Resolved
It was agreed:- (1) to note the quarter 1 performance for 2018/19; and (2) approve the 2018/19 management fee of £47,375 payable to the Council for employee time supporting the Company.
Wigan and Leigh Homes Board agreed this item on Tuesday 18 September 2018. Below is the council's own wording, with the papers it was decided on.
Resolved
It was agreed:- (1) to note the quarter 1 performance for 2018/19; and (2) approve the 2018/19 management fee of £47,375 payable to the Council for employee time supporting the Company.
Wigan & Leigh Homes Board 18 September 2018
Quarter 1 Performance Monitoring 2018/19
Report of the Assistant Director – Homes
Authors: Catriona Rafferty and Julie Preston
[email protected] Tel No: (01942) 486521
[email protected] Tel No: (01942) 489383
Purpose To present the quarter 1 performance for the WALH owned properties and agree the management fee for the Council supporting the company.
Recommendations Board to: Note the quarter 1 performance for 2018/19 Approve the 2018/19 management fee of £47,375 payable to the Council for employee time supporting the company.
For decision or information? Decision
For the open or press and public Open excluded part of the agenda?
Key Risks: The Board are responsible for the Company’s financial position. Failure to monitor income and expenditure through the year could lead to a position of the company having insufficient funds to continue to trade. Impact on Tenants/Customers: All of the indicators impact on our customers in some way.
Resource Implications – Value This report deals with the current financial position of for Money, Employee, the Company, but in itself has no financial implications. Environmental: Social Responsibility None directly from this report. Implications:
Equality and Diversity None directly from this report. Implications: 1.0 Quarter 1 Performance
1.1Appendix 1 provides the detailed first quarter performance position. Performance overall is generally good.
1.2Rent Arrears: Current arrears at the end of quarter 1 were £7,648. The assumed amount of Housing Benefit pending at the 1st of July was £546, leaving arrears of £7,102. At year end 2017/18 arrears stood at £4,870. This means that arrears have increased by £2,232 in the first quarter. At the present time 3 tenancies have arrears in excess of 7 weeks after deducting the housing benefit due. This compares to 2 tenancies at year end 2017/18.
The rent arrears performance for WALH owned properties has been set out in comparison to the Council owned properties. In terms of arrears as a % of the debit, for WALH properties the figure is 5.99% compared to 7.47% for Council properties. The proportion of WALH tenants in arrears is 22.5% (18 tenants) compared to 41.3% of Council tenants in arrears.
1.3Terminations and Voids: There were no terminations in Quarter 1 and there are no void properties, therefore no void rent loss.
1.4Tenancy and Estate Management: There have been no tenancy breaches during the first quarter.
1.5Repairs & Servicing: At the end of quarter 1 all 80 WALH properties had a valid Landlord’s Gas Safety Certificate.
2.0Impact of Welfare Reforms
2.1Current data indicates that there are 6 WALH tenancies which are affected by the under-occupation charge. This is the same as at the end of March 2018. There are 3 WALH tenants who are currently claiming Universal Credit.
3.0Quarter 1 2018/19 Income and Expenditure on Company Owned Properties
3.1The table below summarises the receipts and payments for the period between 1st April and 30th June 2018 for properties owned by Wigan and Leigh Homes. This shows that over this period income exceeded expenditure by £0.1m. However, it is important to note that there are significant items of expenditure such as the loan interest repayments, depreciation and corporation tax which will only be incurred at the end of the financial year. 2018/19 2018/19 2018/19 Under (-) / Full Budget Description Actual to overspend % Year to 30th 30th June (+) Budget June
Expenditure £’000 £’000 £’000 £’000
Repairs 73 18 13 -6 -33% Cleaning 12 3 0 -3 -100% Electricity 5 1 0 -1 -100% Water 0 0 0 0 0% Sub-Total Running Costs 90 23 13 -10 -43%
Other Costs
Corporation Tax 50 0 0 0 0.0% Accountants Fees 5 0 0 0 0.0% Bad Debt Provision 9 0 0 0 0.0% Loan Interest Repayments 140 0 0 0 0.0% Depreciation 135 0 0 0 0.0% Management Fee 47 0 0 0 0.0% Sub-total Other Costs 386 0 0 0 0.0%
Total Expenditure 476 23 13 -10 -43%
Income
Rents -476 -119 -113 6 5% Total Income -476 -119 -113 6 5%
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Quarter 1 Performance Monitoring 2018/19Report | 88 KB | DownloadRead as text |
PDF |
Quarter 1 Performance Monitoring 201819 AppendixAppendix | 77 KB | Download |
Follow Wigan and Leigh Homes Board at Wigan and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 9 Sep 2019 | Annual Self AssessmentsIt was agreed: (1) To note the outcome of the self-assessments against the Regulator of Social Housing’s National Sta... | Agreed | Open |
| 9 Sep 2019 | Collection of Rent ArrearsIt was agreed to note the report. | Agreed | Open |
| 9 Sep 2019 | Audited Accounts for the year ending March 2019It was agreed:- (1) to thank the Strategic Finance Manager and his team for their involvement in the preparation of t... | Agreed | Open |
| 9 Sep 2019 | Q1 Performance ReportIt was agreed:- (1) to note the quarter 1 performance for 2019/20; and (2) approve the management fee of £47,375 paya... | Agreed | Open |
| 9 Sep 2019 | Company Update (verbal)The Cabinet:- (1) approves the transfer of the said properties, currently within Wigan and Leigh Homes Limited owners... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.