THIS IS AN OPEN REPORT
Report to: Cabinet Council
Date of Meeting(s): 16 November 2017 10 January 2018
Subject: Financial Monitoring Quarter 2 and Treasury Management Mid year Review
Report of: Director - Resources and Contracts (Deputy Chief Executive)
Contact Officer: Tony Clarke
Cabinet Portfolio Holder Executive Leader Councillor P R C Smith M.Sc. (Lord and area: Smith of Leigh)
Summary: To report progress on revenue and capital spend at the end of September and to update Members on the Treasury Management mid year position for the same period.
Link to Corporate Priorities: Confident Council Your Council has re-focused its reduced resources towards early intervention and prevention to achieve more for less – integrating public services around whole life issues to build self-reliance and maximising community assets.
Wards Affected: All
Recommendation(s): The Cabinet are requested to agree to the following:-
(1) To consider the monitoring position for the second quarter with the predicted position on the delivery of the budget and budget savings for the financial year.
(2) To consider the position on the Capital Programme as detailed in Appendix 2. (3) To endorse the position on Treasury Management activity prior to its submission to Council. (as detailed in Appendix 3.)
The Cabinet are also asked to recommend to Council:
• To adopt the amended Capital Programme 2017/18 detailed in Appendix 2.
The Council is requested to adopt the revised Capital Programme 2017/18 detailed in Appendix 2
Implications:
What are the financial implications? The report shows that at quarter two the overall position is showing an adverse variation.
However it is predicted that by the year end a break even position will be achieved. The capital programme continues to remain in balance.
The level of cash balances provides the opportunity to repay debt which supports the revenue budget by reducing interest charges.
Is budget release necessary (Capital N/A Expenditure Only)?(if unsure please contact your Strategic Finance Manager)
What are the legal implications? The Council is required to set a balanced budget in accordance with the Local Government and Finance Act 1992.
What are the staffing implications? None identified within the report.
Equality and Diversity Impact The savings identified within the 2017/18 budget Assessment attached or not required have been subject to equality impact because (please give reason) assessments as part of the 2017/18 budget process.
What are the property implications in The work of the Corporate Property terms of reduction, addition or change Management Board to rationalise our asset base to the council’s asset base or its is a key component of our overall savings plans occupation? for 2017/18
Risks: The non-delivery of savings will impact upon the future spending plans of the Council. Changes in market conditions may cause fluctuations in interest rates which can impact upon the interest earned on our investments. Similarly borrowing rates are closely monitored as they could influence the timing of any future borrowing.
Sustainability N/A
Has the Assistant Director - Legal (Monitoring Officer) Yes (Brendan Whitworth) confirmed that the recommendations within this report are lawful and comply with the Council’s Constitution?
Has the Director Resources and Contracts (Deputy Chief Yes Executive)(Paul McKevitt) confirmed that any expenditure referred to within this report is consistent with the Council’s budget?
Are any of the recommendations within this report contrary to No the Policy Framework of the Council?
What are the alternative No alternative to reporting. This is seen as best option(s) to be considered? practice financial management. Please give the reason(s) for recommendation(s):
Is this a Key Decision and, if so, This report does not involve a key decision as under which definition? Council approval is required
This item is included on the Forward Plan.
There are no background papers for this report
Directorate Sign-off: P McKevitt
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Financial Monitoring Quarter 2Report | 307 KB | DownloadRead as text |
Follow Council at Wigan and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 23 Sep 2026 | Appointment of Honorary Aldermen of the BoroughThe Council:- (1) approves the recommendation of the Honorary Alderman Nominations Committee, to confer the title of ... | Approved | Open |
| 23 Sep 2026 | Appointment of Honorary Freeman of the BoroughThe Council agrees to hold a special meeting of the Council on an appropriate date during the 2026/27 municipal year,... | Agreed | Open |
| 23 Sep 2026 | Capital Programme Monitoring - Quarter 1The Council approves the adoption of the updated Capital Programme. | Approved | Open |
| 23 Sep 2026 | Anti-Social Behaviour PolicyThe Council:- (1) approves the refreshed (2026); (2) notes the introduction of the four step ASB Resolution Model and... | Approved | Open |
| 22 Jul 2026 | Appointment of the Monitoring OfficerThe Council notes the appointment of Nina Ellement into the Monitoring Officer role. | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.