- The Cabinet approves:- (1) that officers progress with the statutory process at Stage 1 and publish a statutory proposal for consultation; (2) that agreement is given to utilise the vacant site of the former Our Lady of the Rosary RC School off Heath Lane, Leigh to rebuild the school; and (3) that agreement is given to utilise up to £4,000,000 of capital funding to fund the local authority’s contribution to the project, including budget release.
Word for word from the decision Wigan published for this meeting.Source: democracy.wigan.gov.uk
Subject: Rebuild and relocation of Rowan Tree Primary Special School
Report of: Cath Pealing, Assistant Director - Education
Contact Officer: David Clegg (01942 486026), Darren Thomas-Stanley ([phone removed]), Charmaine Tarring ([phone removed])
Cabinet Portfolio Holder and area: Councillor Jenny Bullen, Portfolio Holder for Children and Families
Summary: This report is to seek permission to follow the statutory process to relocate and rebuild Rowan Tree Primary School, as part of the Department for Education’s (DfE) schools rebuilding programme and agree the release of the necessary land and capital funding to complete the project.
Link to Corporate Priorities:
Our People: Together we feel happy, safe, included and look out for each other:
• Best start in life for children and young people • Happy healthy people • Communities that care for each other
Our Future: Together we will build a future where everyone has the opportunity to thrive:
• Economic growth that benefits everyone • A well-connected place • Confidently digital • A home for all
Wards Affected: Whilst the sites involved are in Atherton North and Leigh West, the children attending the school come from across the borough.
Recommendation(s): The Cabinet is recommended to approve:–
(1) that officers progress with the statutory process at Stage 1 and publish a statutory proposal for consultation; (2) that agreement is given to utilise the vacant site of the former Our Lady of the Rosary RC School off Heath Lane, Leigh to rebuild the school; and (3) that agreement is given to utilise up to £4,000,000 of capital funding to fund the local authority’s contribution to the project, including budget release.
Implications:
What are the financial implications? Up to £4,000,000 subject to the cost of the final proposal. Funding will be basic need from the primary places line on the capital programme and High Needs Capital Programme Allocation funding from existing resources.
Is budget release necessary (Capital Expenditure Only)? Yes.
What are the legal implications? If we do nothing, it is likely that we will be unable to meet our statutory duty to provide suitable and safe educational places for children with special educational needs and disabilities.
What are the staffing implications? There are no known implications for staff at this stage.
Equality and Diversity Impact Assessment attached or not required because (please give reason). If not required, then a relevance check needs to be completed. Not required. All views will be captured via the wide-and-far-reaching formal consultation carried out at Stage 2 of the statutory process as outlined in this report. Relevance Check is attached.
What are the property implications in terms of reduction, addition or change to the council’s asset base or its occupation? The new building will represent an addition to the council’s asset base. The school’s current site at Green Hall Close, Atherton will be retained.
Permission is sought to utilise the vacant site of the former Our Lady of the Rosary RC School off Heath Lane, Leigh to rebuild the school.
What are the Corporate Parenting Implications? There are currently two children who are looked after by Wigan Council attending Rowan Tree Primary School. 21% of Children Looked After by Wigan Local Authority have an Education Health and Care Plan with a number of these children requiring specialist provision, increased capacity at Rowan Tree will help support this cohort were their needs are assessed to require specialist provision in the borough.
Risks: The school’s main building is a timber framed building that has significantly exceeded its design life. The timber frame is starting to rot at the base and a number of timber columns are rotten. Monitoring is on-going and some temporary repairs have been carried out to ensure the existing building remains safe to occupy.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.