Resolved
The recommends the Council to note the monitoring position and predicted position on the delivery of the budget.
Cabinet noted this item on Thursday 18 February 2021. Below is the council's own wording, with the papers it was decided on.
Resolved
The recommends the Council to note the monitoring position and predicted position on the delivery of the budget.
Recommendation(s): The Cabinet is requested to consider and endorse 1. The monitoring position for the 3rd quarter with the predicted position on the budget.
Implications:
What are the financial implications? The report shows that at quarter three the overall position is showing an adverse variation. However, the application of COVID-19 Government grant and contributions from our Health partners will ensure a balanced position at year end.
Is budget release necessary (Capital Expenditure Only)? N/A
What are the legal implications? The Council is required to set a balance budget in accordance with the Local Government and Finance Act 1992
What are the staffing implications? None identified within this report
Equality and Diversity Impact Assessment attached or not required because (please give reason). If not required, then a relevance check needs to be completed. An equality impact assessment is not required at this stage.
What are the property implications in terms of reduction, addition or change to the council’s asset base or its occupation? N/A
Risks: Whilst it is envisaged that Government Support will cover the shortfall in 20/21, the quantum of adverse variations at the end of the financial year remains unknown. However due to our current financial position in terms of having a balanced budget at the beginning of 2020/21 it is felt that there will be sufficient cover in the short term to address this risk.
Sustainability/Environmental implications: The Council is deemed to be a Going Concern, which means that it is to continue to operate for the foreseeable future. As part of this assessment I have considered our financial performance including factors on historical, current and future performance.
Has the Assistant Director - Legal (Monitoring Officer) (Brendan Whitworth) confirmed that the recommendations within this report are lawful and comply with the Council’s Constitution?
Yes Has the Director Resources and Contracts (Deputy Chief Executive)(Paul McKevitt) confirmed that any expenditure referred to within this report is consistent with the Council’s budget?
Yes
Are any of the recommendations within this report contrary to the Policy Framework of the Council?
No
What are the alternative option(s) to be considered? Please give the reason(s) for recommendation(s): No alternative to reporting
Is this a Key Decision and, if so, under which definition?
The Non Key decision made as a result of this report will be published within two working days and cannot be actioned until five working days have elapsed, i.e. before 1 December 2020, unless exempt from call-in.
This item is included on the Forward Plan.
There are no background papers for this report.
Directorate Sign-off: P McKevitt Date: 8 February 2021
Please list any appendices:
Appendix number or letter Description
Appendix 1 Revenue Monitoring Appendix 2 Treasury Management Update Background
1. Introduction
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Financial Monitoring Quarter 3Report | 513 KB | DownloadRead as text |
Follow Cabinet at Wigan and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 24 Sep 2026 | Exclusion of the PublicThat the public is excluded from the meeting when the Cabinet discusses the following item for the reason set out bel... | Decided | Open |
| 24 Sep 2026 | Medium Term Financial Plan 2027/28 - 2029/30The Cabinet:- (1) notes the updated Medium-Term Financial Plan forecast; (2) notes the forecast budget gap for 2027/2... | Approved | Open |
| 24 Sep 2026 | Annual Standards Report 2025/26The Cabinet approves the . | Approved | Open |
| 24 Sep 2026 | Task and Finish (Cabinet Response) - CLA and PCLA Support in SchoolsThe Cabinet:- (1) notes the Director – Children and Family Services’ response to the Task and Finish Outcome Report; ... | Approved | Open |
| 27 Aug 2026 | Exclusion of the PublicThat the public is excluded from the meeting when the Cabinet discusses the following item for the reason set out bel... | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.