That the Cabinet recommends the Council to:- (a) approve the £27.5 m of savings required as set out in the report; (b) a freeze (0%) on general Council Tax for 2018/19; (c) the raising of a 3% adults social care Council Tax rise as set out in the Chancellor’s Autumn statement; (d) approve the growth as set out in section 6; (e) approve the creation of a temporary reserve for the redistribution of Transport for Greater Manchester Reserves as set out in section 12.4 of the report; (f) approve the fees and charges as set out in Appendix 2; and (g) approve Wigan Council’s continued membership of the Greater Manchester Business Rates Pooling arrangement.
Word for word from the decision Wigan published for this meeting.Source: democracy.wigan.gov.uk
Date of Meeting(s): Thursday, 15 February 2018 Wednesday 7 March 2018
Subject: The Delivery of Efficiency 2018/19 - 2020/21
Report of: Director - Resources and Contracts (Deputy Chief Executive)
Contact Officer: Tony Clarke
Cabinet Portfolio Holder Councillor Peter Richard Charles Smith M.Sc. (Lord Smith and area: of Leigh)
Summary: The report provides Members with an update on the Council’s Budget following the provisional settlement announced by the Government in December.
The report will also make recommendations to Council on the 2018/19 Budget.
Link to Corporate Priorities: Confident Places Improving economic and social opportunities; An attractive, accessible and lively borough, with a prosperous economy as the location of choice for investment.
Confident People Protecting vulnerable groups and enhancing self-reliance, improving life opportunities and independence for everyone to start well, live well and age well; Particularly for those most dependent on public services.
Confident Council Your Council has re-focused its reduced resources towards early intervention and prevention to achieve more for less – integrating public services around whole life issues to build self-reliance and maximising community assets. Wards Affected: All
Recommendation(s): (1) The Cabinet is also asked to note the report and the position on Deal for the Future and recommend to Council:
The £27.5m of savings required as set out in the report A freeze (0%) of general council tax An increase of 3% Adult Social Care precept as set out in the Government’s financial settlement To approve the Growth as set out in section 6 To approve the creation of a temporary reserve for the redistribution of Transport for Greater Manchester Reserves as set out in 12.4. The revised fees and charges as set out in Appendix 2 Cabinet is also asked to approve Wigan Council’s continued membership of the Greater Manchester Business Rates Pooling arrangement.
(2) The Council is asked to agree the recommendations of the Cabinet
Implications:
What are the financial implications? There are a number of risks particularly towards the latter part of the plan, which, when combined with the continued uncertainty around the retention of Business Rates mean that the level of required savings for the duration of this forecast stand at £27.5m. Is budget release necessary (Capital No Expenditure Only)? (if unsure please contact your Strategic Finance Manager)
What are the legal implications? Legal issues will arise as a consequence of the content of the report and, in particular, as the Council continues to transform. These will be signposted by impact assessments.
What are the staffing implications? The savings will inevitably lead to changes in staffing numbers and how staff are organised. These will be assessed as plans develop as the Deal for the Future progresses. Any changes will be captured by impact assessments.
Equality and Diversity Impact The MTFP sets the envelope within which Assessment attached or not required individual decisions will arise and these will all because (please give reason) be covered by necessary impact assessments
What are the property implications in The Council’s property portfolio will be terms of reduction, addition or change continually reviewed as operational decisions to the council’s asset base or its are taken. occupation?
Risks: As the Council continues to transform its services it is essential that the required level of efficiencies is delivered. Without the drive to transform it is highly likely that the Council would not be able to deliver its services as its budget is reduced further. Therefore the longer term financial viability of the Council would be at risk.
Reducing budgets may increase the risk of service failure. These risks are to be mitigated by carrying out impact assessments and drawing up detailed operational plans for areas affected.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.