Appendix 1 Internal Audit Plan 2017/2018 – Progress As At 31ST August 2017
Auditable Area Planned / Priority Audit Audit Scope Audit Status Responsive Category Confident Council Governance Local Code of Corporate Planned Mandatory Assurance Annual Compliance Review Complete - reported to AG&S Governance Committee – June 2017
Half Yearly Compliance Review Not commenced Annual Governance Planned Mandatory Corporate Co-ordination and input to the drafting and Final Report – June 2017 Statement (AGS) agreement of the AGS Risk Management Planned Mandatory Corporate Ongoing maintenance and reporting of Strategic Update Report to AG&S and Departmental Risk Registers including Committee due September updating of risk management framework. 2017 Annual Fraud Return Planned High Compliance Completion of the CIPFA Fraud & Corruption Completed July 2017 Tracker Fraud Policies Planned Mandatory Advisory Review of Fraud Policies Complete - reported to AG&S Committee
Anti-Fraud, Bribery & Corruption Strategy August 2017 Review of the Anti-Money Laundering Policy September 2017
National Fraud Initiative Planned Mandatory Compliance Preparation of data extracts, fair processing In progress notices and investigations of data matches Total matches received 9924 Total matches processed 1873 In progress 377 Fraud proven 16 Customer or L/A Errors 12 Total overpayments £27,783 Auditable Area Planned / Priority Audit Audit Scope Audit Status Responsive Category Fraud Investigations Planned Mandatory Compliance Housing Benefit Ongoing Council Tax Reduction Blue Badge HB/CTR Right to Buy HB opmts raised £25,283 Direct Payments (2 cases await DWP Internal Fraud prosecution) CTR opmts raised £18,047 (4 formal cautions issued) CTR savings made £6,156
Blue Badges 52 cases investigates 50 were proven fraud. 3 prosecuted 4 formal cautions 43 warning letters.
HR based Investigations 1 complete – 1 in progress Corporate Stage 2 Planned Mandatory Non-Audit Investigation of formal Stage 2 complaints. Ongoing Complaints 42 complaints received 38 completed 3 upheld 10 partially upheld 25 not upheld
LGO referrals 5 complaints - 2 closed Corporate Strategy Planned High Corporate Corporate Strategy delivery and performance Not commenced reporting overview to include key projects and dashboard reports. Auditable Area Planned / Priority Audit Audit Scope Audit Status Responsive Category Value for Money Planned High Assurance Cost / Budget Reduction Programme Not commenced VFM Self Evaluation / Conclusion Public Sector Audit Revisions Troubled Families Planned Mandatory Compliance Grant validation In progress
Information Governance Planned High Advisory Attendance at GISWG and contributing to Ongoing information governance policies and advising on data breach actions. Participation in GDPR implementation group. Data Sharing Agreements Planned High Assurance Assessment of Council protocols and Not commenced associated verification of existence and validity of third party data sharing agreements. Business Continuity Planned High Advisory Review of corporate policy and associated Ongoing Management processes as a member of the BCM Steering Assurance Group and the ICT BC Review Board. . Undertaking a rolling programme to review Not commenced departmental BCM plans. Flood Grants Planned Mandatory Compliance Grant validation Draft Report
FOI and SAR Planned Mandatory Corporate Senior Officer Reviews as requested by the Ongoing Monitoring Officer. 3 reviews completed.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Enc. 1 for Internal Audit Progress ReportReport | 128 KB | DownloadRead as text |
PDF |
Enc. 2 for Internal Audit Progress ReportReport | 54 KB | Download |
PDF |
Enc. 3 for Internal Audit Progress ReportReport | 57 KB | Download |
PDF |
Internal Audit Progress ReportReport | 162 KB | Download |
Follow Audit, Governance and Standards Committee at Wigan and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 23 Jul 2026 | Exclusion of the PublicThe public is excluded from the meeting when the Committee discusses the following items for the reasons set out belo... | Decided | Open |
| 23 Jul 2026 | External Audit UpdateThe Committee:- (1) thanks the External Auditor for his update; and (2) notes the External Auditor’s update. | Decided | Open |
| 23 Jul 2026 | Treasury Management Annual Review 2025/26The Committee:- (1) thanks the officer for his report; and (2) endorses the Treasury Management position for 2025/26. | Decided | Open |
| 23 Jul 2026 | Draft Statement of AccountsThe Committee:- (1) thanks the Service Lead for his presentation; (2) notes the draft Statement of Accounts for 2025/... | Approved | Open |
| 23 Jul 2026 | Verbal Update on ComplaintsThe Committee:- (1) thanks the Strategic Lawyer – Corporate (Deputy Monitoring Officer) for his verbal update; and (2... | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.