The Cabinet:- (1) notes the report for the third quarter and the impact upon general fund balances and reserves; (2) notes the position in relation to the capital programme; (3) accepts the Treasury Management position and thereby complies with the CIPFA Treasury Management Code of Practice; and (4) agrees that authority be delegated to the Director- Resources and Contracts (Deputy Chief Executive), in conjunction with the Executive Leader, to determine the funding of any necessary contributions towards the Local Highways Maintenance Challenge Fund.
Word for word from the decision Wigan published for this meeting.Source: democracy.wigan.gov.uk
Report to: Cabinet (and meeting with Confident Council Scrutiny Committee later in the day)
Date of Meeting(s): 19 February 2015
Subject: Financial Monitoring Quarter 3
Report of: Deputy Chief Executive (Director of Resources and Contracts)
Contact Officer: Tony Clarke ext 2272
Cabinet Portfolio Holder Councillor P R C Smith and area:
Summary: To report progress on revenue and capital spend as at the end of December and to update Members on the Treasury Management position for the same period. Link to Corporate Priorities: Confident Council Your Council has re-focused its reduced resources towards early intervention and prevention to achieve more for less – integrating public services around whole life issues to build self reliance and maximising community assets. Wards Affected: All
Recommendation(s): To consider the monitoring position for the third quarter together with the predicted position on the delivery of the budget and budget savings for the financial year. To consider the position on the capital programme. To note the Treasury Management activity for the period. Members are asked to note the report and delegate authority to the Deputy Chief Executive in conjunction with the Leader to determine the funding of any necessary contributions towards the Local Highways Maintenance Challenge Fund Implications: What are the financial implications? The report shows that at quarter 3 an overachievement of efficiencies of £0.517m is reported. However it is predicted that by the year end a break even position will be achieved by utilising the transition reserve. The capital programme (£99m) remains in balance. What are the staffing implications? None identified within the report. Equality Impact Assessment attached The savings identified within the 2014/15 budget or not required because (please give have been subject to equality impact reason) assessments as part of the 2014/15 budget process. What are the property implications in As part of the overall savings plans for 2014/15 terms of reduction, addition or change changes to the occupation and use of assets to the council’s asset base or its were planned. This is in line with the office occupation? accommodation strategy to rationalise the numbers of council buildings. Risks: The non delivery of savings will impact upon the future spending plans of the Council.
Has the Assistant Director - Legal (Monitoring Officer) Yes (Linda Fisher) confirmed that the recommendations within this report are lawful and comply with the Council’s Constitution?
Has the Deputy Chief Executive (Director Resources Yes and Contracts (Paul McKevitt) confirmed that any expenditure referred to within this report is consistent with the Council’s budget?
Are any of the recommendations within this report No contrary to the Policy Framework of the Council?
What are the alternative No alternatives to reporting. This is option(s) to be considered? essential best practice financial Please give the reason(s) for management. recommendation(s): Is this a Key Decision and, if The Non Key decision made as a result of so, under which definition? this report will be published within 48 hours and cannot be actioned until seven working days have elapsed, i.e. before 3 March 2015, unless exempt from call-in.
This item is included on the Forward Plan. There are no background papers for this report
Directorate Sign-off:
Date: Please list any appendices:-
Appendix number or Description letter 1 Revenue Monitoring Quarter 3 2 Capital Programme Third Review 3 Treasury Management Quarter 3 update 1. Introduction
The report shows the position on revenue and capital spend as at the end of December 2014. The revenue monitoring position is discussed in detail below. A summary is provided in Appendix 1. The capital programme summary is included in Appendix 2 and the Treasury Management update is included in Appendix 3.
2. Revenue Budget Position
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.