Progress with Unity Scrutiny Committee, Monday 16 December 2013 at 6.00pm

New Ways of Working and Customer Transformation Programme

Decided Scrutiny 2 papers

Progress with Unity Scrutiny Committee decided this item on Monday 16 December 2013. Below is the council's own wording, with the papers it was decided on.

Item31

Resolved

Resolved ; The Committee (1) notes the report; and (2) thanks the officer for the presentation of the report
Word for word from the decision Wigan published for this meeting. Source: democracy.wigan.gov.uk

Follow this further

Built from Wigan's papers

What the report saysPro

Report to Progress with Unity Scrutiny Committee

THIS IS AN OPEN REPORT

Report to: Confident Council Scrutiny Committee

Date of Meeting(s):

Subject: Modernisation Programme: New Ways of Working and Customer Transformation.

Report of: Assistant Director Customer Services

Contact Officer: Natalie Dunn 01942 487358 or ext 87358

Cabinet Portfolio Holder Councillor Terry Halliwell, Portfolio Holder for Efficiency, and area: Resources Directorate

Summary: New Ways of Working and Customer Transformation is one of the four key themes within The Modernisation Programme. It represents a scaling up of our existing Customer Transformation Programme. A presentation will be provided to the committee to update on the achievements of the project to date and future key delivery dates.

Link to Corporate Priorities: Confident Council Your Council has re-focused resources towards early intervention and prevention to achieve more for less.

Wards Affected: Not Applicable.

Recommendation(s): Members of the Committee are invited to make comments and recommendations as appropriate in relation to the content of the report.

Implications:

What are the financial implications? The key aim of the board is to deliver greater value for money services that will contribute to the Council’s efficiency programme. The New Ways of Working and Customer Transformation Programme has been refreshed with an updated project plan and governance arrangements. What are the staffing implications? To be determined.

Customer Impact Assessment attached Not required- Individual Customer Impact or not required because (please give Assessments will be undertaken for elements of reason) the programme that are eligible.

What are the property implications in None. terms of reduction, addition or change to the council’s asset base or its occupation?

Risks: Risk: Failure to deliver the final Business Case Mitigation: Establishment of The Modernisation Programme Board with relevant governance and monitoring arrangements. Risk: Resistance from Services to change Mitigation: Regular meetings and communications with Services and Partners to be held to ensure Services are on board with all the proposed changes. Risk: Interdependencies across workstreams and programmes Mitigation: Importance of the Board, Ambassadors, SMT and members of the Project Team to create a culture of shared ownership, communication and support.

Has the Head of Service, Legal and Risk (Monitoring Officer) Yes (John Mitchell) confirmed that the recommendations within this report are lawful and comply with the Council’s Constitution?

Has the Director Corporate Services (Paul McKevitt) confirmed Yes that any expenditure referred to within this report is consistent with the Council’s budget?

Are any of the recommendations within this report contrary to No the Policy Framework of the Council?

List of Background Papers under Section 100D of the Local Government Act 1972:

There are no background papers for this report

Directorate Sign-off: Alison Mckenzie Folan

Date: 6 December 2013 1.0 Background and Proposals:

The New Ways of Working and Customer Transformation Programme forms part of the Councils Modernisation Programme and has been identified within Wigan Council Corporate Strategy as a key priority. The Modernisation Programme has four key workstreams:  Accommodation and Assets  New Ways of Working and Customer Transformation  Management Delayering and Employee Engagement  Service Specific Value Adding Efficiencies

The New Ways of Working and Customer Transformation Programme will enable the delivery of greater customer satisfaction, faster resolution at the first point of contact with Front and Back office whole system redesign removing duplication and non essential activity to release efficiencies and savings. The programme is driven by the values of the Council, particularly around Putting People First, Efficient and Business Like and One team, one council.

The vision of the programme is ‘Placing Customers at the heart of everything we do’.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
New Ways of Working and Customer Transformation Programme:Report 174 KB DownloadRead as text
PDF
New Ways of Working and Customer Transformation.ppt dec13Report 216 KB Download

At this meeting

Whole meeting

Who was there

10 of 21 attended
JM
Councillor James MoodieChairman, present
FB
Councillor Frederick Bown WalkerVice-Chair, present
PA
Councillor Paul Anthony CollinsCommittee Member, present as substitute
RJ
Councillor Ronald Josef ConwayCommittee Member, apologies
JL
Councillor James Luke CowleyCommittee Member, present
MD
Councillor Michael DewhurstCommittee Member, present
JD
Councillor John Donald HodgkinsonCommittee Member, present
SK
Councillor Stuart KeaneCommittee Member, present
PK
Councillor Phil KellyCommittee Member, present
MM
Councillor Marie MorganCommittee Member, apologies
SM
Councillor Stephen MurphyCommittee Member, apologies
JP
Councillor Jeanette PrescottCommittee Member, expected

All 21 on the meeting page

More from Wigan Progress with Unity Scrutiny Committee

All decisions
MeetingDecisionOutcome
6 Jul 2026 Whipping declarationsThere were no declarations. Decided Open
6 Jul 2026 Executive's Forward Plan of Key and Non-Key DecisionsThe Committee notes the forthcoming decisions, with no items being requested to be placed on a future agenda of the C... Decided Open
6 Jul 2026 Performance Monitoring UpdateThe Committee:- (1) thanks the Performance and Insight Manager for his report; and (2) notes the contents of the Perf... Decided Open
6 Jul 2026 Scrutiny Committee Workplan 2026-27The Committee:- (1) requests that an item regarding the lease agreement at the Three Sisters Racetrack be added to th... Agreed Open
6 Jul 2026 Task and Finish Topic Selection 2026-27The Committee:- (1) proposes ‘Employment Opportunities, Skills and Outcomes in the Borough’ as the topic for a Task a... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies