Resolved
The Cabinet:- (1) approves the inclusion of the rebuilding of Block 7, additional to the original proposal for the relocation of Hope School and the additional funding to cover the rebuild; (2) authorises budget release of the out-turn figures at the sum identified in the report; (3) delegates authority to the Director - Place to approve: a. tender acceptance, b. budget release; and c. authorise the use of the project contingency if required within the budget release figure; and (4) authorises the Assistant Director – Legal Governance and Elections to complete the necessary agreements to give effect to the above.