scrutiny Committee has been informed that this item is a key decision and it has not been possible to give the requisite 28 clear days notice on the Forward Plan. The Chairman has confirmed that he supports the decision for Cabinet to consider this item.
Risks / Implications:
Financial: If the recommended option is agreed there will be full year savings to the Leisure Trust of the current running costs for Hindley pool, £97,000 and the to the Council. There will projected annual average landlord building maintenance and repair costs (based on the last 5 years) at £56,000 per annum.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.