Wigan Town Centre Regeneration - Construction Section 1 and 2a

Approved Executive

Cabinet approved this item on Thursday 20 February 2025. Below is the council's own wording, with the papers it was decided on.

Item80

Resolved

The Cabinet approves:- (1) the maximum budget required for Section 1 of construction works for the Galleries redevelopment project as described in the report; (2) subject to the approval referred to in 5(i) below, entry into the Development Funding Agreement in respect of Section 1 works described within the report, in substantially the form attached to this report; (3) subject to the approval referred to in 5(i) below, entry into the Building Licence for Section 1, in substantially the form attached to this report for the purposes of carrying out the works described therein; (4) subject to the approval referred to in 5(i) below, entry into the Agreement for Lease for the New Market Hall (AFL) in substantially the form attached to this report; (5) delegated authority to the Director – Place (in consultation with the Executive Leader) to: (i) in accordance with the terms of the Development Agreement made between the Wigan Borough Council and Cityheart Limited dated 25 June 2021 (as varied), approve the form of call off documents for Section 1 and/or any necessary variations of the Galleries Building Contract Framework (ii) agree the final detailed terms of the documents referred to in 2, 3 and 4 above (ii) take all necessary steps to agree the terms of any agreements, documents and processes either in anticipation of or, ancillary or collateral to the Building Contract and the documents referred to at 2, 3 and 4 above to facilitate the delivery of the works described in the report, including but not limited to, any warranties, forms of appointment, performance security arrangements and the giving of any approvals; (6) the maximum budget required for Section 2a of construction works for the Galleries redevelopment project as described in the report; (7) delegation of authority to the Director – Place (in consultation with the Executive Leader) to: (i) agree and finalise the costs of the associated Development Funding Agreement for Section 2a in accordance with the financial envelope described in the report, (ii) in accordance with the terms of the Development Agreement made between the Wigan Borough Council and Cityheart Limited dated 25 June 2021 (as varied), call off documents for Section 2a and/or any necessary variations of the Galleries Building Contract Framework; (iii) take all necessary steps to agree the terms of any agreements (including but not limited to a Development Funding Agreement), documents and ... view the full minutes text for item 80.
Word for word from the decision Wigan published for this meeting. Source: democracy.wigan.gov.uk

Follow this further

Built from Wigan's papers

Papers for this item

Kept in our archive, download once signed in

No papers were published with this item. The decision above is the council's full record of it.

At this meeting

Whole meeting

Who was there

7 of 15 attended
DT
Councillor David Trevor Molyneux MBEExecutive Leader, present
KC
Councillor Keith CunliffeDeputy Leader, present
DA
Councillor Dane AndertonCommittee Member, present
JB
Councillor Jenny BullenCommittee Member, present
SG
Councillor Susan GamblesCommittee Member, present
PP
Councillor Paul PrescottCommittee Member, present
CR
Councillor Christopher ReadyCommittee Member, apologies
NR
Councillor Nazia RehmanCommittee Member, present
JD
Janet DaviesOfficer, in attendance
RG
Rachel GibbonsOfficer, in attendance
SJ
Sarah JohnstonOfficer, in attendance
JM
John McDonaldOfficer, in attendance

All 15 on the meeting page

On this subject at Wigan

Search all
  1. Wigan Town Centre Regeneration - Construction Section 1 and 2aThis decision
  2. Wigan Town Centre Regeneration Update - Section 2Approved
  3. Wigan Town Centre Regeneration – Construction Sections 2 and 3Approved
  4. Wigan Town Centre Strategic Development FrameworkApproved
  5. Wigan Town Centre Street Scene StrategyApproved
  6. Update on the Wigan North Township Forum priority - tackling coronary heart diseaseDecided

More from Wigan Cabinet

All decisions
MeetingDecisionOutcome
24 Sep 2026 Exclusion of the PublicThat the public is excluded from the meeting when the Cabinet discusses the following item for the reason set out bel... Decided Open
24 Sep 2026 Medium Term Financial Plan 2027/28 - 2029/30The Cabinet:- (1) notes the updated Medium-Term Financial Plan forecast; (2) notes the forecast budget gap for 2027/2... Approved Open
24 Sep 2026 Annual Standards Report 2025/26The Cabinet approves the . Approved Open
24 Sep 2026 Task and Finish (Cabinet Response) - CLA and PCLA Support in SchoolsThe Cabinet:- (1) notes the Director – Children and Family Services’ response to the Task and Finish Outcome Report; ... Approved Open
27 Aug 2026 Exclusion of the PublicThat the public is excluded from the meeting when the Cabinet discusses the following item for the reason set out bel... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies