The Cabinet:- (1) agrees that funding be drawn down so that the schemes can be developed; and (2) supports the submission of a business case to confirm the funding for delivery of projects, included in the prioritised scheme budget, to achieve the outcomes outlined above.
Word for word from the decision Wigan published for this meeting.Source: democracy.wigan.gov.uk
Wigan Council (“Council”) Our ref : W1-T4-001 Wigan New Town Hall, W1-T5-001 Library Street, Your ref: Wigan, WN1 1YN
Date:
Dear Sirs
Re: Reimbursement of development costs incurred by the Council in connection with The Mayor’s Cycling & Walking Challenge Fund (“Scheme”)
1. We refer to the project being developed by the Council for the purposes of (amongst other things) improving cycling and walking infrastructure within the boundary of the Council (“Project”). Details of the Project can be found at Schedule 1.
2. We note that:
2.1the Project is to be funded by grant monies made available from the Greater Manchester Combined Authority (“GMCA”) for the Scheme ("Grant");
2.2the Project has been approved by the Cycling & Walking Commissioner’s Team, being the team set up to deliver and oversee the Scheme on behalf of the GMCA;
2.3the Council intends to enter into a grant funding agreement with TfGM in order to provide the required funding from the Grant to deliver the Project (“Grant Agreement”), subject to full approval of the Project;
2.4the Council has incurred costs in the form of preliminary development, planning and feasibility costs for the Project, as more particularly described in Schedule 1 (“Development Costs”); and
2.5to the extent that the Project involves supplementing and/or enhancing existing alternately funded infrastructure (such as an existing Growth Deal scheme), Development Costs may only be claimed in relation to the cycling and walking aspects of the Project that are the proposed to be funded by the Scheme.
Transport for Greater Manchester is an executive body of the Greater Manchester Combined Authority 3. Subject to the requirements of paragraphs 4 to 6 of this letter, and in consideration of the Council having already incurred Development Costs in relation to the Project, then upon receipt of valid invoices and/or other appropriate evidence as may be agreed with TfGM relating to the Development Costs from the Council, TfGM shall procure the payment of these Costs to the Council, by way of an advanced payment of the Grant.
4. Any payments of the Grant in accordance with paragraph 3 above shall only be made to the extent that the Development Costs represent costs properly and reasonably incurred by the Council in delivering the Project, and the Council agrees to provide all such documents and further supporting documentation as TfGM may reasonably require to verify the amount of the Development Costs.
5. Upon payment of any Development Costs, an amount equal to these Development Costs shall be deducted from the maximum amount of grant monies to be made available to the Council under the Grant Agreement, post full approval of the Scheme.
6. The Council shall keep TfGM indemnified in full against all reasonably and properly incurred costs and expenses, damages and losses (except indirect losses), including any interest, fines, legal and other professional fees and expenses awarded against or incurred by TfGM to the extent that such costs and expenses, damages and losses are attributable to any acts or omissions of the Council, its employees, agents or subcontractors in relation to the Project, except to the extent that such claims, liabilities, damages, demands or expenses arise out of any negligence, act or the default or omission of TfGM.
7. The aggregate liability of TfGM under or in connection with the terms of this letter shall not exceed an amount equal to the Development Costs properly and reasonably incurred by the Council in delivering the Project.
8. We should be grateful if you would acknowledge your acceptance of the terms of this letter by signing and returning the enclosed copy of this letter, as provided below.
9. This letter may be signed in any number of counterparts, each of which when signed is an original, but all the counterparts together shall constitute the same document.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.