THIS IS AN OPEN REPORT
Report to: Audit Governance and Improvement Review Committee
Date of Meeting(s): 26 September 2013
Subject: Statement of Accounts 2012/13
Report of: Director of Resources and Contracts (Deputy Chief Executive)
Contact Officer: Paul McKevitt
Cabinet Portfolio Holder Councillor T W Halliwell, Portfolio Holder for Corporate and area: Resources/Customer
Summary: To report to members a summary of the findings of the audit of the 2012/13 accounts. To ask members to formally approve the Statement of Accounts.
Link to Corporate Priorities: The Statement of Accounts is a document which portrays the use of financial resource in delivery all its services and so is linked to all of the Corporate Priorities
Confident Places Improving economic and social opportunities; An attractive, accessible and lively borough, with a prosperous economy as the location of choice for investment.
Confident People Protecting vulnerable groups, improving life opportunities and independence, making sure people feel safe and supported in their communities Helping people to stay healthy longer
Confident Council Your Council has re-focused resources towards early intervention and prevention to achieve more for less. Wards Affected: All Recommendation(s): To approve the audited Statement of Accounts for 2012/13
Implications: What are the financial implications? Ensure effective financial management and corporate governance arrangements. What are the staffing implications? None identified within the report
Customer Impact Assessment attached The savings target for 2012/13 has been or not required because (please give achieved. EIAs’ were completed as part of the reason) budget setting process .
What are the property implications in The Council’s corporate office accommodation terms of reduction, addition or change strategy forms part of the overall budget strategy to the council’s asset base or its and therefore reductions to the council’s asset occupation? base will be reflected in the overall underspend reported.
Risks: There is a statutory requirement that the accounts must be certified by 30 September 2013.
Has the Head of Service, Legal and Risk (Monitoring Officer) Yes (John Mitchell) confirmed that the recommendations within this report are lawful and comply with the Council’s Constitution?
Has the Director of Resources and Contracts (Deputy Chief Yes Executive) (Paul McKevitt) confirmed that any expenditure referred to within this report is consistent with the Council’s budget?
Are any of the recommendations within this report contrary to No the Policy Framework of the Council?
What are the alternative No alternative to reporting. This is essential best option(s) to be considered? practice financial management. Please give the reason(s) for recommendation(s):
Is this a Key Decision and, if so, The Non Key decision made as a result of this report under which definition? will be published within 48 hours and cannot be actioned until seven working days have elapsed, i.e. before 8 October 2013, unless exempt from call- in.
There are no background papers for this report
Directorate Sign-off: P McKevitt
Date: 18 September 2013 Please list any appendices:-
Appendix number or Description letter 1. Purpose of the Report
1.1This report provides Members with a summary of the findings of the Audit for the 2012/13 accounts. The Grant Thornton Audit Findings Report is attached and provides further details.
2. Statement of Accounts
2.1I am pleased to inform the Committee that the Audit of the 2012/13 accounts has identified no material misstatements, or items which have resulted in changes to the bottom line previously reported to this Committee in July.
3. Audit Findings
3.1No material or uncertainties have been identified in the financial statements. There were two non material errors which we are not required to amend relating to the Cashflow Statement and Plant, Property and Equipment Note. These are detailed in the Audit Findings Report.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
External Audit Opinion (2012/13 Accounts)Report | 131 KB | DownloadRead as text |
PDF |
Item 6 Wigan Council Audit Findings report: Local Government: 2012-13: Final (2)Report | 277 KB | Download |
Follow Audit and Governance Committee at Wigan and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 23 Mar 2017 | Exclusion of the PublicThe public is excluded from the meeting when the Committee discusses the following item for the reason set out below:... | Decided | Open |
| 23 Mar 2017 | ICT Contract Performance – UpdateThe Committee notes the presentation. | Decided | Open |
| 23 Mar 2017 | External Auditor Progress Report and UpdateThe Committee notes the report. | Decided | Open |
| 23 Mar 2017 | External Audit Plans for 2016/2017 AuditThe Committee notes the report and endorses the External Audit Plans for 2016/17. | Decided | Open |
| 23 Mar 2017 | Internal Audit Quality Assurance and Improvement ProgrammeThe Committee:- (1) notes the report; (2) approves the Internal Audit Section’s Quality Assurance and Improvement Pro... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.