Resolved
The Committee:- (1) thanks the Officers for their report and presentation; and (2) endorses the recommendation to Cabinet to progress the next stage of the Parklife Project.
Progress with Unity Scrutiny Committee decided this item on Monday 13 August 2018. Below is the council's own wording, with the papers it was decided on.
Resolved
The Committee:- (1) thanks the Officers for their report and presentation; and (2) endorses the recommendation to Cabinet to progress the next stage of the Parklife Project.
THIS IS AN OPEN REPORT
Report to: Confident Council Scrutiny Committee Cabinet
Date of Meeting(s): Monday, 13 August 2018 Thursday, 30 August 2018
Subject: Parklife Football Hubs
Report of: Penny McGinty - Assistant Director, Corporate Contracts and Assets
Contact Officer: Karen Hewitt
Cabinet Portfolio Holder Councillor Nazia Rehman - Portfolio Holder Resources, and area: Finance and Transformation
Summary: This report updates on progress of the Parklife Football Hubs project, outlines the financial requirements for the 2nd stage of project development (detailed design and planning consent) and makes relevant recommendations to further progress the project and deliver its benefits.
Link to Corporate Priorities: Confident Places Improving economic and social opportunities; An attractive, accessible and lively borough, with a prosperous economy as the location of choice for investment.
Confident People Protecting vulnerable groups and enhancing self-reliance, improving life opportunities and independence for everyone to start well, live well and age well; Particularly for those most dependent on public services.
Confident Council Your Council has re-focused its reduced resources towards early intervention and prevention to achieve more for less – integrating public services around whole life issues to build self-reliance and maximising community assets. Wards Affected: All
Recommendation(s): The Scrutiny Committee is asked to:-
1. review the report and endorses the recommendation to Cabinet to progress the next stage of the Parklife project.
The Cabinet is asked to;-
2. endorse the next stages of the Parklife project and approve the Project Development Costs stage 2 (PDC2) funding request of £166,799.00
Implications:
What are the financial implications? The financial implications of the full Parklife project are as follows: 1. Project Development Costs stage 1 (PDC1) - £135,367.29 of which 60% (£81,220.37) was funded by Parklife and 40% (£54,146.92) was funded by the Council. 2. Project Development Costs stage 2 (PDC2) – £416,949.00 of which 60% (£250,169) will be funded by Parklife and 40% (£166,779) is to be funded by the Council. 3. Capital Investment of an estimated £17M. 60% of the overall Capital investment will be funded by Parklife; the remaining 40% is required to be funded by the Council, and it is intended this will be by prudential borrowing. This will result in an increased level of savings required across the council. 4. Operational savings – there will be immediate operational savings for the Council at the 3 Parklife sites 5. Removal of annual subsidy – the Council is currently running at an annual subsidy of £210K on playing fields. The Parklife model will remove this subsidy by immediate operational savings at the 3 Parklife hub sites; then reviewing the PPS and prioritising sites to be retained and those which could be released for Community asset Transfers and/or disposal. 6. Reinvestment into remaining council playing fields – the Parklife model demands a percentage of profits to be ring-fenced by the operator of the 3 Parklife hubs, to be reinvested across the remaining council playing fields to improve grass roots sport.
Is budget release necessary (Capital Yes Expenditure Only)?
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Parklife Football HubsReport | 214 KB | DownloadRead as text |
Follow Progress with Unity Scrutiny Committee at Wigan and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 6 Jul 2026 | Whipping declarationsThere were no declarations. | Decided | Open |
| 6 Jul 2026 | Executive's Forward Plan of Key and Non-Key DecisionsThe Committee notes the forthcoming decisions, with no items being requested to be placed on a future agenda of the C... | Decided | Open |
| 6 Jul 2026 | Performance Monitoring UpdateThe Committee:- (1) thanks the Performance and Insight Manager for his report; and (2) notes the contents of the Perf... | Decided | Open |
| 6 Jul 2026 | Scrutiny Committee Workplan 2026-27The Committee:- (1) requests that an item regarding the lease agreement at the Three Sisters Racetrack be added to th... | Agreed | Open |
| 6 Jul 2026 | Task and Finish Topic Selection 2026-27The Committee:- (1) proposes ‘Employment Opportunities, Skills and Outcomes in the Borough’ as the topic for a Task a... | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.