Resolved
The Cabinet:- (1) accepts the revenue monitoring position for quarter 1 and the predicted position for the year; and (2) agrees the position on the capital programme and the proposed changes to the treasury management counterparty limits.
Cabinet agreed this item on Thursday 29 August 2013. Below is the council's own wording, with the papers it was decided on.
Resolved
The Cabinet:- (1) accepts the revenue monitoring position for quarter 1 and the predicted position for the year; and (2) agrees the position on the capital programme and the proposed changes to the treasury management counterparty limits.
THIS IS AN OPEN REPORT
Report to: Cabinet
Date of Meeting(s): 29 August 2013
Subject: Financial Monitoring Quarter 1
Report of: Deputy Chief Executive (Director – Resources & Contracts )
Contact Officer: Tony Clarke ext 2272
Cabinet Portfolio Holder Councillor T W Halliwell, Portfolio Holder Corporate and area: Resources \ Customer
Summary: To report progress on revenue and capital spend against budget to the end of June 2013 and to provide an update on the Treasury Management activities for the same period.
Link to Corporate Priorities: Confident Council Your Council has re-focused resources towards early intervention and prevention to achieve more for less.
Wards Affected: All
Recommendation(s): To consider the monitoring position for the first quarter together with the predicted position on the delivery of the budget for the year. To consider the position on the capital programme and to approve the proposed change to the treasury management counter party limits.
Implications: The report shows that at quarter 1 an overspend of What are the financial £0.384m is reported. However it is predicted that a implications? breakeven position will be reported at the year end. This will be achieved by utilising the transition reserve where necessary, Members will recall that the reserve provides the opportunity to provide the funding to meet any delays in the delivery of budget savings. The delivery of the savings contained within the 2013/14 budget are integral to the budget strategy adopted by the Council. Any non achievement will be detrimental to its future spending plans and the sustainability of Service Delivery
What are the staffing None identified within the report. implications?
Customer Impact Assessment The savings contained within the 2013/14 budget attached or not required because have been subject to Equality Impact Assessments (please give reason) as part of the 2013/14 budget process.
What are the property None implications in terms of reduction, addition or change to the council’s asset base or its occupation?
Risks: The non delivery of the 2013/14 savings will impact upon the future spending plans of the Council.
Has the Head of Service, Legal and Risk (Monitoring Yes Officer) (John Mitchell) confirmed that the recommendations within this report are lawful and comply with the Council’s Constitution?
Has the Director Resources and Contracts (Deputy Yes Chief Executive)(Paul McKevitt) confirmed that any expenditure referred to within this report is consistent with the Council’s budget?
Are any of the recommendations within this report No contrary to the Policy Framework of the Council?
What are the alternative No alternatives to reporting. This is essential option(s) to be considered? best practice financial management. Please give the reason(s) for recommendation(s):
Is this a Key Decision and, if The Non Key decision made as a result of this so, under which definition? report will be published within 48 hours and cannot be actioned until seven working days have elapsed, i.e. before 10 September 2013, unless exempt from call-in.
This item is included on the Forward Plan.
There are no background papers for this report
Directorate Sign-off: Paul McKevitt
Date: 9 August 2013 Please list any appendices:- Appendix number or Description letter 1 Revenue Budget Monitoring position quarter 1 2013/14 2 Capital Programme Summary First Review 3 Treasury Management First Quarter Review 1. Introduction
This report provides a high level position of the projected outturn for 2013/14 based upon the figures as at the first quarter. The revenue and capital monitoring position is discussed below with summary figures being provided in Appendix 1 and 2 respectively. The position on the Treasury Management activity for the quarter is provided in Appendix 3.
2. Revenue Position
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Financial Monitoring 2013/14: First Quarter ReviewReport | 251 KB | DownloadRead as text |
Follow Cabinet at Wigan and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 24 Sep 2026 | Exclusion of the PublicThat the public is excluded from the meeting when the Cabinet discusses the following item for the reason set out bel... | Decided | Open |
| 24 Sep 2026 | Medium Term Financial Plan 2027/28 - 2029/30The Cabinet:- (1) notes the updated Medium-Term Financial Plan forecast; (2) notes the forecast budget gap for 2027/2... | Approved | Open |
| 24 Sep 2026 | Annual Standards Report 2025/26The Cabinet approves the . | Approved | Open |
| 24 Sep 2026 | Task and Finish (Cabinet Response) - CLA and PCLA Support in SchoolsThe Cabinet:- (1) notes the Director – Children and Family Services’ response to the Task and Finish Outcome Report; ... | Approved | Open |
| 27 Aug 2026 | Exclusion of the PublicThat the public is excluded from the meeting when the Cabinet discusses the following item for the reason set out bel... | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.