Resolved
The Committee:- (1) notes the report; and (2) requests that the Civil Contingencies and Business Continuity Planning Annual Report is brought to a future meeting of this Committee.
Audit and Governance Committee decided this item on Thursday 30 January 2014. Below is the council's own wording, with the papers it was decided on.
Resolved
The Committee:- (1) notes the report; and (2) requests that the Civil Contingencies and Business Continuity Planning Annual Report is brought to a future meeting of this Committee.
Corporate Risk Register Appendix 1
Ref Risk Area of Risk High Level Risk Specific Risk Identified Risk Consequences (if risk materialises) Evidence of Risk Management Actions/Controls Additional Action Required (Dec Category (Nov 2013) 2013)
CRisk1a Corporate Corporate Strategy Delivery Failure to deliver Key Delivery Financial Monitoring Quarter 2 Failure to achieve Council vision and values. Emerging issues and risks are set out in the revenue The revised report to support the Projects and the Council's This report concludes that this year's savings target of £18.8m will budget report presented to Council on 6th March Programmes will be developed. vision and objectives as be achieved. However there are still some issues around the 2013 and the quarterly budget monitoiring reports specified in the Corporate delivery of the savings within the Adults Service budget. presented to Cabinet. Strategy The current risk level of each of the key projects is reported in the monthly dashboard. Until April 2013, the dashboards were acompanied by a Programme RAG report which provided further detail on the risk ratings. The report was stopped due to the differing level of detail in it. A replacement is currently being worked on. CRisk2a Corporate Corporate Governance Qualification or adverse Failure to sustain Council performance levels due to budget cut Failure to achieve objectives, poor standards of The Audit Commission's Audit Findings Report was VFM being considered as part of the Compliance with statutory commentary within statutory requirements aligned to current lack of detailed external conduct and decision making, increased risk of presented to Audit, Governance and Improvement Corporate Modernisation financial and internal control accounts based on Ineffective assessment and reporting of overall (Rather than specific) losses through fraud or inefficiency, loss of Review Committee on 26th September 2013. It Programme. requirements (Accounts systems and management performance achievements. personal data, damage to reputation and morale, reported an unqualified audit opinion on the 2011/12 publication and AGS processes leads to potential Failure to demonstrate good value for money across all areas of loss of credibility, additional external audit fees. financial statements and an unqualified conclusion The Internal Audit Plan for 2013/2014 assessment). for corruption, exceeding Council spend. stating that the Council had adequate arrangements includes an overview of the Council's statutory powers Failure to meet the requirements of the future external audit code to secure economy, efficiency and effectiveness in VFM arrangements,in preparation for of practice may lead to additional costs and qualified opinion. the use of resources. However, this is a high level the future external audit code of assessment and there is no internal mechanism to practice to ensure that the Authority provide a corporate view on how well VFM is actually is best placed to demonstrate VFM achieved across all service areas. achievement, without incurring There is a Value for Money guide which is held on additional external audit costs. Share Point but there has been no evaluation of its usage.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Copy of Risk register corp Dec 13Report | 82 KB | DownloadRead as text |
PDF |
Mid Year Corporate Governance Review:Report | 319 KB | Download |
Follow Audit and Governance Committee at Wigan and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 23 Mar 2017 | Exclusion of the PublicThe public is excluded from the meeting when the Committee discusses the following item for the reason set out below:... | Decided | Open |
| 23 Mar 2017 | ICT Contract Performance – UpdateThe Committee notes the presentation. | Decided | Open |
| 23 Mar 2017 | External Auditor Progress Report and UpdateThe Committee notes the report. | Decided | Open |
| 23 Mar 2017 | External Audit Plans for 2016/2017 AuditThe Committee notes the report and endorses the External Audit Plans for 2016/17. | Decided | Open |
| 23 Mar 2017 | Internal Audit Quality Assurance and Improvement ProgrammeThe Committee:- (1) notes the report; (2) approves the Internal Audit Section’s Quality Assurance and Improvement Pro... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.